Facts
The petitioners, legal heirs of Jeevanandham, sought action on his online application dated 21 August 2025 for survey and demarcation of land in Survey No. 336/2A22, Velampalayam village.
Source reference: p.2The required fee had been paid by e-challan.
Source reference: p.2In an earlier writ petition, the Court had directed the authorities to consider the application within four weeks, but the petitioners alleged that no effective steps followed.
Source reference: pp.2–3They then sought consideration of the application and a comprehensive survey, including a disputed three-foot inner portion, with police assistance if necessary.
Source reference: pp.2–3The Government Pleader submitted that the application would be considered if the Court fixed a specific timeframe.
Source reference: p.3Issues
1. Whether the authorities should be directed to consider the deceased applicant’s survey application and conduct a field survey and boundary demarcation of the petitioners’ land.
Source reference: pp.2–42. Whether the survey and related proceedings should be completed within a fixed timeframe, with notice and an opportunity for affected parties to present their objections and documents.
Source reference: pp.3–4Law Applied
The Court acted under its writ jurisdiction, invoked through Article 226 of the Constitution, to direct the relevant authority to consider and dispose of the pending application.
Source reference: p.4It directed that the survey and demarcation be carried out in accordance with the relevant revenue records and the parties’ parental title deeds, with notice and an opportunity for affected parties to be heard.
Source reference: p.4The Court also stated that disputes concerning title or inter se civil rights should be taken to the competent Civil Court.
Source reference: p.5No statutory provision or precedent was cited in the order.
Source reference: no citationReasoning
Given the limited scope of the petition and the respondents’ submission that the application could be considered within a fixed period, the Court issued directions without deciding the merits of the petitioners’ claim.
Source reference: pp.3–4It required notice to the petitioners, counter-claimants, and adjacent landowners, and a fair opportunity to submit objections, representations, and title documents during the inquiry.
Source reference: p.4The Court confined the administrative process to survey and demarcation under the relevant records and deeds, leaving any underlying title or civil-rights dispute to the Civil Court.
Source reference: pp.4–5Holding
The writ petition was disposed of with a direction to the first respondent to entertain the application, conduct a field survey and boundary demarcation, and complete the physical measurement, fixation of boundary stones, and issuance of a reasoned final order within six weeks of receiving a copy of the order.
The authorities may obtain police protection if required, and the jurisdictional police must provide it.
Source reference: p.5The Court expressed no view on the merits of the petitioners’ claim; no costs were awarded.
Source reference: pp.5, 7Original Court PDF
J. SivasankarivsThe Tahsildar
Click to open original judgment