Facts
The plaintiff sought summary judgment for repayment of ₹52 crore, which it said had been advanced for a realty project and later converted into an interest-free loan.
Source reference: pp. 3–4The repayment period was extended, but the amount remained unpaid.
Source reference: pp. 3–4The first defendant’s written statement admitted the transaction and stated that the defendants owed ₹52 crore, attributing non-payment to a slowdown in the realty sector and the COVID-19 pandemic.
Source reference: pp. 5–6The first defendant later argued that the admission was erroneous, that the sum had become a capital/current-account contribution following its conversion into an LLP, and that the claim was barred by limitation; it also raised arbitration.
Source reference: p. 4Defendants 2 and 3 disputed their liability and sought a trial.
Source reference: p. 4The Court had previously dismissed the defendants’ applications to refer the dispute to arbitration and recorded that defendants 2 to 5 had forfeited their right to file written statements.
Source reference: pp. 5–6Issues
Whether the first defendant’s admission of the ₹52 crore liability, with no evidence of repayment, justified summary judgment for the principal under Order XIII-A CPC.
Source reference: pp. 6–7Whether the arbitration and limitation objections prevented summary judgment.
Source reference: pp. 5–6Whether the plaintiff was entitled to summary judgment for interest at 24% per annum, or whether that claim required trial.
Source reference: p. 7Law Applied
Order XIII-A Rules 1 and 3 CPC permit summary judgment where a defendant has no real prospect of successfully defending the claim and there is no compelling reason to defer determination to trial.
Source reference: p. 7The Court also relied on the Supreme Court’s orders in In Re: Cognizance for Extension of Limitation, which excluded the period from 15 March 2020 to 28 February 2022 for limitation purposes.
Source reference: p. 6The Court treated the prior orders dismissing the defendants’ Section 8 applications under the Arbitration and Conciliation Act, 1996, as having concluded the arbitration objection in this application.
Source reference: p. 5Reasoning
The first defendant’s written statement expressly admitted the ₹52 crore liability, and no evidence showed that any part had been repaid.
Source reference: pp. 5–7Its later assertion that the admission was inadvertent, and its contention that the amount had become a capital contribution, did not displace the admission for purposes of the principal claim.
Source reference: pp. 5–7The arbitration objection had already been rejected in earlier orders.
Source reference: pp. 5–6The limitation objection was raised only in the application proceedings and, in any event, the COVID-19 limitation exclusion meant the suit filed on 27 April 2022 was within time.
Source reference: pp. 5–6However, the documents described the loan as interest-free during the agreed period, and the plaintiff’s 24% claim required evidentiary determination.
Source reference: p. 7Holding
The Court allowed the application and entered summary judgment for ₹52 crore against the first defendant, P&R Developers and Builders LLP; it did not grant summary judgment against defendants 2 to 5.
The claim for interest at 24% per annum was left open for trial, and the suit was directed to proceed only on interest and consequential reliefs.
Source reference: p. 8Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19961
Original Court PDF
MGM LOGISTICS AND SHIPPING PRIVATE LIMITEDvsP AND R DEVELOPERS AND BUILDERS LLP
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
