Meghalaya High Court
Administrative and Public LawContract Law

Debarment without prior notice or hearing violates natural justice and is unsustainable.

M/S INDRA CONSTRUCTION AND ANR. vs THE UNION OF INDIA AND 3 ORS.

Meghalaya High CourtJUDGMENT: September 10, 20263 MIN READSOURCE JUDGMENT
Debarment without prior notice or hearing violates natural justice and is unsustainable.. M/S INDRA CONSTRUCTION AND ANR. vs THE UNION OF INDIA AND 3 ORS.. Meghalaya High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioners participated in an FCI tender issued by the Assistant General Manager (CE), Food Corporation of India, under E-Tender Notice dated 07.03.2025.

Source reference: pp. 2–5

After acceptance of their tender, they were required to furnish a Performance Bank Guarantee of ₹5,48,910 by 12.08.2025. On their request, the deadline was extended to 19.08.2025.

Source reference: pp. 2–5

The petitioners created a fixed deposit for the requisite amount on 14.08.2025, but the bank issued the Performance Bank Guarantee only on 20.08.2025, one day after the extended deadline.

Source reference: pp. 2–5

The respondents thereafter terminated the tender, forfeited the earnest money deposit of ₹2,01,680, and debarred the petitioners from participating in future FCI tenders for five years by order dated 15.09.2025.

Source reference: p. 3

The petitioners challenged the termination, forfeiture and debarment, contending that the delay was marginal and attributable to circumstances beyond their control and that no opportunity of hearing had been granted before debarment.

Source reference: pp. 3–4

The respondents relied on Clause 2(c) of the conditions of contract and submitted that the petitioners had failed to comply with the tender conditions; they also contended that only a scanned copy of the guarantee had initially been emailed and that the physical copy had not been timely submitted.

Source reference: p. 4
02

Issues

Whether the petitioners’ failure to furnish the Performance Bank Guarantee by the extended deadline justified termination of the tender and forfeiture of the earnest money deposit?

Source reference: pp. 5–8

Whether debarment for five years under Clause 2(c), without prior notice or an opportunity of hearing, was legally sustainable?

Source reference: pp. 6–8
03

Law Applied

The Court applied the principles of natural justice, particularly the rule that an adverse order of blacklisting or debarment must ordinarily be preceded by notice and a meaningful opportunity to represent.

Source reference: pp. 6–7

Clause 2(c) of the FCI conditions authorised termination, forfeiture of earnest money and five-year debarment upon failure to furnish the Performance Guarantee within the stipulated or extended period, but did not provide for any opportunity of hearing before debarment.

Source reference: pp. 6–7

The Court held that the contractual clause could not exclude the requirement of natural justice and was unsustainable to the extent that it permitted debarment without prior notice or hearing.

Source reference: pp. 7–8

The Court also considered the principle that such coercive consequences must take account of the surrounding circumstances, including whether the default was attributable to the tenderer’s negligence and whether the penalty was proportionate.

Source reference: p. 7

It found persuasive the decision in M/s Feedback Infra Pvt. Ltd. v. Union of India & Ors., WP(C) No. 2934/2024, concerning the requirement of prior notice before debarment.

Source reference: p. 4; p. 7
04

Reasoning

The Court accepted that the Performance Bank Guarantee was technically obtained after the extended deadline, since the extension expired on 19.08.2025 and the bank issued the guarantee on 20.08.2025.

Source reference: pp. 5–6

However, the petitioners had created the required fixed deposit on 14.08.2025, five days before the deadline, and the bank had subsequently issued the physical guarantee on 20.08.2025.

Source reference: p. 5

These facts indicated that the failure could not be squarely attributed to deliberate negligence by the petitioners.

Source reference: p. 7

Although the Court held that the challenge to termination was no longer capable of effective consideration because the contract had ceased to survive, it treated the five-year debarment as a distinct and serious adverse consequence.

Source reference: p. 5; p. 6

Since Clause 2(c) authorised automatic debarment without providing any opportunity to explain the delay, its application in that manner violated natural justice.

Source reference: pp. 7–8

The respondents were therefore required to reconsider the debarment and the forfeiture of the earnest money after receiving the petitioners’ representation.

Source reference: pp. 7–8
05

Holding

The writ petition was allowed to the extent indicated.

The Court declined to revive or otherwise examine the terminated contract, as it no longer survived for consideration.

Source reference: p. 5; p. 8

However, the petitioners were granted an opportunity to represent against the debarment and the forfeiture of the earnest money deposit.

Source reference: p. 8

They were directed to submit their representation within two weeks, and respondents Nos. 2–4 were directed to pass a reasoned and speaking order within four weeks thereafter, confined to the issues of refund of the earnest money and debarment.

Source reference: p. 8

The interim stay of debarment was directed to continue until further orders by the respondents.

Source reference: p. 8
Meghalaya High Court

Original Court PDF

M/S INDRA CONSTRUCTION AND ANR.vsTHE UNION OF INDIA AND 3 ORS.

Meghalaya High Court · September 10, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment