Facts
The petitioners challenged SECL’s order dated 25 March 2025 insofar as it sought recovery of an additional financial impact of ₹19.13 crore, and challenged the invocation of a bank guarantee on the same date.
Source reference: para. 2They also sought repayment of the amount realized under the guarantee, release of security, and payment of outstanding dues.
Source reference: para. 2An interim order had been granted on 6 May 2025.
Source reference: para. 4During the hearing, petitioners’ counsel accepted that the dispute could be pursued through arbitration under Clause 13 of the General Conditions of Contract (GCC), while seeking continuation of interim protection until an application under Section 9 of the Arbitration and Conciliation Act, 1996 was filed.
Source reference: paras. 3–4Issues
Whether the petitioners should be permitted to pursue the contractual dispute through arbitration rather than obtain adjudication of the claims in the writ petition.
Source reference: paras. 3, 6Whether protection should be granted to enable the petitioners to seek interim relief under Section 9 of the Arbitration and Conciliation Act, 1996.
Source reference: paras. 4–6Law Applied
Clause 13 of the GCC provides for redressal through arbitration, under the Arbitration and Conciliation Act, 1996 as amended in 2015, in disputes involving parties other than Government agencies.
Source reference: para. 3Section 9 of the Act provides a route to seek interim measures from the designated court; the court did not determine the merits of any such application and directed that it be considered independently.
Source reference: paras. 5, 8Reasoning
The petitioners accepted the contractual arbitration mechanism, and the respondents did not object to their pursuing that remedy.
Source reference: paras. 3, 5In light of that position, the Court disposed of the writ petition without deciding the legality of the recovery or bank-guarantee invocation.
Source reference: para. 6It allowed time for the petitioners to approach the designated court under Section 9 and limited its protection to a direction against coercive action for 45 days.
Source reference: para. 6Any Section 9 application was to be decided on its own merits, without influence from the High Court’s observations or directions.
Source reference: para. 8Holding
The writ petition was disposed of, with liberty to the petitioners to pursue remedies under the Arbitration and Conciliation Act, 1996 and to apply under Section 9 before the designated court within 30 days.
The Court directed that no coercive action be taken against the petitioners for 45 days to enable them to seek that remedy.
Source reference: para. 6It did not adjudicate the underlying claims or grant the requested refund, interest, or payment of dues.
Source reference: paras. 6–8Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19961
Original Court PDF
M/S S. S. MINING JV COMPANYvsSOUTH EASTERN COALFIELDS LTD.,
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
