NCLAT

CIRP may be stayed to facilitate a bona fide settlement where substantial payment is already made.

Harvinder Singh Sikka v. Nobal Buildtech Pvt. Ltd. Through the Interim Resolution Professional & Ors. [Company Appeal (AT) (Insolvency) No. 256, 287 & 288 of 2026]

NCLATJUDGMENT: no citation3 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Corporate Debtor (CD), Nobal Buildtech Pvt. Ltd., acted as a corporate guarantor for loans raised by Kindle Infraheights Pvt. Ltd. from Asia Pragati Strategic Investment Fund/Orbis Trusteeship Services (Financial Creditors).

Source reference: no citation

Following a default, Section 7 CIRP was initiated against the CD.

Source reference: no citation

During the appeal process, the parties entered into a Settlement Agreement dated 09.05.2025 for ₹210 crore.

Source reference: para. 3(vi)

Consequently, the NCLT allowed the withdrawal of CIRP under Section 12A on 31.07.2025.

Source reference: para. 3(viii)

However, a delay in uploading the order led to a dispute over the payment timeline for the third tranche of ₹25 crore.

Source reference: no citation

The Financial Creditor (FC) moved a Restoration Application (RA 83/2025) for revival of CIRP.

Source reference: para. 3(x)

Although the ₹25 crore was eventually paid and accepted, leaving a balance of ₹90 crore, the Adjudicating Authority (AA) revived the CIRP on 07.01.2026 but granted a 10-day stay for the CD to pay the balance.

Source reference: para. 3(xiii)

The CD sought a 90-day extension via I.A. 312/2026, citing difficulties in monetizing assets due to the unavailability of original title deeds.

Source reference: para. 3(xv)

The AA granted time only until 04.02.2026.

Source reference: para. 3(xvi)

The Appellant challenged these orders.

Source reference: no citation
02

Issues

Whether the Adjudicating Authority erred in reviving the CIRP and refusing a reasonable extension to the Corporate Debtor to pay the balance settlement amount despite substantial part-performance.

Source reference: para. 5

Whether the lack of original title deeds and subsequent actions of the Financial Creditor justified an extension of time under the inherent powers of the Tribunal.

Source reference: para. 19-21
03

Law Applied

The Court relied on Section 12A of the Insolvency and Bankruptcy Code (IBC), 2016, regarding the withdrawal of applications.

Source reference: para. 22

It emphasized the primary objective of the IBC as the "revival and continuation of the corporate debtor" rather than mere recovery, as established in *Swiss Ribbons Pvt. Ltd. v. Union of India*.

Source reference: para. 22-23

The Court further applied the principle from *Anuj Jain v. Axis Bank Ltd.*, noting that Financial Creditors have "parental and nursing roles" to ensure the viability of the CD.

Source reference: para. 24

It also cited *E.S. Krishnamurthy v. Bharat Hi-Tecch Builders Pvt. Ltd.*, which held that settlements must be encouraged to facilitate the rehabilitation of the CD.

Source reference: para. 25

Finally, the Court invoked Rule 11 of the NCLT Rules, 2016, regarding inherent powers to meet the ends of justice.

Source reference: para. 17
04

Reasoning

The Court observed that out of the total settlement of ₹210 crore, the CD had already paid ₹120 crore, demonstrating bona fide intent.

Source reference: para. 16, 26

The dispute regarding the ₹25 crore tranche was largely procedural, stemming from the delay in uploading the NCLT's withdrawal order.

Source reference: para. 14-15

The Court found that the CD’s inability to pay the final ₹90 crore was linked to the unavailability of original title deeds required for investor due diligence—a fact the Resolution Professional (RP) eventually confirmed by seeking duplicates from the Noida Authority.

Source reference: para. 19, 28

Applying *Swiss Ribbons*, the Court reasoned that since Orbis was the sole Financial Creditor, its "pivotal role" should be facilitating the CD’s survival rather than pushing for a "hostile takeover" through revival of CIRP.

Source reference: para. 22-24

The Court determined that the AA’s grant of only two weeks was insufficient given the complexities of asset monetization and that a 90-day extension was a "reasonable and limited period" to achieve the IBC's goal of rehabilitation.

Source reference: para. 27-28
05

Holding

The Appellate Tribunal allowed the appeals and modified the AA's order dated 21.01.2026.

The Court held that sufficient cause existed to grant the 90-day extension prayed for in I.A. 312/ND/2026.

Source reference: para. 28

It directed that if the Appellant pays the balance ₹90 crore within 90 days from the date of the judgment, the order withdrawing CIRP dated 31.07.2025 shall become operative and CIRP shall stand terminated.

Source reference: para. 30(ii)

The FC and RP were directed to provide necessary assistance to the CD to implement the Settlement Deed.

Source reference: para. 30(iii)
NCLAT

Original Court PDF

Harvinder Singh Sikka v. Nobal Buildtech Pvt. Ltd. Through the Interim Resolution Professional & Ors. [Company Appeal (AT) (Insolvency) No. 256, 287 & 288 of 2026]

NCLAT · no citation

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment