Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Court May Extend Arbitral Mandate Under Section 29A Based on Consensus and Sufficient Cause

Ahluwalia Contracts (India) Ltdv.Delhi Agricultural Marketing Board

Court May Extend Arbitral Mandate Under Section 29A Based on Consensus and Sufficient Cause. Ahluwalia Contracts (India) Ltd vs Delhi Agricultural Marketing Board. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the mandate of the learned Sole Arbitrator should be extended under Section 29A of the Arbitration and Conciliation Act, 1996, to conclude final arguments and render an award

The court held

The Court answered the issue in the affirmative, allowing the petition.

It also directed

The Court extended the mandate of the Sole Arbitrator for a period of twelve months, effective until May 31, 2027, and regularized the period between the expiry of the previous mandate and the date of the current order.

All pending applications were disposed of accordingly

01Facts

The Petitioner and Respondent entered into a Letter of Commencement on September 13, 2019

p. 2 · ¶ 2

Following disputes, a Sole Arbitrator was appointed by the High Court of Delhi on January 17, 2023

p. 1 · ¶ 1

Pleadings were completed on July 25, 2024, and evidence was subsequently led

p. 2 · ¶ 3

The mandate was previously extended once until October 31, 2025

p. 2 · ¶ 5

The Petitioner sought a further extension as the proceedings reached the stage of final arguments but exceeded the statutory timeline

p. 2 · ¶ 6

The Respondent expressed no objection to the extension

p. 2 · ¶ 7

02Issues

i.1. Whether the mandate of the learned Sole Arbitrator should be extended under Section 29A of the Arbitration and Conciliation Act, 1996, to conclude final arguments and render an award

p. 2 · ¶ 6

03Law Applied

The Court applied Section 29A of the Arbitration and Conciliation Act, 1996, which mandates that an award must be made within twelve months of the completion of pleadings, allowing for a six-month extension by party consent and further extensions by the Court upon showing "sufficient cause"

p. 3 · ¶ 10

It further relied on the precedent set by the Hon’ble Supreme Court in Rohan Builders (India) Private Limited v. Berger Paints India Limited (2024), which clarified the scope, ambit, and mandatory nature of Section 29-A regarding the termination and extension of an arbitrator's mandate

p. 4 · ¶ 11

Provisions in the judgment · 2 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 11Section 23

04Reasoning

The Court observed that the arbitral proceedings are currently at the advanced stage of final arguments

p. 2 · ¶ 3

It determined that extending the mandate was in the "interest of justice" to ensure "continuity and consistency" in the adjudication of the dispute

p. 2 · ¶ 9

The Court noted that since both parties were ad idem (in agreement) regarding the necessity of the extension, there was no legal impediment to granting the relief

p. 2 · ¶ 9

By applying the "sufficient cause" standard under Section 29A(5), the Court found that the procedural progress (reaching final arguments) justified a further period to prevent the frustration of the effort already invested in the arbitration

p. 4 · ¶ 12-13

05Holding

The Court answered the issue in the affirmative, allowing the petition.

p. 4 · ¶ 13

The Court extended the mandate of the Sole Arbitrator for a period of twelve months, effective until May 31, 2027, and regularized the period between the expiry of the previous mandate and the date of the current order.

p. 4 · ¶ 13

All pending applications were disposed of accordingly

p. 4 · ¶ 14
Delhi High Court

Original Court PDF

Ahluwalia Contracts (India) LtdvsDelhi Agricultural Marketing Board

Delhi High Court · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment