Facts
The Petitioner, a commercial electricity consumer, had its load enhanced to 140KV on July 14, 2023, and remained compliant with all consumption bills
Source reference: para. 1In July 2025, nearly two years later, the respondent supply company issued a notice demanding over ₹54,0,000, claiming a "mistake" in applying the tariff rate for previous consumption
Source reference: para. 1, 4A subsequent notice in October 2025 increased this demand to ₹62,03,152
Source reference: para. 4There were no allegations of electricity theft; the demand was based solely on a billing error discovered by the company
Source reference: para. 1The Petitioner challenged the demand and the threat of disconnection
Source reference: para. 1-2Issues
1. Whether a licensee/supply company can resort to coercive measures, such as disconnection of supply under Section 56 of the Electricity Act, 2003, to recover additional dues arising from a bona fide billing mistake discovered after the limitation period
Source reference: para. 2, 32. Whether the supply company can progressively increase its demand after the initial discovery of the mistake
Source reference: para. 5Law Applied
The Court applied Section 56 of the Electricity Act, 2003, which governs disconnection for non-payment, noting that Section 56(2) imposes a two-year limitation on recovering sums due unless shown continuously as arrears
Source reference: para. 4It relied extensively on the Supreme Court precedent in Assistant Engineer, Ajmer Vidyut Vitran Nigam Limited v. Rahamatullah Khan (2020), which held that while Section 17(1)(c) of the Limitation Act, 1963, allows recovery within two years of discovering a mistake, the licensee is barred from using disconnection as a coercive recovery tool for such "mistake-based" arrears
Source reference: para. 3The court also noted M/s Prem Cottex v. Uttar Haryana Bijli Vitran Nigam Ltd. (2021), clarifying that it did not overrule the bar on coercive action established in Rahamatullah Khan
Source reference: para. 6Reasoning
The Court reasoned that once a demand is raised based on a newly discovered mistake, the supply company cannot bypass the law by threatening disconnection
Source reference: para. 5Under Section 56 as interpreted by the Supreme Court, if a consumer disputes a demand arising from a billing error or if the limitation period for summary recovery has passed, the company's only recourse is through a civil suit for recovery
Source reference: para. 3, 5The Court observed that the Respondent’s notices lacked particulars of a "bona fide" error and that the demand had been arbitrarily revised upward from ₹54 lakhs to ₹62 lakhs without justification
Source reference: para. 4It held that a supply company cannot "progressively increase its demand" once a mistake is identified; it must provide a clear calculation and, if payment is not forthcoming, seek a decree from a civil court where the consumer has the opportunity to test the correctness of the demand
Source reference: para. 5, 6Holding
The Court allowed the writ petition
It held that while the supply company may issue a corrected demand based on a discovered mistake, it is strictly prohibited from taking coercive steps (disconnection) to recover such amounts
Source reference: para. 5-6The Court directed the supply company to provide the Petitioner with a transparent calculation and a prescribed time for payment; however, in the event of non-payment, the company is mandated to resort only to civil remedies to recover the principal sum and any applicable interest
Source reference: para. 6Original Court PDF
M/S Om Food Manufacturing CentervsState Of U.P. And 2 Others
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in