Patna High Court
Administrative and Public LawCivil Procedure and Evidence

BIADA may resume possession when an allottee breaches a court-accepted undertaking to restart operations.

Rajesh Kumar Sinha vs The State of Bihar

Patna High CourtJUDGMENT: September 24, 20262 MIN READSOURCE JUDGMENT
BIADA may resume possession when an allottee breaches a court-accepted undertaking to restart operations.. Rajesh Kumar Sinha vs The State of Bihar. Patna High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

BIADA allotted the petitioner an industrial plot in 2007, and a 90-year lease was executed in 2008.

Source reference: para. 2–4

After the unit’s production was affected by financial difficulties, the allotment was cancelled in 2022.

Source reference: para. 2–4

In an earlier writ proceeding, the cancellation orders were set aside on the basis of the petitioner’s undertaking to resume industrial activity, with BIADA permitted to retake possession if the undertaking was breached.

Source reference: para. 2–4, 19

Following restoration of possession, BIADA inspected the premises in November 2023, found the unit non-functional, issued notice, and took possession on 5 December 2023.

Source reference: para. 5–6, 21

The petitioner claimed that machinery repairs and other revival efforts were underway and challenged the repossession, including on natural-justice grounds.

Source reference: para. 7–8, 14–16
02

Issues

1. Whether BIADA was entitled to retake possession after the petitioner failed to commence industrial activity in accordance with the undertaking accepted by the Court.

Source reference: para. 19–21

2. Whether BIADA’s action was invalid for failure to afford the petitioner a proper opportunity to be heard.

Source reference: para. 8, 24
03

Law Applied

An undertaking furnished to and accepted by a court binds the party that gave it; where the court’s order expressly specifies the consequences of breach, the party cannot avoid those consequences merely by relying on difficulties encountered in compliance.

Source reference: no citation

In the earlier proceeding, the Court expressly permitted BIADA to resume possession if the petitioner failed to comply with the undertaking, and reserved liberty to BIADA to approach the Court.

Source reference: para. 19

The Court also relied on the Division Bench decisions in M/s Yasraj Cycle Rickshaw Udyog v. State of Bihar & Ors., MJC No. 1547 of 2023, and Kavish Infrastructure Pvt. Ltd. v. Bihar Industrial Area Development Authority & Ors., MJC No. 1826 of 2023, for the principle that an undertaking given to the Court is binding and cannot subsequently be modified on the ground of compliance difficulties.

Source reference: para. 23

No specific statutory provision is identified in the judgment.

Source reference: no citation
04

Reasoning

The petitioner had undertaken to commence industrial activity within specified periods, and the earlier order expressly authorized BIADA to retake possession upon breach.

Source reference: para. 19

BIADA’s inspection found the unit locked and production not commenced; the petitioner’s assertion that machinery was present and that repairs or procurement were underway did not establish compliance with the undertaking to commence activity within the stipulated period.

Source reference: para. 21–22

The Court further found that BIADA inspected the premises and issued notice before taking possession, and therefore rejected the natural-justice challenge.

Source reference: para. 24
05

Holding

The Court held that the petitioner had failed to comply with the undertaking and that BIADA’s repossession was not unwarranted.

It dismissed the writ petition and disposed of any pending interlocutory applications.

Source reference: para. 25–27
Patna High Court

Original Court PDF

Rajesh Kumar SinhavsThe State of Bihar

Patna High Court · September 24, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment