Facts
The petitioner, a landowner dissatisfied with the compensation determined by the competent authority, had filed an application under Section 10(2) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (“the 1962 Act”).
Source reference: p.2, para. 6The application remained pending for approximately two years and was dismissed on 6 September 2025 for want of prosecution due to the absence of the petitioner’s advocate.
Source reference: p.2, para. 6The petitioner thereafter filed a restoration application seeking recall of the dismissal order, accompanied by an application under Section 5 of the Limitation Act, 1963, explaining a delay of 37 days.
Source reference: p.2, paras. 3, 6On 17 March 2026, the 6th Additional Sessions Judge, Banaskantha at Deesa, rejected the condonation application.
Source reference: p.1–2, paras. 2–4Issues
1. Whether the application seeking condonation of a 37-day delay in filing the restoration application was required to be considered under Section 5 of the Limitation Act, 1963 and the applicable procedure under the Code of Civil Procedure, 1908?
Source reference: p.2–3, paras. 5–62. Whether the restoration application seeking recall of the order dated 6 September 2025, by which the Section 10 application was dismissed for want of prosecution, ought to be allowed?
Source reference: p.3–4, paras. 6–73. Whether the court below was justified in rejecting the condonation application on the ground that the 1962 Act did not expressly provide for condonation of delay?
Source reference: p.2–3, paras. 3–5Law Applied
The Court applied Section 5 of the Limitation Act, 1963, under which delay in filing an application may be condoned where sufficient cause is shown.
Source reference: p.3, paras. 5–6It further held that a restoration application seeking recall of an order dismissing proceedings for want of prosecution must be dealt with in accordance with the relevant procedure under the Code of Civil Procedure, 1908.
Source reference: p.3, paras. 5–6The Court noted that Section 10(2) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 does not prescribe a period of limitation for an application by a landowner dissatisfied with the compensation determined by the competent authority.
Source reference: p.3, para. 6The question of condonation therefore concerned the delay in filing the restoration application, not the filing of the original Section 10 application.
Source reference: p.3, para. 6Reasoning
The High Court held that the court below had addressed the wrong legal question.
Source reference: p.2–3, paras. 3, 5The application for condonation was filed with the restoration application and did not accompany a fresh application under Section 10 of the 1962 Act; consequently, the relevant inquiry was whether the 37-day delay in seeking restoration should be condoned under Section 5 of the Limitation Act.
Source reference: p.2–3, paras. 3, 5The subordinate court’s focus on whether the 1962 Act contained an independent provision for condonation of delay was therefore misplaced.
Source reference: p.2, paras. 4–5Its rejection of the application, coupled with the refusal of an adjournment and the inference that the request to engage a new advocate was intended to delay the proceedings, did not constitute a proper determination under the applicable legal framework.
Source reference: p.2, paras. 4–5Since the relevant provisions and procedure had not been considered, the High Court set aside the impugned order and proceeded to grant the consequential reliefs.
Source reference: p.3, para. 7Holding
The High Court allowed the petition and set aside the order dated 17 March 2026 rejecting the condonation application.
It allowed the application under Section 5 of the Limitation Act, 1963 and condoned the 37-day delay in filing the restoration application.
Source reference: p.3, para. 7It further allowed the restoration application, recalled the order dated 6 September 2025, and restored the petitioner’s application under Section 10 of the 1962 Act, registered as CMA DC No. 118 of 2023, to its original number.
Source reference: p.3–4, paras. 7–8The concerned court was directed to decide the Section 10 application on its merits and strictly in accordance with law.
Source reference: p.3–4, paras. 7–8Acts & Sections Cited
2 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 19621
Limitation Act, 19631
Original Court PDF
MALI DALPATJI NEMAJIvsCOMPETENT AUTHORITY AND DEPUTY COLLECTOR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
