Jammu and Kashmir High Court

Doctrine of Election Estops Party from Challenging Penal Recoveries After Accepting Contractual Benefits and Admitting Infrastructure Deficiencies

M/S ALPINE AGRO SERVICES vs UNION OF INDIA AND ORS. (CONSUMER AFFAIRS AND PUBLIC DISTRIBUTION)

Jammu and Kashmir High CourtJUDGMENT: June 06, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a partnership firm, was awarded a contract in 2013 to construct a 17,500 MT capacity godown under the Private Entrepreneur Guarantee (PEG) Scheme on a "Build, Own and Operate" basis.

Source reference: para. 03

A Lease and Service Agreement was executed with the Food Corporation of India (FCI), establishing a 10-year guaranteed hiring period starting February 27, 2015.

Source reference: para. 04

At the time of takeover, the godown lacked essential infrastructure, specifically drainage and black-topping of internal roads.

Source reference: para. 09

The petitioner provided undertakings in 2015 to complete these works, and FCI granted extensions until February 26, 2016.

Source reference: para. 09, 39

The black-topping was only completed in mid-2017.

Source reference: para. 07, 18

Consequently, FCI issued orders on September 3, 2021, and November 15, 2021, to recover penalties from rentals based on a "Cost Saving Amount" (CSA) formula approved by a High Level Committee (HLC).

Source reference: para. 01, 16

The petitioner challenged these recoveries as arbitrary and violative of natural justice.

Source reference: para. 19
02

Issues

1. Whether the writ petition is maintainable despite arising from a contractual relationship involving a State instrumentality.

Source reference: para. 21, 36

2. Whether the respondent-FCI acted arbitrarily or outside the scope of the agreement by imposing penal recoveries for delayed infrastructure completion.

Source reference: para. 19, 37

3. Whether the doctrine of estoppel precludes the petitioner from challenging the recoveries after failing to meet undertakings and enjoying the benefits of the contract.

Source reference: para. 24, 44
03

Law Applied

Article 226 jurisdiction is not ousted in contractual matters if the State’s action is arbitrary or violates Article 14.

Source reference: para. 21

The doctrine of "approbate and reprobate" and the principle of estoppel prevents a party from accepting the benefits of a contract while avoiding its corresponding obligations.

Source reference: para. 24, 44

Liquidated damages require proof of loss for penal amounts unless damage is impossible to quantify.

Source reference: para. 23
04

Reasoning

The Court noted that black-topping of internal roads was an essential infrastructure component under the Model Tender Form.

Source reference: para. 10, 41

Although the petitioner argued that the 2016 law-and-order situation in Kashmir caused the delay, the Court found this untenable because the extended deadline for completion expired in February 2016, months before the disturbances began in July 2016.

Source reference: para. 11, 44

The Court observed that the HLC decisions regarding "Cost Saving Amount" and "Actual Utilization Basis" were uniform national policies intended to prevent unjust enrichment of investors who received full rentals without providing full infrastructure.

Source reference: para. 13, 17, 33

The Court highlighted that under Clause 5 of the Agreement, FCI had the power to terminate the contract for such breaches; opting for a fiscal recovery instead constituted a "lenient view".

Source reference: para. 10, 42

Since the petitioner failed to challenge the foundational HLC decisions and only attacked the consequential orders, and because they had benefited from the contract despite the breach, the challenge failed.

Source reference: para. 41, 44
05

Holding

While the writ was maintainable, the petitioner was estopped from challenging the recoveries due to their own breach of undertakings and the doctrine of election.

The Court found no merit in the allegation of arbitrariness, as the recoveries were based on a transparent methodology related to financial advantages gained through non-execution of work; the writ petition was dismissed, all interim directions were vacated, and the impugned recovery orders were upheld.

Source reference: para. 34, 40, 45
Jammu and Kashmir High Court

Original Court PDF

M/S ALPINE AGRO SERVICESvsUNION OF INDIA AND ORS. (CONSUMER AFFAIRS AND PUBLIC DISTRIBUTION)

Jammu and Kashmir High Court · June 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment