Delhi High CourtContract LawProperty and Real Estate Law

Continuous readiness and willingness to perform is mandatory for the grant of specific performance.

Ravi Arorav.J.S. Malik

Continuous readiness and willingness to perform is mandatory for the grant of specific performance.. Ravi Arora vs J.S. Malik. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Plaintiff was ready and willing to perform his obligations under the contract?

The court held

The Court dismissed the plea for specific performance, holding that the Plaintiff failed to satisfy the mandatory requirements of Section 16(c) of the Specific Relief Act

It also directed

The Court partially decreed the suit by directing the Defendant to refund the part-sale consideration of ₹40,00,000/- to the Plaintiff. The refund is subject to 9% per annum simple interest, calculated from 22.11.2003 (the date the 45-day performance window expired) until the date of actual payment

01Facts

On 27.01.2003, the Plaintiff entered into an Agreement to Sell (“ATS”) with Mrs. Joginder Malik (predecessor-in-interest of the Defendant) for the purchase of a residential property in Safdarjung Development Area for ₹2.35 Crores

p. 2

The Plaintiff paid ₹40 Lakhs as part consideration

p. 3

Under Clause 2(b), the balance of ₹1.95 Crores was due by 15.05.2003 or within 45 days of the property being converted to freehold, whichever was later

p. 3

The property was converted to freehold on 09.08.2003

p. 19

Disputes arose regarding the intimation of conversion and demands for 12% interest for delayed payment

p. 9

Mrs. Malik died on 02.03.2004, leaving the Defendant as the sole heir

p. 2

The Plaintiff filed for specific performance in May 2004, alleging readiness and willingness, while the Defendant contended the Plaintiff lacked funds and breached the timeline

p. 15, 26

02Issues

i.1. Whether the Plaintiff was ready and willing to perform his obligations under the contract?

p. 2, para 2(i)

ii.2. Whether the Defendant was justified in rescinding the contract and forfeiting the sum of ₹40 Lakhs?

pp. 2, para 2(iii-iv)

iii.3. Whether the Plaintiff is entitled to a decree of specific performance?

p. 2, para 2(v)

03Law Applied

Section 16(c) of the Specific Relief Act, 1963, which requires the plaintiff to aver and prove continuous readiness (financial capacity) and willingness (conduct) from the date of contract until the decree

p. 33

Saradamani Kandappan v. S. Rajalakshmi, which established that in urban properties with galloping inflation, time is increasingly treated as a material factor, and a purchaser cannot use the "time is not of the essence" doctrine to cover laches or lack of readiness

pp. 40-42

In the absence of an express forfeiture clause or proof of actual loss, advance money/part-payment cannot be forfeited

pp. 46-47

Provisions in the judgment · 2 · Linked ones open on LawLens

Specific Relief Act, 1963 Section 16

Indian Contract Act, 1872 Section 55

04Reasoning

The Court found that the Plaintiff failed to establish "readiness" because he offered the balance consideration in fragmented installments through Pay Orders only starting in 2004, well beyond the 45-day window from the date he admittedly knew of the freehold conversion (07.10.2003)

pp. 37-39

Evidence from PW-2, PW-3, and PW-4 revealed the Plaintiff only began seeking loans/funds in early 2004, indicating he did not possess the funds at the contractually stipulated time

p. 39

The Plaintiff’s refusal to pay the 12% interest stipulated in Clause 6(a) for delays evidenced a lack of "willingness"

pp. 39-40

While the Court held the ATS was validly rescinded due to the Plaintiff’s breach, it ruled against the Defendant on forfeiture. Since the ATS lacked a specific forfeiture clause and the Defendant admitted during cross-examination that no such clause existed, the ₹40 Lakhs was treated as part-payment rather than earnest money, necessitating its refund to prevent unjust enrichment

pp. 47-48

05Holding

The Court dismissed the plea for specific performance, holding that the Plaintiff failed to satisfy the mandatory requirements of Section 16(c) of the Specific Relief Act

p. 48, 50

The Court partially decreed the suit by directing the Defendant to refund the part-sale consideration of ₹40,00,000/- to the Plaintiff. The refund is subject to 9% per annum simple interest, calculated from 22.11.2003 (the date the 45-day performance window expired) until the date of actual payment

pp. 49-50
Delhi High Court

Original Court PDF

Ravi AroravsJ.S. Malik

Delhi High Court · April 30, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment