Facts
The petitioners were successful bidders for water supply projects under the Jal Jeevan Mission and executed agreements with the Public Health Engineering Department
Source reference: p. 19Following a verification process, the respondent authorities alleged that technical experience certificates submitted by the petitioners (purportedly issued by the Municipal Council, Karad) were fake
Source reference: p. 19, 25After an initial round of litigation where the High Court quashed pre-determined show-cause notices
Source reference: p. 20a fresh hearing was conducted by an Apex Committee on December 2, 2025
Source reference: p. 21The Committee resolved to terminate the petitioners' contracts, invite fresh tenders at their "risk and cost," and blacklist the firms for three years
Source reference: p. 21-22The petitioners challenged these decisions, asserting that the certificates were genuine and that substantial work (approx. 70%) had already been completed
Source reference: p. 23, 33Issues
1. Whether the termination of the contracts and the decision to re-tender at the petitioners' risk and cost were legally sustainable given the allegations of fraud
Source reference: p. 38 / para. 21-222. Whether the imposition of a three-year blacklisting period was proportionate and valid in the absence of a definitive finding of intentional fraud by the petitioners
Source reference: p. 39 / para. 23-253. Whether the High Court should adjudicate contractual disputes regarding payments and work measurements under Article 226
Source reference: p. 42 / para. 29Law Applied
The court primarily applied the principles of administrative law regarding fairness and proportionality in government contracts.
Source reference: no citationIt relied on Gorkha Security Services v. Government (NCT of Delhi) (2014) 9 SCC 105, which characterizes blacklisting as "civil death" requiring strict adherence to natural justice and reasoned decision-making
Source reference: p. 41 / para. 26It further applied UMC Technologies Pvt. Ltd. v. Food Corporation of India (2021) 2 SCC 551, which emphasizes that blacklisting must be based on a particularized show-cause notice due to its stigmatic nature
Source reference: p. 41 / para. 27The court also applied the doctrine that fraud vitiates the bidding process, justifying contract termination even if the work is ongoing
Source reference: p. 38 / para. 22Reasoning
The Court observed that the respondents afforded the petitioners an opportunity for a personal hearing, thus satisfying procedural natural justice
Source reference: p. 38 / para. 21On the merits of termination, the Court found that since the petitioners’ technical qualification was based on a certificate which the issuing authority (Municipal Council, Karad) denied issuing, the contract was voidable at the threshold; the employer was thus justified in neutralizing the advantage gained by misrepresentation
Source reference: p. 38-39 / para. 22However, regarding blacklisting, the Court noted that the Apex Committee failed to record a specific finding of mens rea or intentional forgery by the petitioners, who claimed they relied on a third party (Respondent No. 6)
Source reference: p. 40 / para. 24The Court reasoned that while termination was a protective measure for the tender's sanctity, a three-year debarment was a punitive measure that was disproportionate without a conclusive determination of deliberate fraud
Source reference: p. 40-41 / para. 25, 28Holding
The Court partly allowed the writ petitions
It upheld the termination of the contracts and the respondents' right to re-tender the work at the risk and cost of the petitioners
Source reference: p. 42 / para. 28However, it quashed and set aside the order blacklisting the petitioners for three years, holding it disproportionate in the absence of a definitive finding of conscious misrepresentation
Source reference: p. 41-42 / para. 25, 28Regarding claims for outstanding payments and work measurements, the Court declined to interfere under Article 226, granting the petitioners liberty to invoke the arbitration/dispute resolution mechanism provided in the agreement or approach a Civil Court
Source reference: p. 42-43 / para. 29Original Court PDF
M/s A.K. Construction & Ors. v. State of Chhattisgarh & Ors. [2026:CGHC:10481-DB]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in