Facts
The lands of the respondent-claimants in Village Bhavda, Ahmedabad, were acquired for the Narmada Canal project.
Source reference: no citationAn award under Section 11 of the Land Acquisition Act was passed on 30.08.1993.
Source reference: p. 4Upon the claimants' prayer for enhancement, the Reference Court increased the compensation on 30.11.1999.
Source reference: p. 4While the State deposited certain amounts in 2003, the claimants filed recovery applications in 2011 alleging a shortfall in the principal amount and claiming interest on delayed payment.
Source reference: p. 5The Special Judge (LAQ) found a shortfall of ₹20,505 and directed the State to pay this amount along with 15% interest for a delay of 220 months (from 22.05.2003 to 16.10.2021).
Source reference: p. 13-14The State challenged this order, arguing it amounted to "interest upon interest".
Source reference: p. 7Issues
1. Whether the Reference Court erred in directing the payment of 15% interest on the delayed payment of the remaining compensation amount for a period of 220 months under the Land Acquisition Act.
Source reference: p. 8 / para. 082. Whether the court has the power to award interest on equitable grounds or in a manner other than that prescribed by the statute.
Source reference: p. 12 / para. 13Law Applied
Section 28 mandates interest on excess compensation at 9% p.a. for the first year and 15% p.a. thereafter from the date of possession.
Source reference: p. 10Section 34 similarly dictates interest for non-payment or non-deposit of compensation on or before taking possession.
Source reference: p. 10Union of India v. Budh Singh (1995) 6 SCC 233, which held that the statute covers the entire field of interest liability and courts cannot grant interest in excess of statutory rates.
Source reference: p. 12State of Himachal Pradesh v. Dharam Das (1995) 5 SCC 683, which established that equitable considerations have no role in statutory compensation and interest determination.
Source reference: p. 12Reasoning
The Court noted that the acquiring body was required to deposit ₹1,10,942 but only deposited ₹90,438 on 22.05.2003, resulting in a shortfall of ₹20,505.
Source reference: p. 13The High Court found that the Special Judge had correctly identified the unpaid principal balance.
Source reference: p. 13Since this "part thereof" of the compensation remained unpaid for over a year after possession, the statutory proviso of Section 28 (and Section 34) automatically triggered the 15% interest rate.
Source reference: p. 10-11The Court reasoned that because the Land Acquisition Act is a self-contained code, the statutory mandate for 15% interest on delayed "excess or part thereof" must be strictly followed regardless of the delay in claimants filing the recovery application.
Source reference: p. 13-14Holding
The High Court held that the Special Judge’s direction to pay the principal shortfall of ₹20,505 plus ₹56,389 (15% interest for 220 months) was just, proper, and in accordance with Section 28 of the Act.
The High Court dismissed the writ petitions and all connected Special Civil Applications, affirming there was no error of law in applying the statutory interest rate to the delayed payment of the remaining compensation.
Source reference: p. 14Original Court PDF
STATE OF GUJARATvsAMBALAL PARSHOTTAMDAS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in