Facts
The Petitioner, Sunsure Energy Private Limited, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim relief against Respondent No. 1 (Vikram Solar Limited) and Respondent No. 2.
Source reference: p. 1-2The dispute arose from a Domestic Module Supply Agreement dated October 14, 2025, which contained a detailed arbitration clause (Clause 18).
Source reference: para. 2The Petitioner specifically sought to restrain the encashment or negotiation of a Letter of Credit (No. INLCU0100250674) or, alternatively, prayed that any realized amounts be deposited in court pending arbitration.
Source reference: para. 1During the proceedings, both parties reached a consensus to refer their disputes to a three-member Arbitral Tribunal.
Source reference: para. 3-4Issues
1. Whether the Court should grant interim protection regarding the Letter of Credit under Section 9 of the Act or refer the prayer to a newly constituted Arbitral Tribunal.
Source reference: para. 14-152. Whether the Court can dispense with separate Section 11 proceedings to appoint an Arbitral Tribunal when parties reach a consensus during Section 9 hearings.
Source reference: para. 7Law Applied
The Court applied Section 9 of the Arbitration and Conciliation Act, 1996, which allows parties to seek interim measures before or during arbitral proceedings.
Source reference: p. 1Clause 18 of the parties' Agreement, which mandated a three-member tribunal and designated Delhi as the seat of arbitration with exclusive jurisdiction in Delhi courts.
Source reference: para. 2The Court exercised its discretionary power to bypass the procedural requirement of a separate Section 11 application for arbitrator appointment when parties are ad idem on the reference to arbitration.
Source reference: para. 7Reasoning
The Court did not rule on the merits of the interim reliefs regarding the Letter of Credit. Instead, it noted the consensus between the Senior Counsel of both parties to resolve the dispute via arbitration.
Source reference: para. 3To ensure the "commencement of arbitral proceedings... should not be unduly delayed," the Court accepted the nominations of two former Chief Justices as party-appointed arbitrators.
Source reference: para. 5-7The Court determined that the Section 9 petition should be converted into a Section 17 application, thereby shifting the responsibility of deciding interim protection to the Arbitral Tribunal once constituted.
Source reference: para. 14This approach prioritizes party autonomy and the efficiency of the arbitral process over protracted litigation in court.
Source reference: para. 7-9Holding
The Court disposed of the petition by appointing Hon’ble Mr. Justice (Retd.) Dr. S. Muralidhar and Hon’ble Mr. Justice (Retd.) Vipin Sanghi as nominee arbitrators for the Petitioner and Respondents, respectively.
The Court held that the Section 9 petition shall be treated as an application under Section 17 to be decided by the Arbitral Tribunal expeditiously.
Source reference: para. 14-15All rights and contentions were kept open, and the requirement for a separate Section 11 petition was dispensed with.
Source reference: para. 7, 12Original Court PDF
Sunsure Energy Private LimitedvsVikram Solar Limited & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in