Madhya Pradesh High Court
Arbitration and MediationCivil Procedure and Evidence

Excepted-matter and limitation objections under Section 11 must be left to the arbitrator.

The King Security Guards Services Pvt Ltd vs The West Central Railway

Madhya Pradesh High CourtJUDGMENT: August 14, 20264 MIN READSOURCE JUDGMENT
Excepted-matter and limitation objections under Section 11 must be left to the arbitrator.. The King Security Guards Services Pvt Ltd vs The West Central Railway. Madhya Pradesh High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The applicant was awarded Contract No. 511687784746189 by West Central Railway under a Letter of Acceptance dated 25 August 2023 for mechanized cleaning of coaches at Coaching Depot, Jabalpur.

Source reference: para. 2

The contract was valued at ₹5,35,30,910.51 for 24 months, and the applicant furnished a performance guarantee of ₹53,53,100.

Source reference: para. 2

The applicant alleged that the scope of work was enhanced by approximately 33%, beyond the permissible 25% variation limit, resulting in additional financial liability and deductions from its bills.

Source reference: para. 2

By letter dated 27 June 2025, it objected to undertaking work beyond the permissible limit without a formal amendment and compensation.

Source reference: paras. 2–4

The respondent thereafter issued a seven-day notice and terminated the contract on 7 July 2025.

Source reference: paras. 2–4

The applicant disputed the termination, alleged retaliatory action, challenged the deductions, debarment and withholding of bank guarantees, and invoked Clause 8.2 of the GCC, 2018, seeking appointment of an arbitrator through representations dated 3 October 2025 and 17 February 2026.

Source reference: paras. 2–5

The respondent rejected the request on 9 April 2026, contending that the disputes concerned “Excepted Matters” under Clause 8.1 of the GCC and were therefore not arbitrable.

Source reference: paras. 2–5

The applicant consequently filed the present application under Section 11 of the Arbitration and Conciliation Act, 1996, for appointment of a sole arbitrator.

Source reference: para. 1
02

Issues

Whether a valid arbitration agreement existed between the parties and whether the disputes arising from the contract were referable to arbitration under Section 11 of the Arbitration and Conciliation Act, 1996?

Source reference: paras. 1, 3–4, 11

Whether the respondent’s objection that termination and related disputes constituted “Excepted Matters” under Clause 8.1 of the GCC was required to be decided by the High Court at the referral stage?

Source reference: paras. 5, 7, 11

Whether questions concerning limitation, jurisdiction, contractual variation, termination, deductions, debarment and withholding of securities should be left for determination by the Arbitral Tribunal?

Source reference: paras. 7–11
03

Law Applied

The Court applied Section 11(6-A) of the Arbitration and Conciliation Act, 1996, under which the referral court is confined to examining the existence of an arbitration agreement.

Source reference: para. 7

Section 16 embodies the kompetenz-kompetenz principle, enabling the Arbitral Tribunal to rule on its own jurisdiction, including objections concerning the existence, scope or validity of the arbitration agreement and limitation.

Source reference: paras. 7–10

Relying on Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd., (2020) 2 SCC 455, the Court held that threshold issues, including jurisdiction and limitation, ordinarily fall within the Tribunal’s jurisdiction at the post-reference stage.

Source reference: paras. 7–8

It also relied on Central Organisation for Railway Electrification v. ECI SPIC SMO MCML (JV), (2025) 4 SCC 641, and Aslam Ismail Khan Deshmukh v. ASAP Fluids (P) Ltd., (2025) 1 SCC 502, for the principle that the referral court must not conduct an intricate evidentiary inquiry into limitation or the merits of the claims.

Source reference: paras. 9–10

The contractual arbitration mechanism under Clause 8.2 of the GCC, 2018, and the respondent’s reliance on the “Excepted Matters” exclusion under Clause 8.1 were also considered.

Source reference: paras. 5, 11
04

Reasoning

The existence of the arbitration clause in the contract was not disputed.

Source reference: paras. 3–4, 11

The applicant’s claims concerning enhanced work, deductions, termination, performance, debarment and retention of bank guarantees arose out of the contractual relationship and were therefore capable of being placed before the Arbitral Tribunal.

Source reference: paras. 3–4, 11

Although the respondent argued that the variation had been accepted, payments had been made, the applicant had committed fundamental breaches, and termination fell within the “Excepted Matters” clause, these contentions involved disputed questions of fact and contractual interpretation.

Source reference: para. 5

Applying Section 11(6-A) and Section 16, the Court held that it was not required to undertake a detailed examination of those objections at the referral stage.

Source reference: paras. 7–11

The question whether particular disputes were excluded as “Excepted Matters,” as well as limitation and other jurisdictional objections, was left open for determination by the appointed arbitrator.

Source reference: paras. 7–11
05

Holding

The application under Section 11 was allowed because a subsisting arbitration agreement existed and disputes continued between the parties.

The Court appointed Shri Sujoy Paul, Retired Chief Justice of the Calcutta High Court, as the sole arbitrator to adjudicate the disputes.

Source reference: para. 12(i)

The arbitration was directed to take place at Jabalpur; the arbitrator was to issue notices and fix the venue and dates, while the parties were directed to deposit fees and charges in accordance with the applicable M.P. Arbitration Centre Rules, 2019.

Source reference: paras. 12(ii)–(iii)

The issue of whether the disputes were “Excepted Matters,” along with limitation and all other rights and contentions, was expressly left open for adjudication by the Arbitral Tribunal.

Source reference: paras. 11–12

The arbitration case was accordingly disposed of.

Source reference: para. 14
06

Acts & Sections Cited

8 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Indian Contract Act, 18721

Madhya Pradesh High Court

Original Court PDF

The King Security Guards Services Pvt LtdvsThe West Central Railway

Madhya Pradesh High Court · August 14, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment