Gauhati High CourtAdministrative and Public LawConstruction Law

Courts must exercise judicial restraint in tender matters and avoid interfering once project execution has significantly commenced.

Diganta Borahv.The State Of Assam And 4 Ors

Courts must exercise judicial restraint in tender matters and avoid interfering once project execution has significantly commenced.. Diganta Borah vs The State Of Assam And 4 Ors. Gauhati High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Single Judge was justified in interfering with a public tender process after work had significantly progressed and the bid evaluation was performed by experts.

The court held

The Court answered the issues in the negative, holding that the Single Judge's interference was improper.

It also directed

The Division Bench set aside the impugned judgment dated 27.09.2024 and upheld the original work orders

The Court directed the appellants to complete the entire work as per specifications within the extended time limit ending on 30.06.2026

All writ appeals were allowed

01Facts

The Animal Husbandry and Veterinary Department, Assam, invited tenders for construction works in Nalbari district under a two-bid system

p. 9

The appellants emerged as the lowest (L-1) bidders, quoting rates more than 15% below the Detailed Schedule Rate (DSR)

p. 9

Per Clause 2.A.(g) of the bid document, they submitted rate analyses and justifications, which were subsequently validated by a departmental engineer’s physical verification report

pp. 9-10

Based on this, work orders were issued on 06.01.2024

p. 10

A private respondent (an unsuccessful bidder) challenged these allotments via writ petitions

p. 10

A Single Judge set aside the work orders, finding the verification process "pre-determined and biased" due to alleged irregularities in GSTIN quotes, identical photographs used for different sites, and lack of geo-tagging

pp. 11-12

The State and the contractors appealed this decision

p. 8

02Issues

i.1. Whether the Single Judge was justified in interfering with a public tender process after work had significantly progressed and the bid evaluation was performed by experts.

pp. 12-13

ii.2. Whether technical irregularities in supporting documents (e.g., GSTIN of a supplier or non-geo-tagged photos) are sufficient to invalidate a contract awarded to the lowest bidder.

pp. 13-14

03Law Applied

The Court applied the principle of judicial restraint in tender matters, emphasizing that courts should not sit as an appellate authority over the decision-making process of experts unless it is infested with mala fides or unreasonableness

p. 13

It relied on the precedents of Afcon Infrastructure Limited v. Nagpur Metro Rail Corporation Limited & Anr. (2016) 16 SCC 818 and Bharat Coking Coal Limited v. A.R.M. Dev Prabha & Ors. (2020) 16 SCC 759, which establish that the author of the tender is the best judge of its interpretation and that least interference is advisable in commercial matters

p. 14

Provisions in the judgment · 1

Johannesburg Declaration On Sustainable Development RIDF-XXVII

04Reasoning

The Court reasoned that the Bid Process Management Committee, comprised of domain experts, had followed the procedure delineated in Clause 2.A.(g) of the tender document by requiring and accepting rate justifications and physical verification

p. 15

The Court found the Single Judge’s scrutiny of GSTIN numbers belonging to third-party material suppliers (Maa Enterprise) to be irrelevant, as the supplier's registration was not a mandatory criterion for the bidder’s eligibility

p. 13

the Court noted that the challenge was raised by an unsuccessful bidder whose offer was significantly higher, and that interference at a stage where substantial construction had already commenced (allegedly 70%) was "wholly unjustified" as it halted public work

pp. 14-15

The court observed that the allegations of collusion were "overarching" and lacked the requisite proof to overcome the presumption of regularity in expert committee decisions

p. 15

05Holding

The Court answered the issues in the negative, holding that the Single Judge's interference was improper.

pp. 15-16

The Division Bench set aside the impugned judgment dated 27.09.2024 and upheld the original work orders

pp. 15-16

The Court directed the appellants to complete the entire work as per specifications within the extended time limit ending on 30.06.2026

p. 16

All writ appeals were allowed

p. 16
Gauhati High Court

Original Court PDF

Diganta BorahvsThe State Of Assam And 4 Ors

Gauhati High Court · June 04, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment