Delhi High Court

Conditional bank guarantees can only be invoked upon the occurrence of pre-defined contractual contingencies and defaults.

National Highways Infrastructure Development Corporation Ltd vs Sadguru Engineers And Allied Services Pvt Ltd & Ors.

Delhi High CourtJUDGMENT: May 19, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (NHIDCL) awarded a contract to Respondent No. 1 (the contractor) for National Highway road works under EPC mode

Source reference: p. 2

Pursuant to the agreement dated 07.02.2024, the Respondent furnished two performance bank guarantees and one mobilization bank guarantee totaling ₹8,63,46,694/-

Source reference: p. 2

Alleging contractual laxity, the Appellant issued a notice on 14.01.2026 demanding ₹8.496 crores (comprising vendor dues and recovery of released funds) and threatened to encash the bank guarantees upon non-compliance

Source reference: p. 2-3

The Respondent challenged this under Section 9 of the Arbitration and Conciliation Act, 1996. The learned Single Judge stayed the encashment on 24.02.2026, finding the guarantees to be "conditional"

Source reference: p. 3

The Appellant appealed this stay under Section 37(1)(b) of the Act

Source reference: p. 1-2
02

Issues

1. Whether the subject bank guarantees are unconditional or conditional in nature

Source reference: p. 6 / para. 21

2. Whether the contingencies required for the invocation of the bank guarantees were satisfied by the Appellant’s demand notice

Source reference: p. 6 / para. 21
03

Law Applied

The court applied Section 37(1)(b) regarding appeals and Section 9 regarding interim measures under the Arbitration and Conciliation Act, 1996

Source reference: p. 1-2

The court relied on the principles of contractual interpretation of bank guarantees, distinguishing between the "unconditional" nomenclature of a guarantee and specific clauses that restrict invocation to "default in due and faithful performance of obligations"

Source reference: p. 6, 7

The court also considered the principle of "equity and balance of convenience" in granting injunctions against bank guarantee encashment where the underlying demand does not relate to contractual performance

Source reference: p. 8
04

Reasoning

The Court examined the specific language of the bank guarantees. While the opening clauses used the words "unconditionally and irrevocably," a subsequent clause limited invocation to instances where the contractor "committed default in the due and faithful performance of all or any of its obligations"

Source reference: p. 6, para. 22-23

The Court reasoned that despite the "unconditional" label, the guarantees were substantively linked to pre-defined contingencies

Source reference: p. 7, para. 24

Upon reviewing the Appellant’s notice dated 14.01.2026, the Court found the demand was for "undisputed vendor dues" (a matter between the contractor and third parties) and "recovery of funds released on assurances"

Source reference: p. 7-8

It held these claims did not constitute a failure to perform contractual obligations as envisioned by the guarantee terms

Source reference: p. 8, para. 26-27
05

Holding

The Court upheld the Single Judge’s order and dismissed the appeal, finding no error in interdicting the bank guarantee encashment

It held that the purported claims were not relatable to contractual defaults

Source reference: p. 8, para. 26

With the consent of both parties, the Court appointed Hon’ble Mr. Justice Arun Mishra (Retd.) as the sole Arbitrator to adjudicate the disputes, granting parties liberty to seek further interim relief under Section 17 of the Act

Source reference: p. 8-9, para. 30-31
Delhi High Court

Original Court PDF

National Highways Infrastructure Development Corporation LtdvsSadguru Engineers And Allied Services Pvt Ltd & Ors.

Delhi High Court · May 19, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment