Facts
The Plaintiffs, original developers of three slum rehabilitation schemes, were terminated by the Slum Rehabilitation Authority (SRA) and replaced by Defendant No. 4
Source reference: para. 1, 31The Plaintiffs alleged that their removal and the subsequent appointment of Defendant No. 4 resulted from a fraudulent conspiracy involving the Defendants, including state officials and "blacklisted" developers
Source reference: para. 1, 3, 28Following the dismissal of their Special Leave Petition by the Supreme Court on 12th April 2019, which granted liberty to pursue remedies for breach of contract and damages, the Plaintiffs filed this suit seeking declarations of entitlement to benefits, compensation, and damages
Source reference: para. 32, 34Defendants 11, 12, 4, 3, and 19 filed applications under Order VII Rule 11 of the CPC for rejection of the plaint on grounds of limitation, bar of jurisdiction under the Slum Act, non-compliance with pre-institution mediation, and Order II Rule 2
Source reference: para. 1, 2Issues
1. Whether the suit is barred by limitation considering the COVID-19 extension granted by the Supreme Court
Source reference: para. 4, 11, 18, 472. Whether the jurisdiction of the Civil Court is barred under Section 42 of the Maharashtra Slum Areas Act, 1971
Source reference: para. 6, 10, 12, 363. Whether the suit is liable for rejection for non-compliance with mandatory pre-institution mediation under Section 12A of the Commercial Courts Act, 2015
Source reference: para. 5, 17, 534. Whether the suit is barred under the principle of Order II Rule 2 of the CPC due to a pending counterclaim in a separate suit
Source reference: para. 14, 16, 63Law Applied
The Court applied Order VII Rule 11 of the CPC regarding the rejection of a plaint
Source reference: para. 1, 54It relied on the Supreme Court's decision in Cognizance for Extension of Limitation, In Re, which provided that if the balance period of limitation remaining as of 1st March 2022 is greater than 90 days, the longer period applies
Source reference: para. 48-49Regarding the bar under Section 42 of the Slum Act, it cited Qari Mohammed Zakir Hussain v. MCGM and Om Shree Sai Developers v. State of Maharashtra, establishing that Civil Courts retain jurisdiction where acts are alleged to be fraudulent, malicious, or not in good faith
Source reference: para. 41, 42For Section 12A of the Commercial Courts Act, it applied Yamini Manohar v. T.K.D. Keerthi and Dhanbad Fuels, which state that the court must holistically assess if urgent interim relief is "contemplated" from the plaintiff's standpoint to bypass mediation
Source reference: para. 56, 57Finally, it applied Cuddalore Powergen Corp v. Chemplast Cuddalore, holding that the bar under Order II Rule 2 requires an identity of cause of action and cannot be decided on a "reductive approach" at the threshold
Source reference: para. 65, 66Reasoning
The Court found the suit within limitation because the cause of action arose on 3rd October 2018; as of 15th March 2020, the balance period was over 1.5 years, which remained available post-COVID extension (until 17th September 2023), making the 11th September 2023 filing timely
Source reference: para. 49, 50On the statutory bar, the Court reasoned that since the Plaintiffs specifically pleaded detailed particulars of fraud, collusion, and malice (vitiating "good faith"), the bar under Section 42 of the Slum Act did not apply, as such triable issues of civil nature are within the plenary jurisdiction of the Civil Court under Section 9 CPC
Source reference: para. 45, 62Regarding Section 12A, the Court held that the Plaintiffs genuinely "contemplated" urgent relief to protect private rights against ongoing construction by Defendant No. 4, thus exempting them from pre-institution mediation
Source reference: para. 53, 62Regarding Order II Rule 2, the Court determined that the Plaintiffs' counterclaim in a separate suit was based on contractual breach, whereas the present suit was based on fraud, meaning the causes of action were not identical and required trial evidence
Source reference: para. 68Holding
The Court held that the plaint discloses a valid cause of action and is not barred by limitation, Section 42 of the Slum Act, or Section 12A of the Commercial Courts Act
The Court dismissed all Interim Applications for rejection of the plaint. Finding that the applications were an attempt to delay proceedings and defeat the object of the Commercial Courts Act, the Court directed the Applicants/Defendants to pay costs of ₹2,00,000 per application to the Plaintiffs
Source reference: para. 71, 72Original Court PDF
L And T Asian Realty Project Llp Now Known As Elevated Avenue Realty LlpvsK S Chamankar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in