01Facts
The Appellant (NHIDCL) awarded a contract to Respondent No. 1 (the contractor) for National Highway road works under EPC mode
p. 2Pursuant to the agreement dated 07.02.2024, the Respondent furnished two performance bank guarantees and one mobilization bank guarantee totaling ₹8,63,46,694/-
p. 2Alleging contractual laxity, the Appellant issued a notice on 14.01.2026 demanding ₹8.496 crores (comprising vendor dues and recovery of released funds) and threatened to encash the bank guarantees upon non-compliance
pp. 2-3The Respondent challenged this under Section 9 of the Arbitration and Conciliation Act, 1996. The learned Single Judge stayed the encashment on 24.02.2026, finding the guarantees to be "conditional"
p. 3The Appellant appealed this stay under Section 37(1)(b) of the Act
pp. 1-202Issues
i.1. Whether the subject bank guarantees are unconditional or conditional in nature
p. 6 / para. 21ii.2. Whether the contingencies required for the invocation of the bank guarantees were satisfied by the Appellant’s demand notice
p. 6 / para. 2103Law Applied
The court applied Section 37(1)(b) regarding appeals and Section 9 regarding interim measures under the Arbitration and Conciliation Act, 1996
pp. 1-2The court relied on the principles of contractual interpretation of bank guarantees, distinguishing between the "unconditional" nomenclature of a guarantee and specific clauses that restrict invocation to "default in due and faithful performance of obligations"
p. 6, 7The court also considered the principle of "equity and balance of convenience" in granting injunctions against bank guarantee encashment where the underlying demand does not relate to contractual performance
p. 8Provisions in the judgment · 6 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 11Section 12Section 17Section 37Section 4
04Reasoning
The Court examined the specific language of the bank guarantees. While the opening clauses used the words "unconditionally and irrevocably," a subsequent clause limited invocation to instances where the contractor "committed default in the due and faithful performance of all or any of its obligations"
p. 6 · ¶ 22-23The Court reasoned that despite the "unconditional" label, the guarantees were substantively linked to pre-defined contingencies
p. 7 · ¶ 24Upon reviewing the Appellant’s notice dated 14.01.2026, the Court found the demand was for "undisputed vendor dues" (a matter between the contractor and third parties) and "recovery of funds released on assurances"
pp. 7-8It held these claims did not constitute a failure to perform contractual obligations as envisioned by the guarantee terms
p. 8 · ¶ 26-2705Holding
The Court upheld the Single Judge’s order and dismissed the appeal, finding no error in interdicting the bank guarantee encashment
p. 8 · ¶ 29It held that the purported claims were not relatable to contractual defaults
p. 8 · ¶ 26With the consent of both parties, the Court appointed Hon’ble Mr. Justice Arun Mishra (Retd.) as the sole Arbitrator to adjudicate the disputes, granting parties liberty to seek further interim relief under Section 17 of the Act
pp. 8-9 · ¶ 30-31Original Court PDF
National Highways Infrastructure Development Corporation LtdvsSadguru Engineers And Allied Services Pvt Ltd & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
