Facts
The petitioner claimed that, in addition to 0.040 hectare of land bearing Khasra No. 192/1A acquired pursuant to acquisition proceedings culminating in an award dated 27.09.2016, a further area of 1,248 square metres from Khasra Nos. 192/1A and 192/1B had been utilised for construction of the National Highway without acquisition or payment of compensation.
Source reference: para. 2A revenue demarcation report/Panchnama dated 09.05.2019 allegedly recorded that the additional area had been affected by the road and required to be acquired or purchased by the Government.
Source reference: para. 2The petitioner submitted a representation dated 13.08.2019 seeking compensation, but it remained undecided.
Source reference: para. 4Relying on an earlier order in Mathura Bai v. State of Chhattisgarh, WPC No. 797 of 2017, the petitioner sought either payment of compensation or a direction for consideration of his representation.
Source reference: para. 3The State submitted that no return had yet been filed and that the merits should not be adjudicated at that stage.
Source reference: para. 5Issues
1. Whether the competent authority should be directed to consider and decide the petitioner’s pending representation seeking compensation for the additional 1,248 square metres allegedly utilised for construction of the National Highway.
Source reference: paras. 4, 6–72. Whether the High Court could direct payment of compensation or determine the merits of the petitioner’s entitlement in the absence of a response/return from the authorities.
Source reference: paras. 5, 8Law Applied
The Court applied the administrative-law principle that a competent statutory authority must consider a duly submitted representation and pass an independent, reasoned and speaking order in accordance with law.
Source reference: para. 8The Court did not determine the petitioner’s substantive entitlement to compensation, noting that such entitlement had to be examined under the applicable land-acquisition and compensation provisions on the basis of the available material.
Source reference: para. 8The Court also followed the procedural approach adopted in the earlier matter concerning similarly utilised land, where directions had been issued for expeditious consideration of compensation.
Source reference: para. 3Reasoning
The petitioner’s allegation regarding utilisation of the additional land was supported, at this stage, by the asserted demarcation report and the pending representation.
Source reference: paras. 2, 4However, the State had not filed its return, and the factual and legal merits of the alleged encroachment, acquisition, utilisation, and compensation entitlement were therefore not appropriate for final adjudication in the petition.
Source reference: para. 5Balancing these considerations, the Court directed the concerned authority to examine the representation independently, apply the relevant law and available record, and issue a reasoned decision, without expressing any opinion on the merits of the claim.
Source reference: paras. 6–8Holding
The Court disposed of the petition by directing the respondent authority concerned to consider and decide the petitioner’s representation seeking compensation for the additional 1,248 square metres allegedly utilised for construction of the National Highway.
The decision was required to be made strictly in accordance with law by a reasoned and speaking order within 60 days from production of a certified copy of the order.
Source reference: para. 7The Court expressly clarified that it had not adjudicated the merits of the compensation claim.
Source reference: para. 8No order as to costs was made.
Source reference: para. 9Original Court PDF
YASHWANT KUMARvsSTATE OF CHHATTISGARH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
