Facts
The Appellant (NHIDCL) awarded a contract to Respondent No. 1 (the contractor) for National Highway road works under EPC mode
Source reference: p. 2Pursuant to the agreement dated 07.02.2024, the Respondent furnished two performance bank guarantees and one mobilization bank guarantee totaling ₹8,63,46,694/-
Source reference: p. 2Alleging contractual laxity, the Appellant issued a notice on 14.01.2026 demanding ₹8.496 crores (comprising vendor dues and recovery of released funds) and threatened to encash the bank guarantees upon non-compliance
Source reference: p. 2-3The Respondent challenged this under Section 9 of the Arbitration and Conciliation Act, 1996. The learned Single Judge stayed the encashment on 24.02.2026, finding the guarantees to be "conditional"
Source reference: p. 3The Appellant appealed this stay under Section 37(1)(b) of the Act
Source reference: p. 1-2Issues
1. Whether the subject bank guarantees are unconditional or conditional in nature
Source reference: p. 6 / para. 212. Whether the contingencies required for the invocation of the bank guarantees were satisfied by the Appellant’s demand notice
Source reference: p. 6 / para. 21Law Applied
The court applied Section 37(1)(b) regarding appeals and Section 9 regarding interim measures under the Arbitration and Conciliation Act, 1996
Source reference: p. 1-2The court relied on the principles of contractual interpretation of bank guarantees, distinguishing between the "unconditional" nomenclature of a guarantee and specific clauses that restrict invocation to "default in due and faithful performance of obligations"
Source reference: p. 6, 7The court also considered the principle of "equity and balance of convenience" in granting injunctions against bank guarantee encashment where the underlying demand does not relate to contractual performance
Source reference: p. 8Reasoning
The Court examined the specific language of the bank guarantees. While the opening clauses used the words "unconditionally and irrevocably," a subsequent clause limited invocation to instances where the contractor "committed default in the due and faithful performance of all or any of its obligations"
Source reference: p. 6, para. 22-23The Court reasoned that despite the "unconditional" label, the guarantees were substantively linked to pre-defined contingencies
Source reference: p. 7, para. 24Upon reviewing the Appellant’s notice dated 14.01.2026, the Court found the demand was for "undisputed vendor dues" (a matter between the contractor and third parties) and "recovery of funds released on assurances"
Source reference: p. 7-8It held these claims did not constitute a failure to perform contractual obligations as envisioned by the guarantee terms
Source reference: p. 8, para. 26-27Holding
The Court upheld the Single Judge’s order and dismissed the appeal, finding no error in interdicting the bank guarantee encashment
It held that the purported claims were not relatable to contractual defaults
Source reference: p. 8, para. 26With the consent of both parties, the Court appointed Hon’ble Mr. Justice Arun Mishra (Retd.) as the sole Arbitrator to adjudicate the disputes, granting parties liberty to seek further interim relief under Section 17 of the Act
Source reference: p. 8-9, para. 30-31Original Court PDF
National Highways Infrastructure Development Corporation LtdvsSadguru Engineers And Allied Services Pvt Ltd & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in