Facts
The petitioners were successful bidders for several water supply projects under the "Jal Jeevan Mission".
Source reference: p. 19, 25Following the execution of agreements and commencement of work, respondent authorities received verification from the Municipal Council, Karad, indicating that a technical experience certificate submitted by the petitioners (purportedly issued to Respondent No. 6, a joint venture partner) was fake.
Source reference: p. 25, 28Based on this, the respondents issued show-cause notices and subsequently passed a decision on 20.12.2024 to cancel the tenders and blacklist the petitioners for three years.
Source reference: p. 19, 21This decision was initially challenged and quashed by the High Court in an earlier round of litigation (WPC No. 1263/2025) due to pre-determination, with liberty granted to the State to take a fresh, unbiased decision.
Source reference: p. 20, 26Upon reconsideration in a meeting dated 02.12.2025, the Apex Committee maintained the cancellation of the contracts and the three-year blacklisting.
Source reference: p. 21, 27The petitioners challenged this fresh decision, claiming the certificates were genuine and they had completed substantial work (approx. 70%).
Source reference: p. 22-23Issues
1. Whether the respondent authorities were justified in terminating the contracts and initiating re-tendering at the risk and cost of the petitioners due to the submission of doubtful experience certificates.
Source reference: p. 38, para. 222. Whether the imposition of a three-year blacklisting was proportionate and legally sustainable in the absence of a conclusive finding of deliberate fraud or mens rea by the petitioners.
Source reference: p. 39, 40, para. 23-253. Whether the court should adjudicate contractual disputes regarding measurements and payments under Article 226.
Source reference: p. 42, para. 29Law Applied
The Court primarily applied the principles of administrative law regarding fairness and proportionality in government contracts.
Source reference: no citationIt relied on Gorkha Security Services v. Government (NCT of Delhi) (2014) 9 SCC 105, which establishes that blacklisting is equivalent to "civil death" and must be preceded by a specific show-cause notice and founded on clear culpability.
Source reference: p. 22, 41It relied on UMC Technologies Pvt. Ltd. v. Food Corporation of India (2021) 2 SCC 551, which establishes that blacklisting is equivalent to "civil death" and must be preceded by a specific show-cause notice and founded on clear culpability.
Source reference: p. 22, 41The Court also applied the doctrine that fraud or misrepresentation in securing a tender vitiates the contract at its inception, justifying termination.
Source reference: p. 30, 38Finally, the Court noted the limitation of writ jurisdiction under Article 226 of the Constitution of India in matters involving complex factual and contractual disputes where an alternative remedy (arbitration/civil suit) exists.
Source reference: p. 42Reasoning
The Court reasoned that while the respondents provided an opportunity for hearing, the decision-making process fell into two distinct categories: the termination of the contract and the act of blacklisting.
Source reference: p. 38, para. 21Regarding termination, the Court found that since the petitioners secured technical qualification based on a document the issuing authority denied issuing, the sanctity of the public procurement process was compromised, justifying the cancellation of the contract regardless of the petitioners' claims of bona fides.
Source reference: p. 38-39However, regarding blacklisting, the Court observed that the respondents failed to record a definitive finding of mens rea—specifically, whether the petitioners knowingly fabricated the document or merely relied on a defective one provided by a partner.
Source reference: p. 40, para. 24-25Applying the test of proportionality, the Court held that termination was sufficient to neutralize the unfair advantage, and blacklisting for three years without proved intentional fraud was excessive and disproportionate.
Source reference: p. 41, para. 25Holding
The Court partly allowed the writ petitions.
It upheld the respondents' right to annul the contracts and proceed with re-tendering at the petitioners' risk and cost due to the doubtful eligibility documents.
Source reference: p. 39, 42However, it quashed and set aside the order of blacklisting/debarring the petitioners for three years, finding it disproportionate and lacking a conclusive finding of deliberate fraud.
Source reference: p. 42, para. 28Regarding claims for balance payments and work valuation, the Court declined to interfere, granting the petitioners liberty to approach a Civil Court or invoke the arbitration mechanism provided in the agreement.
Source reference: p. 43, para. 29Original Court PDF
M/s A.K. Construction & Ors. v. State of Chhattisgarh & Ors. [2026:CGHC:10481-DB]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in