APTEL

Delayed Payment Charges Benchmarked to Banking Norms Mandate Compound Interest with Monthly Rests.

Essar Power Limited vs Gujarat Electricity Regulatory Commission & Anr

APTELJUDGMENT: May 29, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (Essar Power) and Respondent No. 2 (GUVNL) entered into a Power Purchase Agreement (PPA) on 30.05.1996. Following disputes regarding monetary claims, the Commission allowed the Appellant’s claims in 2014, a decision upheld by the Tribunal in 2022

Source reference: p. 3-4

On remand for quantification, the Appellant claimed ₹1556 crores, including ₹1296.33 crores as Delayed Payment Charges (DPC)

Source reference: p. 5

By an order dated 05.05.2023, the Commission rejected the claim for compound interest, granting only simple interest based on Article 5.3.4 of the PPA and a previous order in Petition No. 972/2009

Source reference: p. 5

The Appellant challenged this, asserting that the contractual mechanism implies compounding.

Source reference: no citation
02

Issues

1. Whether Article 5.3.4 of the PPA provides for the payment of Delayed Payment Charges (DPC) on a compound interest basis or only simple interest

Source reference: p. 6, para. 8

2. Whether the Tribunal’s earlier judgment in Appeal No. 138/2021 precluded the Appellant from claiming compound interest under the principle of binding precedent

Source reference: p. 10, para. 11(h); p. 27, para. 32
03

Law Applied

The Tribunal applied the principle that compound interest is granted only upon specific contractual stipulation or statutory authority, as established in State of Haryana v. S.L. Arora Company

Source reference: p. 14, para. 15

The principle was recently reaffirmed in D. Khosla Company v. Union of India

Source reference: p. 13, para. 14

It relied on Central Bank of India v. Ravindra, which recognizes banking practices of "periodical rests" and capitalization of unpaid interest as valid compounding

Source reference: p. 14, para. 16

Furthermore, it followed T.N. Generation and Distribution Corporation Ltd. v. PPN Power Generating Co. (P) Ltd., which held that PPA clauses pegging interest to banking "rates charged" incorporate the compounding norms of those banks

Source reference: p. 21, para. 22
04

Reasoning

The Tribunal found that Article 5.3.4 was not a standalone interest rate but a "specific stipulation" incorporating the actual "rate charged" by GUVNL’s banks on working capital

Source reference: p. 17, para. 19

Evidence, including GUVNL’s banking documents and RBI Circulars, proved that these banks charge interest on "monthly rests," which entails compounding

Source reference: p. 26, para. 30

The Tribunal distinguished Article 5.4, noting that the express mention of "semi-annual" compounding there merely fixed a specific frequency, whereas Article 5.3.4 adopted whatever frequency the banks used (monthly)

Source reference: p. 24, para. 27

The Tribunal rejected GUVNL’s reliance on Appeal No. 138/2021, noting that the "simple interest" observation there was academic and not a conclusive interpretation of Article 5.3.4

Source reference: p. 30, para. 35

Finally, the Tribunal held GUVNL to its own prior admissions in affidavits where it acknowledged discharging debt on a compounding basis

Source reference: p. 38, para. 48
05

Holding

The Tribunal allowed the appeal, holding that Article 5.3.4 of the PPA constitutes a specific contractual stipulation for DPC on a compound interest basis with monthly rests

It set aside the Commission’s order dated 05.05.2023 to the extent it granted only simple interest

Source reference: p. 43, para. 52

The Commission was directed to recompute the DPC amounts in accordance with this finding within one month

Source reference: p. 43, para. 54
APTEL

Original Court PDF

Essar Power LimitedvsGujarat Electricity Regulatory Commission & Anr

APTEL · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment