Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Consent to Appoint Arbitrator Converts Section 9 Petition into Section 17 Application Before the Arbitral Tribunal

CARS24 Services Private Ltd. v. Dreams Car O.M.P.(I) (COMM.) 490/2025 & I.A. 2071/2026

Consent to Appoint Arbitrator Converts Section 9 Petition into Section 17 Application Before the Arbitral Tribunal. CARS24 Services Private Ltd. v. Dreams Car O.M.P.(I) (COMM.) 490/2025 & I.A. 2071/2026. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether the parties’ consensus to refer the dispute to arbitration and waive formal requirements under Section 11 and Section 21 of the Act warrants the appointment of a Sole Arbitrator by the Court

The court held

The Court appointed Mr. Essenese Obhan, Advocate, as the Sole Arbitrator under the aegis of DIAC

It also directed

The Section 9 petition was disposed of with directions to treat it as a Section 17 application before the Arbitrator, and the interim order dated 28.11.2025 was extended until the Arbitrator adjudicates the application

The Contempt Petition [CCP(O) 15/2026] was kept alive and listed for 29.04.2026 to allow the Respondent to file a reply

01Facts

The Petitioner, CARS24 Services Private Ltd., filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim reliefs against the Respondent, Dreams Car

¶ 1

The dispute arose from a Franchise Agreement dated 22.04.2024

¶ 3

The Petitioner sought to restrain the Respondent from alienating specific inventory and requested mandatory injunctions for the delivery of physical possession and protection of the inventory's condition

¶ 1

During the proceedings, both parties reached a consensus to refer the disputes to arbitration rather than adjudicate the Section 9 petition on merits

¶ 2

02Issues

i.Whether the parties’ consensus to refer the dispute to arbitration and waive formal requirements under Section 11 and Section 21 of the Act warrants the appointment of a Sole Arbitrator by the Court

¶ 4-5

ii.Whether the pending Section 9 petition should be converted into an application under Section 17 for adjudication by the newly appointed Arbitrator

¶ 13

iii.Whether contempt proceedings should be initiated against the Respondent for alleged violation of the interim order dated 28.11.2025

¶ 17-18

03Law Applied

The court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures by the Court

¶ 1

Section 17 of the Act, which empowers an Arbitral Tribunal to pass interim orders

¶ 13

Section 11 (appointment of arbitrators) and Section 21 (commencement of arbitral proceedings), noting that parties can expressly waive these formal procedural requirements

¶ 4

Sections 11 & 12 of the Contempt of Courts Act, 1971, regarding the enforcement of judicial orders

¶ 17

Provisions in the judgment · 7 · Linked ones open on LawLens

Contempt of Courts Act, 1971 Section 11Section 12

Arbitration and Conciliation Act, 1996 Section 9Section 11Section 12Section 17Section 21

04Reasoning

Given the parties’ agreement (ad idem) on the arbitration clause (Clause 21) and the appointment of an arbitrator, the Court determined that the commencement of proceedings should not be delayed

¶ 2-5

The Court calculated the approximate claim value at Rs. 2 crores to justify the reference

¶ 6-7

To ensure continuity of protection, the Court directed that the Section 9 petition be treated as a Section 17 application before the Tribunal

¶ 13

Regarding the contempt plea (CCP(O) 15/2026), the Court noted the Petitioner's allegation that four vehicles were alienated in breach of the 28.11.2025 stay order, and while the Respondent denied this, the Court scheduled a separate hearing for the contempt matter to allow for replies

¶ 18-21

05Holding

The Court appointed Mr. Essenese Obhan, Advocate, as the Sole Arbitrator under the aegis of DIAC

¶ 8-9

The Section 9 petition was disposed of with directions to treat it as a Section 17 application before the Arbitrator, and the interim order dated 28.11.2025 was extended until the Arbitrator adjudicates the application

¶ 13

The Contempt Petition [CCP(O) 15/2026] was kept alive and listed for 29.04.2026 to allow the Respondent to file a reply

¶ 19-21
Delhi High Court

Original Court PDF

CARS24 Services Private Ltd. v. Dreams Car O.M.P.(I) (COMM.) 490/2025 & I.A. 2071/2026

Delhi High Court · no citation

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment