Madhya Pradesh High Court
Administrative and Public LawContract Law

CUF shortfall alone cannot justify termination of hydel project lease without examining water supply, rules Madhya Pradesh High Court

Madhav Infra Projects Limited A Company Incorporated Under The Compnies Act vs M.P. Madhya Kshetra Vidyut Vitran Co. Limited

Madhya Pradesh High CourtJUDGMENT: September 07, 20264 MIN READSOURCE JUDGMENT
CUF shortfall alone cannot justify termination of hydel project lease without examining water supply, rules Madhya Pradesh High Court. Madhav Infra Projects Limited A Company Incorporated Under The Compnies Act vs M.P. Madhya Kshetra Vidyut Vitran Co. Limited. Madhya Pradesh High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner operated and maintained the Chambal Mini Hydel Project, Morena, comprising three 600 kW generating units, under a 30-year Lease Agreement dated 24.03.2014 executed pursuant to the tender process and Letter of Award dated 07.02.2014.

Source reference: paras. 3–4

Article 10.3 required the O&M contractor to achieve a minimum annual Capacity Utilisation Factor (CUF) of 30%, while Article 10.4.2 provided for proportionate reduction of the O&M rate if the CUF fell below that benchmark.

Source reference: paras. 13–14

The respondents alleged that the petitioner had failed to achieve the prescribed CUF for six consecutive years and issued notices dated 03.11.2021 and 06.04.2022. The petitioner replied that generation depended upon adequate water quantity and discharge, and that the shortfall resulted from inadequate and irregular water supply, canal operations, variation in water levels and other circumstances beyond its control.

Source reference: paras. 5–6, 42

By order dated 30.05.2022, respondent No. 1 terminated the Lease Agreement. The petitioner challenged the termination and the preceding notices under Article 226, alleging arbitrariness, non-application of mind and violation of natural justice.

Source reference: para. 2
02

Issues

Whether a mere numerical shortfall in CUF below the contractual minimum could, by itself, constitute an attributable Event of Default justifying termination of the long-term Lease Agreement, without examining whether the shortfall was caused by inadequate or interrupted water supply?

Source reference: para. 15

Whether the respondents’ failure to consider and give reasons for rejecting the petitioner’s specific defence regarding water availability rendered the termination arbitrary and violative of Article 14 of the Constitution?

Source reference: paras. 42–44, 61

Whether the existence of a contractual dispute-resolution mechanism barred the maintainability of the writ petition challenging the State instrumentality’s termination decision?

Source reference: paras. 12, 57–60
03

Law Applied

The Court applied Article 14 of the Constitution, which prohibits arbitrary State action, and the principle that judicial review in contractual matters is available where the decision-making process is arbitrary, irrational, unreasonable, biased or affected by non-application of mind.

Source reference: paras. 48–55

It relied on Silppi Constructions Contractors v. Union of India, (2020) 16 SCC 489; Air India Ltd. v. Cochin International Airport Ltd., (2000) 2 SCC 617; Master Marine Services (P) Ltd. v. Metcalfe & Hodgkinson (P) Ltd., (2005) 6 SCC 138; and Joshi Technologies International Inc. v. Union of India, (2015) 7 SCC 728, for the limited but recognised scope of judicial review over State contracts.

Source reference: paras. 48–55

M.P. Power Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd., (2023) 2 SCC 703, was applied for the principle that contractual obligations do not exempt State action from the requirements of non-arbitrariness under Article 14.

Source reference: para. 58

The Court relied on S.N. Mukherjee v. Union of India, (1990) 4 SCC 594, for the duty of administrative authorities to record reasons, thereby excluding arbitrariness and ensuring fairness.

Source reference: para. 43

Sections 32 and 37 of the Indian Contract Act, 1872 were invoked by analogy to hold that an obligation dependent upon an external and uncertain circumstance cannot be treated as an unexcused breach without first determining whether that circumstance occurred.

Source reference: paras. 34–36
04

Reasoning

The Court distinguished between a numerical CUF shortfall and an attributable contractual breach. Although Article 10.3 imposed a minimum CUF obligation, the contract did not state that every shortfall, irrespective of cause, automatically constituted an Event of Default warranting termination.

Source reference: para. 16

Article 10.4.2 contemplated a proportionate reduction in the O&M rate where CUF fell below 30%, indicating a graded financial consequence and militating against treating every shortfall as an automatic ground for termination.

Source reference: paras. 17, 46

Because hydel generation necessarily depends upon adequate water availability and discharge, the respondents were required to determine whether the shortfall resulted from deficient operation or maintenance, technical defects and avoidable shutdowns, or from inadequate water supply beyond the petitioner’s control.

Source reference: paras. 19, 33–35

The respondents did not inspect the plant or determine whether the CUF deficiency arose from operational or technical failures. Instead, they proceeded substantially on the admitted CUF figures and relied on the “as is where is” clause without addressing the petitioner’s specific defence regarding water availability.

Source reference: paras. 42–45, 63–64

This amounted to non-application of mind to a material issue and failure to provide a reasoned determination of default, contrary to Article 14 and the requirement of reasoned administrative decision-making.

Source reference: paras. 43, 57–61

The alternative contractual remedy did not bar the writ petition because the challenge concerned the legality and fairness of the State instrumentality’s termination process, rather than merely a monetary or technical contractual claim.

Source reference: paras. 55–60
05

Holding

The Court answered the principal issue in the negative: a mere numerical CUF shortfall cannot, by itself, be treated as an attributable Event of Default justifying termination where the contractor has raised a specific defence that the shortfall resulted from inadequate or interrupted water supply beyond its control.

The termination order dated 30.05.2022 was held arbitrary and legally unsustainable and was quashed.

Source reference: para. 65

The notices dated 03.11.2021 and 06.04.2022 were also quashed to the extent that they formed the basis of the termination.

Source reference: para. 65

The petitioner’s other claims and issues were left open for adjudication before the arbitral tribunal, and the parties were directed to bear their own costs.

Source reference: para. 65
06

Acts & Sections Cited

3 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19961

Indian Contract Act, 18722

Madhya Pradesh High Court

Original Court PDF

Madhav Infra Projects Limited A Company Incorporated Under The Compnies ActvsM.P. Madhya Kshetra Vidyut Vitran Co. Limited

Madhya Pradesh High Court · September 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment