Bombay High Court

Bombay HC Sets Aside ₹2.16-Crore Belt Refund Award After Buyer Replaced Only 860 Of 3,490 Metres And Tribunal Ignored Supplier Evidence

M/S Forech India Ltd vs Jsw Jaigarh Port Ltd

Bombay High CourtJUDGMENT: October 19, 20263 MIN READSOURCE JUDGMENT
Bombay HC Sets Aside ₹2.16-Crore Belt Refund Award After Buyer Replaced Only 860 Of 3,490 Metres And Tribunal Ignored Supplier Evidence. M/S Forech India Ltd vs Jsw Jaigarh Port Ltd. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

JSW Jaigarh Port Limited (the Claimant before the Tribunal) placed two purchase orders in 2011 for EP conveyor belts manufactured by Forech India Limited.

Source reference: paras. 6–9, pp. 3–4

The orders required compliance with specified technical standards and provided a warranty for free repair or replacement of defective or unserviceable parts.

Source reference: paras. 6–9, pp. 3–4; para. 65, p. 46

After installation, waviness and air pockets were reported, and portions of the supplied belts were replaced.

Source reference: paras. 14–17, pp. 5–6

The Claimant sought, among other relief, a refund of the purchase price; the Tribunal awarded Rs. 2,16,44,423 with interest, after accounting for the encashed bank guarantees, and rejected Forech’s counter-claim.

Source reference: paras. 14–17, pp. 5–6; paras. 2–3, p. 2

Forech challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996.

Source reference: para. 2, p. 2
02

Issues

Whether the Tribunal’s finding that the supplied belts were defective was reached after considering both parties’ evidence, or by disregarding Forech’s evidence.

Source reference: para. 40(1), p. 22

Whether the Tribunal exceeded the contract’s warranty terms by awarding the price of the entire belting system, and whether the award thereby contravened the Sale of Goods Act, 1930 or Section 73 of the Indian Contract Act, 1872.

Source reference: para. 40(2), p. 22

Whether the Tribunal treated the parties unequally in assessing their witnesses’ evidence, contrary to Section 18 of the Arbitration and Conciliation Act, 1996.

Source reference: para. 40(3), p. 22

Whether the award suffered from patent illegality warranting interference under Section 34.

Source reference: para. 40(4), p. 22
03

Law Applied

Under Section 34, a court does not sit in appeal over an arbitral award or reappreciate evidence; interference is available on the statutory grounds, including patent illegality appearing on the face of a domestic award under Section 34(2A).

Source reference: paras. 41–42, pp. 23–30

Patent illegality must go to the root of the matter; it may arise where the Tribunal ignores vital evidence, contravenes substantive law or the Arbitration Act, or departs from the contract, but a reasonable contractual interpretation or a merely erroneous application of law is not enough (Associate Builders v. DDA; Ssangyong Engineering and Construction Co. Ltd. v. NHAI; MMTC Ltd. v. Vedanta Ltd.).

Source reference: paras. 41–42, pp. 23–30

Section 18 requires equal treatment of the parties.

Source reference: para. 40(3), p. 22

Under Sections 12 and 13 of the Sale of Goods Act, 1930, acceptance of goods may preclude rejection for breach of condition, leaving a claim for breach of warranty; Section 59 provides remedies for breach of warranty.

Source reference: paras. 63–65, pp. 42–46

Section 73 of the Indian Contract Act, 1872 limits compensation to loss caused by the breach.

Source reference: paras. 63–65, pp. 42–46

The contract’s warranty provided for free repair or replacement of defective or unserviceable parts.

Source reference: para. 65, p. 46
04

Reasoning

The Court found that the Tribunal rejected Forech’s evidence concerning conveyor speed and operating parameters because its witnesses were in-house witnesses and not experts, while relying on evidence from the Claimant’s similarly situated in-house witnesses.

Source reference: paras. 52, 58–60, pp. 38–41

The Tribunal’s failure to engage with Forech’s relevant evidence amounted to one-sided assessment and contravened the requirement of equal treatment.

Source reference: paras. 52, 58–60, pp. 38–41

The Court also noted that only 860 metres of the 3,490 metres supplied were shown to have been replaced; there was no evidence that the remaining 2,630 metres, or the entire supply, had been replaced.

Source reference: paras. 59, 62, pp. 41–42

As the Claimant had accepted and continued to use the belts, with replacement of defective portions, the case was one of breach of warranty.

Source reference: paras. 63, 65–67, pp. 42–47

The award of the entire purchase price was inconsistent with the warranty’s provision for repair or replacement of defective parts and was unsupported by proof that the entire belting had been replaced.

Source reference: paras. 63, 65–67, pp. 42–47

The Court held that these defects went to the root of the award and constituted patent illegality.

Source reference: para. 69, p. 48
05

Holding

The Court allowed the Section 34 challenge and set aside the award, including the award on the counter-claim.

The petition was disposed of, with the parties left to pursue remedies available in law; if a further arbitration is sought, the evidence from the existing proceedings may be used along with such additional evidence as the Tribunal permits.

Source reference: paras. 70–71, p. 49
06

Acts & Sections Cited

13 provisions across 3 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19969 provisions

Sale of Goods Act, 19303

Indian Contract Act, 18721

Bombay High Court

Original Court PDF

M/S Forech India LtdvsJsw Jaigarh Port Ltd

Bombay High Court · October 19, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment