Madras High Court
Administrative and Public LawContract Law

Energy wheeling agreements must provide 75% tariff payment for surplus solar energy under the applicable tariff order.

M/s.Manobaala Energy Private limited vs TAMIL NADU ELECTRICITY REGULATORY COMMISSION

Madras High CourtJUDGMENT: September 30, 20262 MIN READSOURCE JUDGMENT
Energy wheeling agreements must provide 75% tariff payment for surplus solar energy under the applicable tariff order.. M/s.Manobaala Energy Private limited vs TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a solar power generator, challenged a clause in its Energy Wheeling Agreement dated 29 August 2025 under which surplus energy remaining at the end of the billing period would lapse.

Source reference: p.2

It sought revision of the agreement to conform to Clause 5.5.8 of the Tamil Nadu Electricity Regulatory Commission’s Solar Tariff Order No. 9 of 2020, and payment for unutilised surplus energy.

Source reference: p.2

The parties accepted that the issue was covered by earlier High Court decisions directing amendment of similar agreements.

Source reference: pp.3–6

The respondents submitted that TANGEDCO’s appeal against the Commission’s order was pending before APTEL.

Source reference: p.6
02

Issues

1. Whether the respondents should be directed to revise the petitioner’s Energy Wheeling Agreement to incorporate the requirements of Clause 5.5.8 of Solar Tariff Order No. 9 of 2020.

Source reference: pp.2, 6–7

2. Whether implementation of that direction should await the outcome of the pending APTEL appeal.

Source reference: p.6
03

Law Applied

Clause 5.5.8 of Solar Tariff Order No. 9 of 2020, dated 16 October 2020, governed payment for excess energy: the generator is entitled to 75% of the tariff fixed by the Commission or, where no tariff is fixed, 75% of the tariff discovered through competitive bidding.

Source reference: pp.4–5

In M.P. No. 47 of 2021, the Commission held that a contractual clause inconsistent with Clause 5.5.8 and Regulation 7 of the Power Procurement from New and Renewable Sources of Energy Regulations, 2008 could not stand, and set out the applicable payment principle.

Source reference: pp.4–5

The High Court followed its earlier decisions directing amendment of inconsistent wheeling-agreement clauses.

Source reference: pp.3–6
04

Reasoning

The Court treated the dispute as covered by its earlier decisions, which had required amendment of similar agreements to reflect Clause 5.5.8. It therefore directed the respondents to revise the petitioner’s agreement on the same basis.

Source reference: pp.6–7

Although the respondents sought to make compliance dependent on the pending APTEL appeal, the Court held that they need not await its outcome; the authorities could proceed in accordance with law after APTEL decided the matter.

Source reference: p.7
05

Holding

The writ petition was disposed of with a direction to respondents 2 to 4 to revise the relevant agreement clause to incorporate Clause 5.5.8 within six weeks from uploading of the web copy.

Any amount payable to the petitioner following that modification was to be settled within a further eight weeks.

Source reference: pp.6–7

Compliance was not to be deferred pending the APTEL appeal, though the authorities could act in accordance with law after its decision.

Source reference: pp.6–7

No costs were awarded.

Source reference: pp.6–7
Madras High Court

Original Court PDF

M/s.Manobaala Energy Private limitedvsTAMIL NADU ELECTRICITY REGULATORY COMMISSION

Madras High Court · September 30, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment