Facts
The petitioner was engaged under Agreement No. 38/MBD/2015-16 to construct and maintain two roads for five years.
Source reference: no citationThe construction work was recorded in the Measurement Book, and the respondents admitted that it was completed and that ₹6,83,45,113 had been paid towards construction costs.
Source reference: para. 2–3, 7The parties disputed the maintenance work and related payments: the respondents said the petitioner had maintained the roads for only three years, while the petitioner claimed payment of outstanding contractual dues, including maintenance charges, GST and security deposit.
Source reference: para. 7–12The petitioner also challenged the recorded completion date for part of the work.
Source reference: para. 1(VI)The writ petition sought payment and related reliefs.
Source reference: para. 1Issues
1. Whether the petitioner was entitled to payment of admissible maintenance dues for the disputed 150-metre portion, and how the completion date affected calculation of the maintenance period.
Source reference: para. 14–172. Whether the Court should direct payment of the petitioner’s other claimed contractual dues, including GST, interest and security deposit.
Source reference: para. 1, 8, 11–12Law Applied
The Court applied the terms of the parties’ agreement, the applicable rules, and the departmental records—including the Measurement Book—to determine the admissible maintenance dues and the relevant completion date.
Source reference: para. 16–17The judgment cites no statute, regulation, or precedent, and states no broader legal doctrine governing contractual claims.
Source reference: no citationReasoning
The Court found that the construction had been completed and recorded, and that the remaining dispute concerned a 150-metre portion and the consequent maintenance period.
Source reference: para. 14–16Because that portion was also completed, the Court directed the respondents to determine the admissible maintenance dues by verifying the Measurement Book and other departmental records. It further held that the actual completion date must be used to calculate the five-year maintenance period.
Source reference: para. 16–17The Court did not separately adjudicate the claims for GST, interest, security deposit, or other reliefs.
Source reference: no citationHolding
The Court directed the respondents to verify the relevant records and pay the admissible maintenance dues relating to the 150-metre portion, in accordance with the agreement and applicable rules, after completion of the stipulated five-year period.
Payment was to be made within three months of receipt or production of the order.
Source reference: para. 17The judgment did not grant the claimed GST, interest, security-deposit or litigation-cost reliefs.
Source reference: no citationOriginal Court PDF
M/s Jai Mata Di Construction CompanyvsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
