Facts
The petitioners are the recorded owners of land at Khasra No. 110/8, area 0.54 dismil, situated in village Sirgitti, Bilaspur
Source reference: para. 2The land was acquired for the construction of a railway overbridge, and an award was passed on 22-06-2020, followed by a supplementary award on 13-06-2021
Source reference: para. 2Despite these awards, the petitioners claimed that no compensation had been paid
Source reference: para. 2Consequently, the petitioners applied for the disbursement of the award and the demarcation of the subject land.
Source reference: para. 2Although the Tahsildar (Respondent No. 5) constituted a team of revenue officers for demarcation on 12-11-2025 and a notice was issued by the Revenue Inspector on 05-01-2026, the demarcation process was never completed
Source reference: para. 2, 5The petitioners approached the High Court under Article 226 of the Constitution seeking directions for the disbursement of the award and the completion of the demarcation
Source reference: para. 1Issues
Whether the Court should exercise its writ jurisdiction to direct the revenue authorities to complete the demarcation of the acquired land within a stipulated timeframe to facilitate the disbursement of the compensation award
Source reference: para. 2, 5Law Applied
The court exercised its jurisdiction under Article 226 of the Constitution of India, which empowers the High Court to issue writs for the enforcement of legal rights and the performance of statutory duties by public authorities
Source reference: para. 1The court relied on the principle that administrative and revenue authorities are duty-bound to execute their own orders (such as demarcation orders) within a reasonable timeframe, especially when such inaction hinders the realization of compensation for land acquisition
Source reference: para. 5Reasoning
The court observed a "sorry state of affair" regarding the administrative delay, noting that despite the Tahsildar constituting a team for demarcation in November 2025 and issuing notices in January 2026, the process remained stalled without justification
Source reference: para. 5Since the respondents expressed no objection to the limited prayer for a time-bound demarcation, the court determined that judicial intervention was necessary to resolve the impasse
Source reference: para. 3, 5The court reasoned that for the award amount to be properly processed and the rights of the parties to be settled, the physical boundaries of the acquired land must first be legally established through the pending demarcation process
Source reference: para. 5, 6Holding
The High Court disposed of the writ petition by directing Respondents No. 4 (Land Acquisition Officer) and No. 5 (Tahsildar) to complete the demarcation of the subject land in accordance with the law within 30 days of receiving the order
the court directed that representatives of the South East Central Railway (Respondents No. 1 to 3) must be notified and kept present during the demarcation process to ensure transparency and finality
Source reference: para. 6No specific order was passed regarding the immediate disbursement of the award, as it remained contingent upon the completion of the directed demarcation
Source reference: para. 7Original Court PDF
SATYA NARAYAN DHANKARvsUNION OF INDIA
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in