Facts
The Petitioner was contracted by the Respondent to execute a 131 Km Iron Ore Slurry Pipeline Project in Odisha via an Agreement dated September 14, 2023
Source reference: p. 2The original completion date was January 18, 2024; however, the Respondent granted an extension until May 31, 2026, via "Amendment No. 1," which stated that liquidated damages ("LD") charges would not apply for the validity extension
Source reference: p. 2-3Subsequently, disputes arose regarding delays and site stoppages. On May 7, 2026, the Respondent descoped 50% of the work and reserved the right to levy LD
Source reference: p. 2The Petitioner terminated the contract on May 18, 2026, citing the Respondent's failures
Source reference: p. 3The Respondent then sought to invoke an unconditional Advance Bank Guarantee dated July 18, 2025, leading the Petitioner to seek interim protection under Section 9 of the Arbitration and Conciliation Act, 1996
Source reference: p. 1-2, 6Issues
1. Whether a prima facie case exists to restrain the Respondent from levying liquidated damages for a period previously covered by an extension granted without such levy?
Source reference: p. 3 / para. 7.32. Whether the Petitioner is entitled to an injunction restraining the invocation of an unconditional and irrevocable Bank Guarantee?
Source reference: p. 10 / para. 25-26Law Applied
The court applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures
Source reference: p. 5It relied on the settled principle that a bank guarantee is an independent contract, and courts should only interfere in cases of "egregious fraud" or "irretrievable injury," as established in Gujarat Maritime Board v. Larsen and Toubro Infrastructure Development Projects Ltd. and U.P. State Sugar Corporation v. Sumac International Limited
Source reference: p. 12, 13Regarding LD, the court examined Clause 18.3 of the contract, which allows the levy of liquidated damages notwithstanding extensions if the delay is not attributable to the employer
Source reference: p. 9The "irretrievable injury" exception requires proof that restitution would be impossible in law, as per Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Work (P) Ltd.
Source reference: p. 16Reasoning
The court found that while "Amendment No. 1" initially waived LD for the extension, the Petitioner failed to complete the work and terminated the contract before the extended deadline
Source reference: p. 7Consequently, Clause 18.3 of the contract preserved the Respondent's right to levy LD for delays not caused by the Respondent, a matter requiring factual adjudication by an Arbitral Tribunal
Source reference: p. 9-10Regarding the Bank Guarantee, the court determined it was unconditional, irrevocable, and specifically intended to secure advance payments
Source reference: p. 11Since the Petitioner stopped work on July 7, 2025, leaving advances unadjusted, the Respondent was entitled to invoke the guarantee
Source reference: p. 12The court noted that the Petitioner failed to plead "egregious fraud" and that "financial hardship" does not constitute "irretrievable injury" as restitution remains possible through future arbitration
Source reference: p. 15-16Holding
The court answered Issue 1 by holding that no prima facie case was made to bar LD recovery at this stage, as the underlying causes of delay are subject to trial
On Issue 2, it held that the unconditional Bank Guarantee must be honored irrespective of the underlying contract dispute
Source reference: para. 30The court dismissed the petition and all pending applications, refusing to grant an injunction against the invocation of the Bank Guarantee or the levy of liquidated damages
Source reference: para. 37-39Original Court PDF
Kalpataru Projects International LimitedvsJsw Infrastructure Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in