Facts
The Appellant, a cement manufacturer and captive user of power generated by Arasmeta Captive Power Company Pvt. Ltd., was permitted to operate its captive plant in parallel with the Respondent-DISCOM’s system and to wheel 16 MW of power to its Sonadih cement plant.
Source reference: para. 4–5By letter dated 10 October 2006, the Appellant sought reduction of its contract demand from 9,500 KVA to zero with effect from 16 October 2006, relying on the Chhattisgarh State Electricity Regulatory Commission’s orders dated 6 February 2006 and 29 September 2006, which liberalised contract-demand reduction for captive consumers.
Source reference: para. 6, 12CSPDCL declined to give immediate effect to the request on 4 November 2006 and subsequently approved reduction to zero with effect from 1 January 2007.
Source reference: para. 6–7, 27Meanwhile, wheeling of 16 MW was operationalised from 4 November 2006, but CSPDCL continued billing the Appellant on the basis of the subsisting 9,500 KVA contract demand for the period 4 November–31 December 2006.
Source reference: para. 7–9, 27–28The Appellant claimed a refund of ₹1,40,96,072 for allegedly excessive demand, penal demand, energy and related charges. Its petition before the State Commission was ultimately dismissed on merits after remand proceedings concerning limitation. The present appeal challenged that decision.
Source reference: para. 10Issues
Whether the State Commission’s orders permitting captive consumers to reduce contract demand “to any extent, even to zero, at any time” dispensed with the procedural requirements and timeline prescribed under Clause 7.11 of the Supply Code, 2005.
Source reference: para. 28–32, 35–37Whether operationalisation of open access and wheeling of 16 MW from 4 November 2006 automatically resulted in reduction of the Appellant’s contract demand to zero from that date.
Source reference: para. 38Whether CSPDCL was entitled to levy contract-demand and related charges for the period from 4 November to 31 December 2006.
Source reference: para. 27–28, 39Law Applied
The Tribunal applied Clause 7.9 of the Chhattisgarh State Electricity Supply Code, 2005, which ordinarily restricted reduction of contract demand during the initial two-year agreement period and permitted only limited reduction in specified circumstances.
Source reference: para. 32It also applied Clause 7.11, requiring the licensee to verify and decide an application for reduction within 60 days by a reasoned order, with deemed permission arising only upon failure to decide within the prescribed further period; any approved reduction takes effect from the first day of the month following communication of the decision or deemed permission.
Source reference: para. 32The Commission’s orders dated 6 February and 29 September 2006 relaxed the substantive restrictions in Clause 7.9 for captive consumers, permitting reduction to any extent, including zero, and once during each year, but did not expressly modify Clause 7.11’s procedural requirements.
Source reference: para. 29–30, 34–36The Tribunal further recognised that open access and contract demand are legally distinct: open access regulates use of the distribution system and wheeling of energy, whereas contract demand concerns the licensee’s obligation to maintain capacity for the consumer.
Source reference: para. 38Section 42(2) of the Electricity Act, 2003, governing open access, does not override the Supply Code’s procedure for modification of contract demand.
Source reference: para. 24Reasoning
The Tribunal construed the expression “any time” contextually. It held that the Commission’s relaxation removed the substantive two-year prohibition and the requirement of demonstrating compelling reasons under Clause 7.9, but did not eliminate the procedural discipline under Clause 7.11, since the Commission’s orders contained no reference to or modification of that clause.
Source reference: para. 33–37The Appellant’s application was therefore not self-executing from the date requested. CSPDCL was entitled to examine the application, verify the relevant conditions, and determine the effective date in accordance with the Supply Code.
Source reference: para. 27, 31, 39Since CSPDCL approved reduction to zero with effect from 1 January 2007, that date complied with Clause 7.11.
Source reference: para. 27, 31, 39The Tribunal also rejected the argument that commencement of wheeling on 4 November 2006 automatically extinguished the existing contract demand. Wheeling could be accounted for independently while the 9,500 KVA contract demand remained operative until formally modified under the Supply Code.
Source reference: para. 38Consequently, the absence or operationalisation of open-access arrangements did not invalidate billing based on the subsisting contract demand.
Source reference: para. 38–40Holding
The Tribunal answered all issues against the Appellant. It held that the Commission’s orders relaxed only the substantive restrictions under Clause 7.9 and did not override Clause 7.11’s procedure and timeline; open access and contract-demand reduction were distinct legal and commercial matters; and CSPDCL lawfully maintained the Appellant’s 9,500 KVA contract demand until 31 December 2006.
The levy of demand and related charges for the period from 4 November to 31 December 2006 was therefore upheld.
Source reference: para. 37–39The impugned order of the State Commission was affirmed, the appeal was dismissed, and pending interlocutory applications were disposed of accordingly.
Source reference: Order; para. 40Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Electricity Act, 20031
Original Court PDF
NUVOCO VISTAS CORPORATION LIMITED & AnrvsCHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION & Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
