APTEL
Administrative and Public LawContract Law

Biomass power tariffs can exceed bid-stage ceiling rates, APTEL rules, allowing yearly tariff determination based on actual costs minus bidder discount

Jind Bio-Energy LLP & Anr vs Haryana Power Purchase Centre & Anr

APTELJUDGMENT: September 09, 20264 MIN READSOURCE JUDGMENT
Biomass power tariffs can exceed bid-stage ceiling rates, APTEL rules, allowing yearly tariff determination based on actual costs minus bidder discount. Jind Bio-Energy LLP & Anr vs Haryana Power Purchase Centre & Anr. APTEL. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Haryana Renewable Energy Development Agency (“HREDA”) issued an RfP in August 2017 for setting up paddy-straw-based biomass power projects in Haryana.

Source reference: paras. 10–18; pp. 9–12

The RfP provided that bidders would offer discounts on the applicable generic tariff, described as the “ceiling tariff,” while the successful bidders would subsequently approach the Haryana Electricity Regulatory Commission (“HERC”) for tariff determination under Section 62 of the Electricity Act, 2003.

Source reference: paras. 10–18; pp. 9–12

Jind Bio-Energy LLP and Fatehabad Bio-Energy LLP were allotted 9.9 MW projects each after offering discounts in the bidding process.

Source reference: paras. 3, 18; pp. 6, 11

HPPC sought HERC’s approval to execute PPAs with the selected developers.

Source reference: paras. 20–21; p. 12

By order dated 3 January 2019, HERC approved the PPAs, subject to the tariff agreed by the developers not being revisited.

Source reference: paras. 20–21; p. 12

The parties thereafter executed PPAs dated 22 February 2019.

Source reference: paras. 23–24, 27; pp. 12–14

The PPAs defined “Tariff” as the tariff determined by HERC after applying the bidder’s discount, but added that it would remain “subject to” the 2017–18 ceiling tariff.

Source reference: paras. 23–24, 27; pp. 12–14

The developers challenged the application of the ceiling tariff as an absolute cap.

Source reference: paras. 21–25; pp. 12–14

HERC initially held that the ceiling tariff forming the basis of selection could not be exceeded in tariff determination.

Source reference: paras. 21–25; pp. 12–14

The developers filed Appeal No. 348 of 2019 before the Tribunal.

Source reference: paras. 21–25; pp. 12–14

Separately, HERC directed the parties to modify the PPAs because the executed definition of “Tariff” deviated from the definition approved in its order dated 3 January 2019.

Source reference: paras. 26–30, 53–60; pp. 14–15, 33–37

HPPC challenged that direction in Appeal No. 95 of 2022.

Source reference: paras. 26–30, 53–60; pp. 14–15, 33–37
02

Issues

1. Whether the ceiling tariff used as the basis for offering discounts in the RfP also operated as an absolute maximum cap on the tariff which HERC could determine under Section 62 of the Electricity Act, 2003?

Source reference: para. 31; p. 15

2. Whether the PPAs executed between HPPC and the developers were required to be modified because their definition of “Tariff” deviated from the draft PPA approved by HERC?

Source reference: paras. 53–60; pp. 33–37
03

Law Applied

The Tribunal applied Section 62 of the Electricity Act, 2003, under which the State Commission determines the tariff for electricity supplied by generating companies.

Source reference: paras. 34–41; pp. 16–24

The RfP clauses were construed to mean that the bidder’s discount, and not the bid-stage ceiling tariff, would apply to the tariff determined by HERC for the project.

Source reference: paras. 34–41; pp. 16–24

The Tribunal relied on the principle of contemporanea expositio, under which the interpretation placed on a document by the authority responsible for framing and implementing it is entitled to considerable persuasive weight, as recognised in Desh Bandhu Gupta & Co. v. Delhi Stock Exchange Association Ltd., (1979) 4 SCC 565.

Source reference: para. 45; pp. 26–28

It also applied the principle in Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corporation, (2016) 16 SCC 818, that the author of tender documents is ordinarily best placed to interpret them, absent perversity, mala fides, or legal error.

Source reference: para. 46; pp. 28–29

Further, a PPA executed after regulatory approval must conform to the Commission-approved draft, and material deviations may be directed to be corrected.

Source reference: paras. 58–60; pp. 35–37
04

Reasoning

The Tribunal read Clauses 1.6.1 and 1.6.2 of the RfP together.

Source reference: paras. 34–40; pp. 16–23

Clause 1.6.1 required bidders to offer discounts with reference to the applicable ceiling or generic tariff, while Clause 1.6.2 expressly required the successful bidders to seek project-specific tariff determination under Section 62, with the offered discount to be applied to the tariff fixed by HERC for the project throughout the PPA period.

Source reference: paras. 34–40; pp. 16–23

Accordingly, the ceiling tariff was relevant for evaluating and selecting bidders, but did not become an immutable upper limit on HERC’s subsequent tariff determination.

Source reference: paras. 34–40; pp. 16–23

HREDA’s own interpretation supported this construction, particularly because biomass fuel, transportation, labour, and other variable costs could change over time, making a fixed 2017–18 cap commercially unviable.

Source reference: paras. 42–50; pp. 24–31

The Tribunal therefore held that allowing tariff above the bid-stage ceiling did not rewrite the parties’ bargain but gave effect to the RfP and the statutory tariff-determination process.

Source reference: paras. 51–52; pp. 31–33

On the second issue, the Tribunal compared the executed PPAs with HERC’s approved draft.

Source reference: paras. 54–60; pp. 34–37

HERC had specifically directed that the tariff payable should be the year-to-year tariff determined with reference to the project’s COD, less the discount offered by the IPP.

Source reference: paras. 54–60; pp. 34–37

The executed PPAs, however, inserted an additional qualification making the tariff subject to the 2017–18 ceiling tariff.

Source reference: paras. 54–60; pp. 34–37

This was a deviation from the approved PPA, and the developers’ consent to the executed document could not validate a term inconsistent with the Commission’s approval.

Source reference: paras. 54–60; pp. 34–37
05

Holding

Appeal No. 348 of 2019 was allowed.

The Tribunal held that the ceiling tariff used for determining the bidders’ discounts was not an absolute cap on the tariff to be determined by HERC under Section 62.

Source reference: para. 52; pp. 32–33; para. 62; p. 38

HERC could determine the tariff on a year-to-year basis, and the determined tariff could exceed the bid-stage ceiling tariff, subject to application of the bidder’s discount.

Source reference: para. 52; pp. 32–33; para. 62; p. 38

Appeal No. 95 of 2022 was dismissed.

Source reference: paras. 60–62; pp. 37–38

The Tribunal upheld HERC’s direction requiring HPPC and the developers to modify the PPAs so that the definition of “Tariff” conformed to the Commission-approved draft PPA and reflected the year-to-year tariff determined by HERC less the applicable bidder discount.

Source reference: paras. 60–62; pp. 37–38
06

Acts & Sections Cited

2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Electricity Act, 20032

APTEL

Original Court PDF

Jind Bio-Energy LLP & AnrvsHaryana Power Purchase Centre & Anr

APTEL · September 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment