Bombay High Court
Arbitration and MediationProperty and Real Estate Law

Bombay High Court refers question of arbitrability in RERA promoter–allottee disputes to larger bench

Rensar Infra Private Limited vs Rais Kasam Shaikh

Bombay High CourtJUDGMENT: October 07, 20263 MIN READSOURCE JUDGMENT
Bombay High Court refers question of arbitrability in RERA promoter–allottee disputes to larger bench. Rensar Infra Private Limited vs Rais Kasam Shaikh. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Applicant promoter sought appointment of a sole arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996, relying on an arbitration clause in an Agreement for Sale dated 31 December 2020 for Flat No. 1901.

Source reference: para. 1–4

The claims included balance sale consideration, an amount for additional area, and compensation. The allottee-Respondents had earlier obtained relief before MahaRERA under Section 18 of the Real Estate (Regulation and Development) Act, 2016 (“RERA”); the Applicant’s review was rejected, and it appealed to MahaREAT.

Source reference: para. 3–4

The Respondents objected, among other things, that promoter-allottee disputes governed by RERA were non-arbitrable and that the Applicant’s participation in the RERA proceedings barred a later arbitration application.

Source reference: para. 19–28
02

Issues

1. Whether a dispute between an individual promoter and allottee under an Agreement for Sale governed by RERA is non-arbitrable as a class, or whether arbitrability depends on the subject matter, relief sought, and statutory powers of RERA authorities.

Source reference: para. 61–64

2. Whether the Applicant’s earlier RERA proceedings, including its failure to seek reference under Section 8 of the Arbitration Act, barred its Section 11 application on grounds of parallel proceedings, election, or issue estoppel.

Source reference: para. 47–56

3. Whether the limitation of the Applicant’s individual claims could be decided at the Section 11 stage.

Source reference: para. 57–59
03

Law Applied

Under Sections 11 and 16 of the Arbitration Act, the referral court’s scrutiny is limited, but it may consider a prima facie objection that a dispute is non-arbitrable; it should not conduct a detailed inquiry into the merits or limitation of individual claims.

Source reference: para. 31–32

Under SBI General Insurance Co. Ltd. v. Krish Spinning, the Section 11 court’s limitation inquiry is confined to whether the Section 11 application itself was filed within time, leaving limitation of the underlying claims to the tribunal.

Source reference: para. 58

The Court considered the competing Bombay High Court decisions in Rashmi Realty Builders Pvt. Ltd. v. Rahul Pagariya and Abhay Damodar Kanhere v. Morya Infraconstruct Pvt. Ltd., as well as Laxman Mura Vaid v. Shree Siddhivinayak, on the arbitrability of RERA-governed promoter-allottee disputes.

Source reference: para. 34–41, 61–64

It also considered Sections 79, 88 and 89 of RERA, the anti-bifurcation principle in Sukanya Holdings (P) Ltd. v. Jayesh H. Pandya, and the principles concerning prior proceedings and overlapping reliefs in Anil v. Rajendra, SSIPL Lifestyle Pvt. Ltd. v. Vama Apparels (India) Pvt. Ltd., and Neo Developers Private Limited v. Rahul Bhargava.

Source reference: para. 48–56
04

Reasoning

The Court found that an arbitration agreement existed and that the Applicant’s claims were genuine disputes, but held that the existence of the clause did not end the Section 11 inquiry where a prima facie non-arbitrability objection was raised.

Source reference: para. 30–33, 60

The balance consideration and additional-area claims arose from the promoter-allottee transaction and could not be taken outside RERA merely by describing them as contractual or monetary claims.

Source reference: para. 43–45

However, the Applicant’s claims had not been shown to have been decided by MahaREAT, and the record did not establish a prior decision rejecting arbitration or a blanket bar under Section 8, issue estoppel, or election; substantially overlapping reliefs could not, however, be pursued through parallel proceedings.

Source reference: para. 42, 47–56

The Court left the limitation of the individual claims open, applying Krish Spinning.

Source reference: para. 57–59

Because Rashmi Realty and Laxman Mura Vaid supported class-wide non-arbitrability while Abhay Kanhere took a materially different approach to the issue, the Court considered authoritative clarification necessary rather than finally deciding arbitrability itself.

Source reference: para. 61–65
05

Holding

The Court did not finally hold that the Applicant’s claims were arbitrable or non-arbitrable.

It referred the question of whether RERA-governed disputes between an individual promoter and allottee are non-arbitrable as a class—or must be assessed by the nature of the dispute and relief—to an appropriate larger Bench, together with the related question concerning paragraph 63(i) of Rashmi Realty.

Source reference: para. 64–66

The Section 11 proceedings were deferred pending the larger Bench’s decision.

Source reference: para. 67
06

Acts & Sections Cited

19 provisions across 3 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19965

Real Estate (Regulation and Development) Act, 2016.13 provisions

Limitation Act, 19631

Bombay High Court

Original Court PDF

Rensar Infra Private LimitedvsRais Kasam Shaikh

Bombay High Court · October 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment