Patna High Court
Criminal LawAdministrative and Public Law

Civil liability challenges in electricity-theft cases must be pursued before the pending criminal Special Court.

North Bihar Power Distribution Company Ltd. and Anr vs M/s Trina Construction Pvt. Ltd. and Ors

Patna High CourtJUDGMENT: September 11, 20263 MIN READSOURCE JUDGMENT
Civil liability challenges in electricity-theft cases must be pursued before the pending criminal Special Court.. North Bihar Power Distribution Company Ltd. and Anr vs M/s Trina Construction Pvt. Ltd. and Ors. Patna High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

An inspection of the respondent-consumer’s premises on 25 August 2011 allegedly revealed tampering with the electricity meter, including interference with its seals, ultrasonic strips, and metering mechanism. An FIR was registered under Section 135 of the Electricity Act, 2003.

Source reference: pp. 1–2

A provisional assessment of ₹50,10,969 was made and deposited under protest to avoid disconnection, followed by a final assessment of ₹40,96,070 dated 28 September 2011.

Source reference: pp. 1–2

The consumer challenged the assessment under Section 127 of the Electricity Act. During the appellate proceedings, FPPCA charges of ₹4,26,676 were added. By order dated 10 June 2016, the Appellate Authority allowed the appeal and directed that reassessment be undertaken only for the period from 2 August 2011 to 25 August 2011, rather than for the period of 365 days.

Source reference: pp. 2–3

The distribution company challenged that appellate order before the High Court, contending that the assessment period had been unlawfully restricted and that the matter ought to have been remitted for fresh assessment.

Source reference: pp. 3–4
02

Issues

Whether the High Court should adjudicate the distribution company’s challenge to the appellate assessment order, or direct the parties to approach the Special Court constituted under Section 154 of the Electricity Act for determination of civil liability arising from alleged theft of electricity?

Source reference: paras. 8–12; pp. 4–7

Whether the petitioner should be permitted to challenge the appellate order dated 10 June 2016 before the Special Court where the criminal proceeding was pending?

Source reference: paras. 10–12; pp. 5–7
03

Law Applied

The Court applied Sections 154(5) and 154(6) of the Electricity Act, 2003, under which the Special Court dealing with an offence of theft of electricity is empowered to determine the civil liability payable by the consumer or other person concerned.

Source reference: paras. 8–10; pp. 4–6

The Court relied on the Division Bench decision in Mosmat Swaran @ Swaran Man Ra v. The State of Bihar & Ors., 2012 (2) PLJR 229, holding that questions concerning civil liability for theft should be placed before the Special Court.

Source reference: paras. 8–10; pp. 4–6

It also followed the earlier order in The South Bihar Power Distribution Company Ltd. v. The State of Bihar & Ors., CWJC No. 19868 of 2013, directing the distribution company to challenge the relevant assessment-related order before the Special Court where the criminal case was pending.

Source reference: paras. 8–10; pp. 4–6
04

Reasoning

The Court treated the alleged meter tampering and the pending prosecution under Section 135 as matters falling within the statutory jurisdiction of the Special Court.

Source reference: paras. 9–12; pp. 5–7

Following Mosmat Swaran and the earlier South Bihar Power Distribution Company decision, it held that the dispute regarding the assessment and the corresponding civil liability should be considered by the Special Court rather than being resolved in the writ petition.

Source reference: paras. 9–12; pp. 5–7

Consequently, the Court did not examine whether the Appellate Authority had correctly applied Section 126(5), whether the 365-day assessment period was justified, or whether remand to the Assessing Officer was necessary.

Source reference: paras. 9–12; pp. 5–7

Instead, it adopted the previously established procedural course and required the petitioner to pursue its challenge before the competent Special Court.

Source reference: paras. 9–12; pp. 5–7
05

Holding

The writ petition was disposed of without adjudication on the merits.

The petitioner-distribution company was directed to file a separate petition before the Special Court where the criminal proceeding was pending, challenging the appellate order dated 10 June 2016, within 30 days.

Source reference: paras. 11–13; pp. 6–7

The Special Court was directed to decide the challenge in accordance with law by a reasoned order.

Source reference: paras. 11–13; pp. 6–7

Any pending interlocutory applications were also disposed of.

Source reference: para. 14; p. 7
06

Acts & Sections Cited

4 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Patna High Court

Original Court PDF

North Bihar Power Distribution Company Ltd. and AnrvsM/s Trina Construction Pvt. Ltd. and Ors

Patna High Court · September 11, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment