CESTAT
Tax LawAdministrative and Public Law

Composite works contracts were not taxable under service tax before 1 June 2007.

Gearge Thomas Engg Contractor vs Cochin-cce

CESTATJUDGMENT: September 03, 20263 MIN READSOURCE JUDGMENT
Composite works contracts were not taxable under service tax before 1 June 2007.. Gearge Thomas Engg Contractor vs Cochin-cce. CESTAT. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellant executed civil and construction contracts, including construction of BSNL exchange buildings, towers and tower foundations, a Rubber Board building, and a meditation centre for the Marthoma Sabha. The Department alleged non-payment of service tax under the taxable categories of Commercial or Industrial Construction Service, Erection, Commissioning or Installation Service, and Works Contract Service for the period 2004–05 to 2007–08.

Source reference: pp. 1–2

A show-cause notice dated 18 December 2008 was issued invoking the extended limitation period under Section 73(1) of the Finance Act, 1994. The adjudicating authority confirmed the demand and imposed penalties; the Commissioner (Appeals) upheld the demand, set aside the penalty under Section 76 subject to payment of penalty under Section 78, and upheld the remaining penalties.

Source reference: pp. 1–2

The appellant contended that the contracts were composite contracts involving supply of materials and therefore constituted works contracts.

Source reference: pp. 2–5
02

Issues

Whether service tax could be demanded for the period prior to 1 June 2007 on composite contracts involving both provision of services and supply of materials, by classifying them under Commercial or Industrial Construction Service or Erection, Commissioning or Installation Service.

Source reference: pp. 2–4, 5–6

Whether the extended period of limitation under the proviso to Section 73(1) of the Finance Act, 1994, and the penalties imposed under the Act, were sustainable.

Source reference: pp. 4–5

Whether the service tax and interest paid by the appellant for the period from 1 June 2007 to March 2008 were liable to be appropriated.

Source reference: p. 5
03

Law Applied

The Tribunal applied the principle laid down by the Supreme Court in Commissioner of Customs v. Larsen & Toubro Ltd., 2015 (39) S.T.R. 913 (S.C.), that a composite contract involving transfer of property in goods and provision of services is a works contract and could not be vivisected and taxed under other taxable-service categories for the period preceding the specific introduction of Works Contract Service.

Source reference: pp. 2–5

Works Contract Service became taxable with effect from 1 June 2007.

Source reference: pp. 2–5

The Tribunal also considered the statutory framework concerning Commercial or Industrial Construction Service, Erection, Commissioning or Installation Service, the extended limitation provision under the proviso to Section 73(1), and penalties under Sections 77 and 78 of the Finance Act, 1994.

Source reference: pp. 2–5

The departmental Circular No. 80/10/2004-ST dated 17 September 2004 indicated that construction for non-commercial governmental, religious, charitable, educational, health, sanitation, or philanthropic purposes would generally not be taxable, although the final decision principally rested on the works-contract issue.

Source reference: pp. 2–5
04

Reasoning

The Tribunal found, on the evidence, that the appellant’s activities were composite contracts involving supply of materials and therefore fell within the category of works contracts.

Source reference: p. 5

Applying Larsen & Toubro, it held that such contracts could not be retrospectively vivisected to extract a service component and tax it under Commercial or Industrial Construction Service or Erection, Commissioning or Installation Service before the statutory introduction of Works Contract Service on 1 June 2007.

Source reference: p. 5

Consequently, the demand covering the period before 1 June 2007 was unsustainable.

Source reference: p. 5

Since the principal demand for the pre-1 June 2007 period failed on merits, the penalties imposed under the impugned orders were also set aside.

Source reference: p. 5

However, the amount of service tax and interest already paid by the appellant for the period from 1 June 2007 to March 2008 was properly payable and was therefore upheld for appropriation.

Source reference: p. 5
05

Holding

The appeal was partly allowed.

The Tribunal set aside the service-tax demand relating to the period prior to 1 June 2007, and also set aside the penalties imposed under the impugned orders.

Source reference: pp. 5–6

The appropriation of the service tax and interest paid by the appellant for the period from 1 June 2007 to March 2008 was upheld.

Source reference: pp. 5–6

Consequential relief, if any, was directed to follow in accordance with law.

Source reference: pp. 5–6
06

Acts & Sections Cited

5 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.

Finance Act, 19945

Section 76Section 78Section 77Section 65Section 73
CESTAT

Original Court PDF

Gearge Thomas Engg ContractorvsCochin-cce

CESTAT · September 03, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment