Supreme Court

Blacklisting requires a specific show-cause notice and cannot be a mechanical consequence of contract termination.

M/S A. K. G. Construction And Developers Pvt. Ltd vs State Of Jharkhand

Supreme CourtJUDGMENT: April 02, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellant, a registered contractor, was awarded a contract for the construction of an Elevated Service Reservoir (ESR) on March 6, 2023.

Source reference: para. 6

On June 1, 2024, the top dome of the reservoir collapsed.

Source reference: para. 6

The Department issued a show-cause notice on June 4, 2024, alleging negligence and poor quality of work, requiring an explanation within three days.

Source reference: para. 6

Following multi-level internal enquiries and technical inputs from institutions like BIT Sindri and various IITs, the Chief Engineer passed a composite order on August 23, 2024, terminating the contract and blacklisting the appellant for five years.

Source reference: para. 7

The appellant’s appeal to the Departmental Secretary and a subsequent writ petition and review before the High Court of Jharkhand were dismissed.

Source reference: paras. 8-9

The appellant challenged both the termination and the blacklisting before the Supreme Court.

Source reference: no citation
02

Issues

1. Whether the standards of judicial review for termination of a contract are distinct from those applicable to the blacklisting of a contractor.

Source reference: paras. 2, 18

2. Whether the termination of the contract was substantiated by findings of negligence and compliance with due process.

Source reference: paras. 3, 15

3. Whether the blacklisting order was legally sustainable in the absence of a specific show-cause notice proposing blacklisting and a lack of independent application of mind.

Source reference: paras. 18, 22
03

Law Applied

Clause 59 of the General Conditions of Contract (GCC) governing termination for fundamental breach.

Source reference: para. 13

Rule 10 of the Contractor Registration Rules, 2012, which mandates a prior show-cause notice before blacklisting.

Source reference: paras. 14, 18

The principle of audi alteram partem, emphasizing that blacklisting involves "civil consequences" and "casts a slur," necessitating a higher standard of natural justice as established in Erusian Equipment & Chemicals Ltd. v. State of West Bengal.

Source reference: para. 19

Doctrine from UMC Technologies Pvt Ltd v. Food Corporation of India, requiring a show-cause notice to "specifically and unambiguously" mention the proposed penalty of blacklisting to be valid.

Source reference: para. 20
04

Reasoning

The Court distinguished between termination and blacklisting, noting that while termination relates to past and subsisting contractual breaches, blacklisting is a "drastic step" that impacts future business prospects and carries a stigma.

Source reference: paras. 18, 21

Regarding termination, the Court found the order unimpeachable because findings of negligence were corroborated by multiple technical committees and the appellant had participated in hearings and appeals.

Source reference: para. 15

Regarding blacklisting, the Court found the show-cause notice dated June 4, 2024, patently infirm as it failed to explicitly notify the appellant that blacklisting was being contemplated, thereby violating Rule 10.5 of the 2012 Rules.

Source reference: paras. 22-23

The Court observed that the Department failed to demonstrate an independent application of mind to show why blacklisting (a future-oriented penalty) was a necessary consequence beyond the immediate termination of the contract.

Source reference: para. 22
05

Holding

The Supreme Court upheld the order of termination, finding the evidence of negligence and the procedural fairness regarding the breach sufficient.

The Court set aside the blacklisting order, declaring it illegal and arbitrary for want of a specific show-cause notice and lack of application of mind.

Source reference: para. 25

Rather than remanding for a fresh notice, the Court "moulded the relief" due to the passage of time (1.5 years already served) and directed that the blacklisting shall cease to operate with immediate effect.

Source reference: paras. 5, 24

The appeals were partly allowed.

Source reference: para. 25
Supreme Court

Original Court PDF

M/S A. K. G. Construction And Developers Pvt. LtdvsState Of Jharkhand

Supreme Court · April 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment