Delhi High CourtContract LawAdministrative and Public Law

Contractual default in license fee payments justifies termination and forfeiture despite disputes over site area dimensions.

Giriraj Enterprisesv.Municipal Corporation Delhi And Ors

Contractual default in license fee payments justifies termination and forfeiture despite disputes over site area dimensions.. Giriraj Enterprises vs Municipal Corporation Delhi And Ors. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the allotted parking site included all four Gates (1 to 4) or was restricted to Gate Nos. 1 and 2 as per the countersigned site map.

The court held

The Court held that the parking site was validly restricted to Gate Nos. 1 and 2 and that the Appellant had no justification for withholding dues.

It also directed

The termination of the contract and forfeiture of the security deposit/FDR were upheld as the Appellant was in clear breach of contractual terms and judicial directions.

The Court dismissed the appeal and upheld the judgment of the learned Single Judge; the setting aside of the blacklisting order remained undisturbed.

01Facts

The Appellant was awarded a contract by Respondent No. 1 (MCD) for a parking site at Red Fort Metro Station Gate Nos. 1 to 4 following an e-tender.

pp. 2, para 5.1-5.2

Possession was handed over on 16.12.2024.

p. 3, para 5.5

The Appellant subsequently requested facilities and claimed they were unable to operate at Gate Nos. 3 and 4 due to police restrictions.

pp. 4-6, para 5.6-5.12

MCD issued Show Cause Notices regarding unauthorized parking and outstanding dues.

pp. 5-6, para 5.10-5.13

After a previous Writ Petition (W.P.(C) 9024/2025) directed the Appellant to deposit ₹10,00,000—which they failed to do—MCD issued an order on 13.08.2025 terminating the contract, forfeiting the security deposit, and blacklisting the Appellant.

pp. 7-8, para 5.14-5.16

The learned Single Judge upheld the termination and forfeiture but set aside the blacklisting, granting liberty for fresh proceedings.

p. 2, para 3

02Issues

i.1. Whether the allotted parking site included all four Gates (1 to 4) or was restricted to Gate Nos. 1 and 2 as per the countersigned site map.

pp. 9, para 7-8

ii.2. Whether the termination of the contract and forfeiture of the security deposit were legally valid in light of the Appellant's defaults in license fees and non-compliance with court-ordered deposits.

p. 15, para 25

03Law Applied

The doctrine of acquiescence and estoppel, noting that a party cannot challenge the extent of a site after accepting possession without protest.

p. 11, para 13

Principles laid down in Kulja Industries Ltd. v. Western Telecom Project BSNL, (2014) 15 SCC 731, which require adherence to natural justice and proportionality regarding blacklisting.

p. 15, para 24

The principle that non-compliance with specific judicial directions (e.g., a pre-deposit of ₹10,00,000) justifies the withdrawal of interim protection and subsequent coercive administrative action.

pp. 14, para 22-23

04Reasoning

The Court examined the original record and found that the site map annexed to the possession letter, which was countersigned by the Appellant, specifically designated the area as "RED FORT METRO GATE 1 AND 2".

pp. 12-13, para 17-18

The Court reasoned that despite the nomenclature mentioning Gates 1-4, the physical boundaries were clearly defined at the time of handover, and the Appellant raised no contemporaneous objection.

pp. 13, para 19-20

The Court further noted that the Appellant was in breach of contract for failing to pay monthly license fees and penalties, and failed to comply with the High Court's earlier direction to deposit ₹10,00,000.

p. 14, para 22

Since the e-tender terms provided for termination and forfeiture upon default, the MCD's actions were found to be within the scope of the agreement.

pp. 15-16, para 23-28

05Holding

The Court held that the parking site was validly restricted to Gate Nos. 1 and 2 and that the Appellant had no justification for withholding dues.

p. 16, para 28

The termination of the contract and forfeiture of the security deposit/FDR were upheld as the Appellant was in clear breach of contractual terms and judicial directions.

p. 16, para 29

The Court dismissed the appeal and upheld the judgment of the learned Single Judge; the setting aside of the blacklisting order remained undisturbed.

pp. 15-16, para 24-29
Delhi High Court

Original Court PDF

Giriraj EnterprisesvsMunicipal Corporation Delhi And Ors

Delhi High Court · May 15, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment