Facts
The Petitioner was allotted SKO/LDO Depot site no. 2, Vasant Vihar, New Delhi, for storing petroleum products.
Source reference: p. 2, 4Following the ban on kerosene in Delhi, the Petitioner sought to establish a CNG facility and obtained a Letter of Intent from Indraprastha Gas Limited and a No-Objection Certificate (NOC) from the Respondent (DDA) in 2016.
Source reference: p. 4-8On 14.11.2018, the DDA issued a show-cause notice (SCN) alleging illegal construction and encroachment on public land.
Source reference: p. 12Although the Petitioner replied on 24.01.2019 stating the unauthorized construction was removed, the DDA passed a cancellation order on 06.02.2019/07.02.2019, claiming no reply was filed.
Source reference: p. 14-16In 2022, the Court directed DDA to consider the Petitioner’s representation for an alternative site.
Source reference: p. 2-3DDA rejected this on 19.01.2023, asserting the site fell within a "District Park" (where CNG stations are prohibited under MPD-2021) and that the Petitioner did not meet policy criteria for relocation.
Source reference: p. 21-23Issues
1. Whether the show-cause notice and subsequent cancellation order were void for violating the principles of natural justice and being cryptic in nature.
Source reference: p. 18, 212. Whether the Petitioner is entitled to the allotment of an alternative site under the extant policy following the classification of the original site as a District Park.
Source reference: p. 23-24Law Applied
Principles of natural justice regarding the adequacy of a show-cause notice, relying on Gorkha Security Services v. Govt. (NCT of Delhi) (2014) 9 SCC 105, which mandates that a noticee must be informed of precise allegations and the proposed penalty to ensure a meaningful opportunity to respond.
Source reference: p. 19-20Clause 12.13 of the Master Plan for Delhi (MPD-2021), which prohibits CNG stations in developed district parks.
Source reference: p. 21Reasoning
The Court found that the Respondent’s cancellation order was procedurally flawed as it claimed no reply was received, whereas the DDA’s own counter-affidavit and a physical receipt confirmed the Petitioner had filed a reply on 24.01.2019.
Source reference: p. 17-18The Court characterized the SCN as "cryptic" and "devoid of any detail," failing to specify the nature or extent of the alleged encroachment, thus rendering it a mere "empty formality."
Source reference: p. 18-21Regarding the alternative site, the Court rejected DDA's contention that the Petitioner did not meet the policy criteria (which required the applicant to be an operational licensee); the Court reasoned that since the initial license termination was illegal, the Petitioner must be deemed a valid licensee and the site considered operational.
Source reference: p. 23-24Holding
The Court held that the Petitioner prima facie meets the criteria for an alternative site and directed the Respondent to consider the case afresh and pass a reasoned order within eight weeks.
The Court allowed both writ petitions and quashed the show-cause notice dated 14.11.2018, the cancellation order dated 06.02.2019/07.02.2019, and the speaking order dated 19.01.2023.
Source reference: p. 21, 24The interim stay on dispossession was extended until the fresh order is passed and for one week thereafter; additionally, the DDA was directed to file an affidavit regarding its responsibility to maintain the park once possession is retrieved.
Source reference: p. 24Original Court PDF
M/S Shiv Dayal Singh Oil CompanyvsDelhi Development Authority
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in