Facts
The Appellant (TSECL), the sole off-taker of power from the Tripura Gas Based Power Project, challenged the Central Electricity Regulatory Commission's (CERC) order dated 04.04.2019.
Source reference: no citationThe project suffered significant delays: 33 months for the Gas Turbine (GT) and 44 months for the Steam Turbine (ST)
Source reference: p. 5NEEPCO (Respondent No. 1) attributed 8 months of delay to its EPC contractor, BHEL (partially due to offloading work to a joint venture, NBPPL), and the remainder (25–36 months) to ONGC’s failure to supply gas
Source reference: p. 6, paras 17-18CERC condoned these delays as "uncontrollable" and approved a revised capital cost of ₹1062.24 Crore based on a CEA recommendation, despite the lack of formal Ministry approval for the RCE-II
Source reference: p. 30, 32Issues
1. Whether CERC erred in allowing a time overrun of 8 months for GT and ST attributable to the contractor BHEL?
Source reference: p. 6, para 182. Whether CERC erred in allowing a time overrun of 25 months and 36 months for GT and ST respectively attributable to non-supply of gas by ONGC?
Source reference: p. 6, para 183. Whether CERC erred in allowing the cost overrun and using the CEA-vetted cost instead of the formally approved RCE-I?
Source reference: p. 6, para 18; p. 33Law Applied
Regulation 12 of the CERC (Terms and Conditions of Tariff) Regulations, 2014, which classifies "delay on account of contractor, supplier or agency" as a "controllable factor," meaning cost escalations therefrom cannot be passed to consumers
Source reference: p. 20-21Maharashtra State Power Generation Co. Ltd. v. MERC (Appeal No. 72 of 2010) regarding the categorization of delays
Source reference: p. 11Regulation 10(4) provides that if a Power Purchase Agreement (PPA) provides a ceiling on capital expenditure, the Commission must consider it
Source reference: p. 33-34Suresh Madhukar Ganorkar v. Union of India to hold that D.O. letters lack statutory force and are not executive instructions
Source reference: p. 16-17Reasoning
The Tribunal found that CERC failed to apply its own 2014 Regulations. Since both BHEL (contractor) and ONGC (supplier) fall under "controllable factors" per Regulation 12, NEEPCO cannot pass the resulting Interest During Construction (IDC) and Incidental Expenditure during Construction (IEDC) to the beneficiaries
Source reference: p. 21-22, 28The Tribunal rejected the "Force Majeure" argument for gas supply, noting that non-supply by a vendor does not constitute Force Majeure under the Specific PSA or Regulations
Source reference: p. 27-28Regarding cost-overrun, the Tribunal held that CERC erred by treating a CEA recommendation letter as a formal "Investment Approval." Per Regulation 10(4) and Clause 3.2 of the PSA, the formally approved RCE-I (₹623.44 Crore) should have served as the benchmark for the prudence check, adjusted only for appropriate price levels, rather than adopting the unapproved RCE-II
Source reference: p. 33-35Holding
It held that (a) the 8-month delay by BHEL and specific delays by ONGC were "controllable" and not condonable for tariff purposes; and (b) capitalization of cost escalations, IDC, and IEDC arising from these delays is disallowed
The Tribunal allowed the appeal, set aside the Impugned Order, and remanded the matter to CERC to re-determine the tariff by performing a fresh prudence check of capital cost with reference to the RCE-I (2010 price level) instead of the CEA's 2017 recommendation
Source reference: p. 35-36Original Court PDF
Tripura State Electricity Corporation Ltd.vsNorth Eastern Electric Power Corporation Ltd. & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in