Delhi High Court

Express written waiver under Section 12(5) validates arbitral appointments despite unilateral nomination by an interested party.

Krishna Udyog vs Union Of India

Delhi High CourtJUDGMENT: April 09, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner challenged an Arbitral Award dated 14.11.2023, which dismissed its claims regarding the recovery of Liquidated Damages (LD)

Source reference: para. 1

The dispute arose from a tender dated 08.06.2021 for the supply of signaling cables to the Railways

Source reference: para. 16

The Respondent (Union of India) constituted a three-member Arbitral Tribunal comprising retired Railway officials

Source reference: para. 16

Prior to the constitution, the Petitioner issued a letter dated 08.02.2023 expressly waiving the applicability of Section 12(5) of the Arbitration and Conciliation (A&C) Act and subsequently selected two names from a panel of four retired officers provided by the Respondent

Source reference: para. 24

The Tribunal upheld the Respondent's imposition of LD for delays beyond the extended delivery period

Source reference: para. 30

The Petitioner challenged the award on grounds of limitation, unilateral appointment of the tribunal, and the legality of LD without proof of actual loss

Source reference: para. 2, 11
02

Issues

1. Whether the petition was barred by limitation under Section 34(3) of the A&C Act given it was filed beyond three months but within the thirty-day grace period

Source reference: para. 2, 7

2. Whether the appointment of the Arbitral Tribunal was vitiated by unilateralism and bias under Section 12(5) of the A&C Act

Source reference: para. 11, 15

3. Whether the imposition of Liquidated Damages is legally sustainable under Sections 73 and 74 of the Indian Contract Act in the absence of proof of actual loss

Source reference: para. 11, 29
03

Law Applied

The Court applied Section 34(3) of the A&C Act, noting the mandatory three-month limitation period and the strictly circumscribed thirty-day extension allowed only upon showing "sufficient cause"

Source reference: para. 4-6

Regarding the tribunal's constitution, the Court relied on Section 12(5) and its Proviso, which permits parties to waive the ineligibility of an arbitrator through an express agreement in writing after disputes have arisen

Source reference: para. 21, 25

It further referenced the Constitution Bench decision in Central Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV) regarding the prospective application of rules against curated panels for three-member tribunals

Source reference: para. 20-21

On the merits of LD, the Court applied Sections 73 and 74 of the Indian Contract Act, 1872, and the principle from ONGC v. Saw Pipes Ltd., which establishes that pre-estimated damages are recoverable without proof of actual loss if they are a genuine estimate and not a penalty

Source reference: para. 31(f-g)
04

Reasoning

On limitation, the Court held that since the petition was filed within the "outer limit" of three months and thirty days, the marginal delay was condonable even without a formal application, as the legislative intent is to balance finality with fairness

Source reference: para. 8-9

Regarding the tribunal's appointment, the Court found the Petitioner’s challenge meritless because the Petitioner had provided an unequivocal written waiver under the Proviso to Section 12(5) via its letter dated 08.02.2023 and had actively participated in the selection process

Source reference: para. 23-26

Concerning Liquidated Damages, the Court found the Tribunal’s reasoning sound; the contract (IRS Conditions) explicitly defined LD as agreed compensation and not a penalty

Source reference: para. 31(a), 31(g)

The Court distinguished ONGC v. Remi Metals, noting that in this case, the Respondent never waived the LD during extensions

Source reference: para. 31(e)

The Court concluded that the Tribunal's view—that LD is recoverable without proving actual loss when a contractually predetermined measure exists—was a plausible interpretation of law and fact, precluding interference under the limited scope of Section 34

Source reference: para. 33-35
05

Holding

The Court dismissed the petition and upheld the Arbitral Award

(1) A Section 34 petition filed within the 30-day grace period is maintainable if the court is satisfied with the cause, even absent a formal condonation application

Source reference: para. 9

(2) An express written waiver of Section 12(5) post-dispute precludes a party from later challenging the tribunal's independence based on the arbitrators' relationship with a party

Source reference: para. 26-27

(3) Recovery of Liquidated Damages as per a pre-estimated contractual clause is valid without proof of actual loss, provided the contract characterizes it as compensation and not a penalty

Source reference: para. 31(g), 35
Delhi High Court

Original Court PDF

Krishna UdyogvsUnion Of India

Delhi High Court · April 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment