Chhattisgarh High Court
Administrative and Public LawProperty and Real Estate Law

Challenges to RERA orders should be pursued before the functioning RERA Appellate Authority.

GOPAL BHAI PATEL vs M/S Aadharshila Developers Pvt Ltd.

Chhattisgarh High CourtJUDGMENT: October 08, 20262 MIN READSOURCE JUDGMENT
Challenges to RERA orders should be pursued before the functioning RERA Appellate Authority.. GOPAL BHAI PATEL vs M/S Aadharshila Developers Pvt Ltd.. Chhattisgarh High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner challenged a RERA order dated 18 June 2026, which he said wrongly required him to pay maintenance charges and GST before the occupancy/completion certificate was issued. He also sought directions concerning possession and transfer of common areas, penal proceedings, and compensation

Source reference: para. 1

Although the petitioner initially approached the High Court on the basis that the RERA Appellate Authority was not functioning properly, respondents submitted that it was hearing appeals and interim applications

Source reference: paras. 2–5

The petitioner then sought permission to withdraw the petition and appeal to the Appellate Authority

Source reference: para. 6
02

Issues

1. Whether the petitioner should pursue an appeal before the RERA Appellate Authority, which respondents submitted was functioning and hearing matters.

Source reference: paras. 2–5

2. Whether the petitioner should be permitted to withdraw the writ petition with liberty to file an appeal and an interim application before that Authority.

Source reference: para. 6
03

Law Applied

The Court did not determine the substantive rights or obligations arising under the Real Estate (Regulation and Development) Act, 2016. Although the petitioner’s requested reliefs invoked Sections 11(4)(b), 19(10), 17(1)–(2), 63, 71 and 18(3) of the Act, the Court did not interpret or apply those provisions on their merits

Source reference: para. 1

It permitted the petitioner to pursue the appeal remedy and directed the Appellate Authority to consider the appeal, particularly the interim application, in accordance with law

Source reference: para. 7
04

Reasoning

Respondents stated that the RERA Appellate Authority was functioning and entertaining appeals and stay applications

Source reference: paras. 3–5

In light of those submissions, the petitioner chose to withdraw the writ petition and seek recourse before that Authority

Source reference: para. 6

The Court accepted that course without deciding the merits of the challenge to the RERA order or the petitioner’s statutory claims, and left their consideration to the Appellate Authority

Source reference: paras. 7–8
05

Holding

The Court dismissed the petition as withdrawn, granting the petitioner liberty to file a duly constituted appeal before the RERA Appellate Authority along with an appropriate interim application.

It directed the Authority to consider the appeal, particularly the interim application, in accordance with law and endeavour to decide it expeditiously.

Source reference: para. 7
06

Acts & Sections Cited

6 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Real Estate (Regulation and Development) Act, 2016.6

Chhattisgarh High Court

Original Court PDF

GOPAL BHAI PATELvsM/S Aadharshila Developers Pvt Ltd.

Chhattisgarh High Court · October 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment