APTEL

CERC cannot refer disputes to arbitration under Section 79(1)(f) if it lacks jurisdiction to adjudicate them.

Gujarat Urja Vikas Nigam Limited v. Tata Power Company Limited & Ors. (Common Judgment in Appeal Nos. 348, 371 & 400 of 2025)

APTEL3 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellants (State Discoms of Gujarat, Punjab, and Haryana) filed petitions before the Central Electricity Regulatory Commission (CERC) seeking specific performance of Power Purchase Agreements (PPAs) dated 22.04.2007, and compensation for short-supply of electricity.

Source reference: p. 10-14

The Respondent (Tata Power/TPCL) filed a cross-petition challenging the legality of penalties and deductions made by the Discoms.

Source reference: p. 15

TPCL argued that the disputes were "non-tariff" contractual breaches and should be referred to arbitration per the PPA’s arbitration clause.

Source reference: p. 34

Although parties had already filed pleadings on merits, the CERC passed an order on 19.11.2025 holding that it lacked adjudicatory jurisdiction over non-tariff disputes and mandatorily referred the matters to arbitration under the second limb of Section 79(1)(f) of the Electricity Act, 2003.

Source reference: p. 41-42

The Appellants challenged this reference, arguing the disputes were regulatory and impacted tariff.

Source reference: p. 16
02

Issues

1. Whether the CERC has the power to refer a dispute to arbitration under Section 79(1)(f) if it lacks inherent jurisdiction to adjudicate the subject matter under clauses (a) to (d) of Section 79(1).

Source reference: p. 69 / para. V

2. Whether the filing of an application under Section 8 of the Arbitration and Conciliation Act, 1996, at the earliest stage, is a mandatory pre-condition for the Commission to refer a dispute to arbitration.

Source reference: p. 130 / para. VIII

3. Whether the CERC can bifurcate a cause of action to refer contractual disputes to arbitration while keeping statutory/regulatory claims (against WRLDC) for its own adjudication.

Source reference: p. 144 / para. IX
03

Law Applied

The court applied Section 79(1)(f) of the Electricity Act, 2003, which grants CERC the power to adjudicate disputes involving generating companies regarding matters connected to "regulation of tariff" or to refer them to arbitration.

Source reference: p. 68

It relied on *GUVNL v. Essar Power Ltd.* (2008) 4 SCC 755, which established that the word "and" in the referral clause should be read as "or," giving the Commission discretion to choose between adjudication or arbitration.

Source reference: p. 51, 75

The "jurisdictional fact" doctrine from *Arun Kumar v. Union of India* (2007) 1 SCC 732 was applied to hold that CERC must first have subject-matter competence before exercising referral powers.

Source reference: p. 72

The court also followed *Hindustan Zinc Ltd. v. Ajmer VVN Ltd.* (2019) 17 SCC 82, clarifying that only disputes capable of being adjudicated by the Commission can be referred to arbitration.

Source reference: p. 92, 94

Finally, it applied *Sukanya Holdings (P) Ltd. v. Jayesh H. Pandya* (2003) 5 SCC 531, which prohibits the bifurcation of a single suit or cause of action into arbitration and court proceedings.

Source reference: p. 146, 168
04

Reasoning

The Tribunal reasoned that the CERC’s power under Section 79(1)(f) is not two independent powers but a single discretionary choice: it can only refer to arbitration what it is otherwise empowered to adjudicate.

Source reference: p. 84, 94

Therefore, if a dispute does NOT fall under Section 79(1)(a)-(d) (regulation of tariff), the CERC has no power to refer it elsewhere; it must simply dismiss it for lack of jurisdiction.

Source reference: p. 95, 177

On the application of the 1996 Act, the Tribunal held that Section 8(1) requirements are mandatory; since TPCL filed its own petition and responded to others on merits without a timely Section 8 application, the right to seek arbitration was waived.

Source reference: p. 141-142

Regarding bifurcation, the Tribunal found the claims against TPCL and the statutory body WRLDC (for scheduling failures under Section 28) were "integrally connected".

Source reference: p. 172

Since WRLDC is not a party to the arbitration agreement and the dispute involves statutory functions (non-arbitrable), splitting the case would lead to conflicting judgments and is legally impermissible.

Source reference: p. 169, 177
05

Holding

The Tribunal set aside the CERC's order and allowed all three appeals.

(i) CERC cannot refer a dispute to arbitration if it lacks the competence to adjudicate it.

Source reference: p. 177

(ii) TPCL failed to comply with Section 8(1) of the 1996 Act, rendering the reference invalid.

Source reference: p. 175

(iii) the bifurcation of the cause of action involving WRLDC was illegal.

Source reference: p. 177

The CERC is directed to restore the petitions and first determine if the disputes relate to the "regulation of tariff" under Section 79(1)(b); if they do, CERC must adjudicate them on merits; if not, it must dismiss them for lack of jurisdiction.

Source reference: p. 177-178
APTEL

Original Court PDF

Gujarat Urja Vikas Nigam Limited v. Tata Power Company Limited & Ors. (Common Judgment in Appeal Nos. 348, 371 & 400 of 2025)

APTEL

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment