Bombay High Court

Doctrine of indoor management prevents corporate bodies from repudiating contracts based on internal lack of authorization.

Adtrack Media Llp vs Happy Valley Homes Chs Federation Ltd

Bombay High CourtJUDGMENT: June 08, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, an advertisement agency, entered into an "Agreement for Construction of Hoardings and Display of Advertisements" dated 28 October 2025 with the Respondent Federation

Source reference: para. 1, 3

The Federation had previously passed a General Body Resolution on 4 May 2025 awarding the contract to the Petitioner

Source reference: para. 2

The Petitioner obtained necessary permissions from the Thane Municipal Corporation (TMC) and Traffic Department, paying substantial fees

Source reference: para. 4

When the Petitioner commenced work on 21 February 2026, the Federation’s Chairman obstructed it, claiming the location was unsafe and that the Secretary—who signed the Agreement and NOCs—had no authority to bind the Federation

Source reference: para. 5, 8

The Petitioner filed this Section 9 petition seeking interim measures to restrain the Federation from disturbing the construction or terminating the agreement

Source reference: para. 1, 5
02

Issues

1. Whether a valid arbitration agreement exists between the parties given the Respondent's challenge to the Secretary's authority to sign the Agreement.

Source reference: para. 13-14

2. Whether the Petitioner is entitled to interim measures to protect its rights to install the hoarding at the specifically agreed site.

Source reference: para. 19-20
03

Law Applied

The court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures before the commencement of arbitral proceedings

Source reference: para. 1

The court relied on the "Doctrine of Indoor Management," as established in Shri. Kantu Shankar Dessai v. Soceidade Agricola Dos Gauncares De Cuncolim E Veroda, which protects third parties dealing with a body corporate by allowing them to assume that internal procedures (like resolutions or authorizations) have been duly complied with

Source reference: para. 16(ii)

The court also applied the principles of balance of convenience, prima facie case, and irreparable injury required for the grant of interim injunctions

Source reference: para. 28
04

Reasoning

The court found a strong prima facie case that an arbitration agreement exists, noting that the Agreement was backed by a General Body Resolution and the ministerial act of signing by the Secretary falls under the doctrine of indoor management

Source reference: para. 16(i)-16(ii)

The Federation's denial was deemed an afterthought because contemporaneous correspondence (specifically the letter dated 22 February 2026) did not challenge the Agreement's validity but only the site location

Source reference: para. 16(iii)

Furthermore, a letter signed by both the Chairman and Secretary in November 2025 confirmed the contract award

Source reference: para. 16(iv)

Regarding the site, the court noted North Recital (C) of the Agreement specifically identified the location, and the Petitioner's proposal had also specified "next to the entry gate"

Source reference: para. 22(i)-22(ii)

The court dismissed the Federation's safety concerns by referencing a Structural Engineer's report certifying sufficient road width for emergency vehicles

Source reference: para. 26

The balance of convenience favored the Petitioner, who had already invested significantly, whereas the hoarding (a non-permanent structure) could be removed if the final award favored the Federation

Source reference: para. 28
05

Holding

The court held that the Petitioner established a prima facie case and that the Federation was likely bound by the Agreement signing by its Secretary

The Petition was partly allowed. The court restrained the Respondents from obstructing or stopping the construction of the hoarding structure at the agreed site till the final arbitral award

Source reference: para. 29(i)

This relief is subject to the Petitioner commencing arbitration within 90 days as per Section 9(2) of the Act

Source reference: para. 29(iii)

The operative directions were stayed for four weeks at the Respondent’s request

Source reference: para. 31
Bombay High Court

Original Court PDF

Adtrack Media LlpvsHappy Valley Homes Chs Federation Ltd

Bombay High Court · June 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment