Facts
BIADA allotted the petitioner an industrial plot in 2007, and a 90-year lease was executed in 2008.
Source reference: para. 2–4After the unit’s production was affected by financial difficulties, the allotment was cancelled in 2022.
Source reference: para. 2–4In an earlier writ proceeding, the cancellation orders were set aside on the basis of the petitioner’s undertaking to resume industrial activity, with BIADA permitted to retake possession if the undertaking was breached.
Source reference: para. 2–4, 19Following restoration of possession, BIADA inspected the premises in November 2023, found the unit non-functional, issued notice, and took possession on 5 December 2023.
Source reference: para. 5–6, 21The petitioner claimed that machinery repairs and other revival efforts were underway and challenged the repossession, including on natural-justice grounds.
Source reference: para. 7–8, 14–16Issues
1. Whether BIADA was entitled to retake possession after the petitioner failed to commence industrial activity in accordance with the undertaking accepted by the Court.
Source reference: para. 19–212. Whether BIADA’s action was invalid for failure to afford the petitioner a proper opportunity to be heard.
Source reference: para. 8, 24Law Applied
An undertaking furnished to and accepted by a court binds the party that gave it; where the court’s order expressly specifies the consequences of breach, the party cannot avoid those consequences merely by relying on difficulties encountered in compliance.
Source reference: no citationIn the earlier proceeding, the Court expressly permitted BIADA to resume possession if the petitioner failed to comply with the undertaking, and reserved liberty to BIADA to approach the Court.
Source reference: para. 19The Court also relied on the Division Bench decisions in M/s Yasraj Cycle Rickshaw Udyog v. State of Bihar & Ors., MJC No. 1547 of 2023, and Kavish Infrastructure Pvt. Ltd. v. Bihar Industrial Area Development Authority & Ors., MJC No. 1826 of 2023, for the principle that an undertaking given to the Court is binding and cannot subsequently be modified on the ground of compliance difficulties.
Source reference: para. 23No specific statutory provision is identified in the judgment.
Source reference: no citationReasoning
The petitioner had undertaken to commence industrial activity within specified periods, and the earlier order expressly authorized BIADA to retake possession upon breach.
Source reference: para. 19BIADA’s inspection found the unit locked and production not commenced; the petitioner’s assertion that machinery was present and that repairs or procurement were underway did not establish compliance with the undertaking to commence activity within the stipulated period.
Source reference: para. 21–22The Court further found that BIADA inspected the premises and issued notice before taking possession, and therefore rejected the natural-justice challenge.
Source reference: para. 24Holding
The Court held that the petitioner had failed to comply with the undertaking and that BIADA’s repossession was not unwarranted.
It dismissed the writ petition and disposed of any pending interlocutory applications.
Source reference: para. 25–27Original Court PDF
Rajesh Kumar SinhavsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
