01Facts
The petitioner, a civil contractor, was awarded a contract by the M.P. Rural Road Development Authority (MPRRDA) in December 2022 for the maintenance of a rural road in District Rewa.
¶ 2(i)Following disputes regarding pre-existing road defects and project delays, the petitioner invoked the contractual dispute resolution mechanism.
¶ 2(iii)-(iv)However, on May 4, 2026, the respondent terminated the contract under Clause 52 and debarred the petitioner from future tenders for two years.
¶ 2(v)The petitioner challenged this order under Article 226 of the Constitution, alleging a violation of natural justice as no specific show-cause notice was issued regarding the debarment.
¶ 302Issues
i.1. Whether the writ petition is maintainable against the termination of a contract when an alternative statutory remedy is available.
¶ 4ii.2. Whether the petitioner’s grievance regarding debarment/blacklisting should be adjudicated by the court or through administrative representation.
¶ 403Law Applied
The court applied Article 226 of the Constitution of India regarding the exercise of writ jurisdiction in the presence of alternative remedies.
¶ 1It relied on the principle that contractual terminations are subject to specialized arbitration under the Madhya Pradesh Arbitration Tribunal.
¶ 4Principles of natural justice and administrative law concerning debarment, which require a specific show-cause notice and the right to be heard before a contractor is blacklisted.
¶ 3-404Reasoning
Regarding the termination, the court observed that the petitioner has an effective alternative remedy before the Madhya Pradesh Arbitration Tribunal, making the writ petition unsuitable for that specific relief.
¶ 4Regarding the two-year debarment, the court noted the petitioner’s argument that no specific notice for blacklisting was provided.
¶ 3The court determined that the issue of blacklisting should first be addressed through a formal representation to the Engineer-in-Chief/Respondent No. 1, who is obligated to follow state policies and contractual terms.
¶ 405Holding
The court held that the challenge to the termination must be pursued before the Madhya Pradesh Arbitration Tribunal.
¶ 4The court directed the petitioner to submit a representation/appeal to the respondent No. 1 regarding the debarment, who is ordered to decide the matter in accordance with the law and state blacklisting policies.
¶ 4The court disposed of the writ petition without interfering with the termination order.
¶ 5Original Court PDF
Neeraj DwivedivsM.P Rural Road Development Authority
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
