01Facts
The appellant, a registered contractor, was awarded a contract for the construction of an Elevated Service Reservoir (ESR) on March 6, 2023.
¶ 6On June 1, 2024, the top dome of the reservoir collapsed.
¶ 6The Department issued a show-cause notice on June 4, 2024, alleging negligence and poor quality of work, requiring an explanation within three days.
¶ 6Following multi-level internal enquiries and technical inputs from institutions like BIT Sindri and various IITs, the Chief Engineer passed a composite order on August 23, 2024, terminating the contract and blacklisting the appellant for five years.
¶ 7The appellant’s appeal to the Departmental Secretary and a subsequent writ petition and review before the High Court of Jharkhand were dismissed.
¶ 8-9The appellant challenged both the termination and the blacklisting before the Supreme Court.
02Issues
i.1. Whether the standards of judicial review for termination of a contract are distinct from those applicable to the blacklisting of a contractor.
¶ 2, 18ii.2. Whether the termination of the contract was substantiated by findings of negligence and compliance with due process.
¶ 3, 15iii.3. Whether the blacklisting order was legally sustainable in the absence of a specific show-cause notice proposing blacklisting and a lack of independent application of mind.
¶ 18, 2203Law Applied
Clause 59 of the General Conditions of Contract (GCC) governing termination for fundamental breach.
¶ 13Rule 10 of the Contractor Registration Rules, 2012, which mandates a prior show-cause notice before blacklisting.
¶ 14, 18The principle of audi alteram partem, emphasizing that blacklisting involves "civil consequences" and "casts a slur," necessitating a higher standard of natural justice as established in Erusian Equipment & Chemicals Ltd. v. State of West Bengal.
¶ 19Doctrine from UMC Technologies Pvt Ltd v. Food Corporation of India, requiring a show-cause notice to "specifically and unambiguously" mention the proposed penalty of blacklisting to be valid.
¶ 20Provisions in the judgment · 1
General Conditions of Contract Section 59
04Reasoning
The Court distinguished between termination and blacklisting, noting that while termination relates to past and subsisting contractual breaches, blacklisting is a "drastic step" that impacts future business prospects and carries a stigma.
¶ 18, 21Regarding termination, the Court found the order unimpeachable because findings of negligence were corroborated by multiple technical committees and the appellant had participated in hearings and appeals.
¶ 15Regarding blacklisting, the Court found the show-cause notice dated June 4, 2024, patently infirm as it failed to explicitly notify the appellant that blacklisting was being contemplated, thereby violating Rule 10.5 of the 2012 Rules.
¶ 22-23The Court observed that the Department failed to demonstrate an independent application of mind to show why blacklisting (a future-oriented penalty) was a necessary consequence beyond the immediate termination of the contract.
¶ 2205Holding
The Supreme Court upheld the order of termination, finding the evidence of negligence and the procedural fairness regarding the breach sufficient.
¶ 25The Court set aside the blacklisting order, declaring it illegal and arbitrary for want of a specific show-cause notice and lack of application of mind.
¶ 25Rather than remanding for a fresh notice, the Court "moulded the relief" due to the passage of time (1.5 years already served) and directed that the blacklisting shall cease to operate with immediate effect.
¶ 5, 24The appeals were partly allowed.
¶ 25Original Court PDF
M/S A. K. G. Construction And Developers Pvt. LtdvsState Of Jharkhand
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
