01Facts
The Petitioner, a developer, constructed 12 buildings (A to H, J, K, L, and M) on a 21,736 sq. mtr. plot
¶ 2Respondent No. 1 (comprising buildings A–K) originally sued in 1985 for conveyance; the City Civil Court granted an order in 1997 for only the land appurtenant to those specific buildings
¶ 3While a First Appeal was pending, Respondent No. 1 joined Respondents Nos. 2 and 3 (buildings L and M) and withdrew the appeal in 2016 to seek a joint unilateral deemed conveyance under Section 11 of the MOFA
¶ 3-4The Competent Authority granted the conveyance for the entire 21,736 sq. mtr. plot on 15 May 2017
¶ 4The Petitioner challenged this, arguing they retained rights to build two more buildings (N and P) and that the Civil Court’s 1997 decree barred the Competent Authority’s order
¶ 6-802Issues
i.1. Whether a prior Civil Court decree and the withdrawal of a First Appeal bar a Society from applying for deemed conveyance before the Competent Authority
¶ 15-21ii.2. Whether a developer can withhold conveyance for an indefinite period on the basis of potential future FSI or development rights
¶ 25-32iii.3. Whether the Competent Authority erred in conveying the entire plot area without deducting land surrendered for DP roads or reserved for public utilities
¶ 22-2403Law Applied
The court primarily applied Section 11 of the Maharashtra Ownership Flats Act, 1963 (MOFA), which mandates the promoter to convey title to the Society within the prescribed period
¶ 1, 33It relied on the principle that an appeal is a continuation of a suit and that statutory remedies for deemed conveyance can be pursued upon withdrawal of a suit/appeal
¶ 20The court followed precedents established in Lakeview Developers v. Eternia CHS Ltd. and Rajkumar Gulati v. S.D. Corporation Pvt. Ltd., which hold that a developer cannot exploit building potential for eternity or delay conveyance based on future FSI accruals
¶ 31-32Provisions in the judgment · 4 · Linked ones open on LawLens
Maharashtra Ownership Flats (Regulation of the promotion of construction, sale, management and transfer) Act, 1963 Section 3Section 4Section 11
Maharashtra Regional and Town Planning Act, 1966. Section 127
04Reasoning
The Court rejected the Petitioner's argument regarding res judicata, noting that the 1997 decree was passed when buildings L and M were incomplete and the MoFA was not yet amended to include "deemed conveyance"
¶ 18-20The Court found that Respondent No. 1's withdrawal of the appeal to join other societies for a joint conveyance was a valid procedural shift
¶ 19Regarding the Petitioner's claim to build buildings N and P, the Court noted that the MCGM had confirmed as early as 1991 that no balance FSI existed
¶ 27The Court held that the "novel idea" of using TDR/FSI from reserved land (market/school) for these buildings was preposterous, as compensation for acquired land does not entitle the developer to delay the society's conveyance indefinitely
¶ 29-30The Court acknowledged a factual error in the Competent Authority’s order for failing to exclude land already surrendered or reserved for public purposes
¶ 3405Holding
The Court held that the statutory obligation to convey title must be performed once the existing buildings' development potential is exhausted
¶ 33The Court partly allowed the petition. It set aside the Competent Authority’s order dated 15 May 2017 but remanded the matter for the limited purpose of issuing a fresh certificate of unilateral deemed conveyance for a reduced area of 16,584.55 sq. mtrs.
¶ 35(i), 35(ii), 36Original Court PDF
Kiran Builders Pvt. Ltd.vsKalpita Enclave Co-Op. Housing Society Ltd. And Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
