National Company Law Appellate TribunalInsolvency and Bankruptcy LawCommercial and Corporate Law

Failed Resolution Plan implementation precludes de novo CIRP revival and necessitates mandatory liquidation.

G Madhusudhan Raov.Bheema Cements Limited & Ors.

Failed Resolution Plan implementation precludes de novo CIRP revival and necessitates mandatory liquidation.. G Madhusudhan Rao vs Bheema Cements Limited & Ors.. National Company Law Appellate Tribunal. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the CIRP can be revived and restored de novo after it has culminated in an approved Resolution Plan which subsequently failed implementation

The court held

The NCLAT dismissed the appeal, holding that a culminated CIRP cannot be revived de novo once it has resulted in a failed Resolution Plan and the subsequent initiation of liquidation proceedings

It also directed

The Tribunal affirmed that liquidation under Section 33 is the only valid recourse remaining under these circumstances

The impugned order of the NCLT was upheld, and all pending interlocutory applications were closed

01Facts

The Corporate Debtor (Bheema Cements Ltd.) was placed under the Corporate Insolvency Resolution Process (CIRP) on 09.07.2018

¶ 4

A Resolution Plan submitted by Respondent No. 2 (Consortium SRA) was approved by the Committee of Creditors (CoC) on 11.02.2020

¶ 4

Following persistent defaults by the SRA in meeting payment obligations, the Appellant filed for liquidation under Section 33 of the IBC (IA No. 15/2024) on 01.04.2024

¶ 7

This liquidation application was briefly withdrawn to allow a revised payment schedule, but was later restored via Restoration Application No. 1/2025 due to continued breaches

¶ 7

Subsequently, in January 2026, the Appellant filed IA No. 252/2026 seeking a de novo restoration and revival of the CIRP, the issuance of a fresh Form G, and his re-appointment as Resolution Professional (RP)

¶ 8

The Adjudicating Authority (NCLT Hyderabad) rejected this application on 05.02.2026, holding that the CIRP had already culminated and cannot be revived

¶ 1, 10

02Issues

i.1. Whether the CIRP can be revived and restored de novo after it has culminated in an approved Resolution Plan which subsequently failed implementation

¶ 9, 15

ii.2. Whether the appropriate recourse for the non-implementation of a Resolution Plan and its revised schedule is the initiation of liquidation proceedings under Section 33 of the IBC

¶ 11, 24

03Law Applied

The court primarily applied Section 33(1) of the Insolvency and Bankruptcy Code (IBC), 2016, which mandates the initiation of liquidation when a Resolution Plan is not implemented as per its terms

¶ 7, 10

It further addressed Rule 11 of the NCLAT Rules, 2016, regarding inherent powers, clarifying that such powers cannot be used to restart a culminated CIRP to bypass mandatory liquidation

¶ 17-18

The court distinguished Edelweiss Asset Reconstruction Company Limited v. Peter Beck and Peter Vermoenesverwaltung Limited, noting that judicial discretion for extension is distinct from de novo revival after multiple implementation failures

¶ 18-19

Provisions in the judgment · 1 · Linked ones open on LawLens

Insolvency and Bankruptcy Code, 2016. Section 33

04Reasoning

The Appellate Tribunal observed that the CIRP legally culminated upon the approval of the Resolution Plan; once the process matures to this stage and the plan fails, the CIRP "is no more breathing in the eyes of law"

¶ 9, 10

The court highlighted the Appellant's inconsistent conduct, noting he had himself initiated and restored the liquidation process under Section 33(1) of the IBC due to the SRA's persistent defaults

¶ 11, 24

The Tribunal rejected the plea to "put the clock back" by re-initiating the CIRP de novo, as the very purpose of the original CIRP stood frustrated by the partial/non-implementation of the revised repayment plan

¶ 11, 15

It distinguished the Edelweiss and Darwin Platform precedents, finding them factually inapplicable as they dealt with extensions of time or performance bank guarantees, rather than the total revival of a closed insolvency process

¶ 19, 23

05Holding

The NCLAT dismissed the appeal, holding that a culminated CIRP cannot be revived de novo once it has resulted in a failed Resolution Plan and the subsequent initiation of liquidation proceedings

¶ 25, 26

The Tribunal affirmed that liquidation under Section 33 is the only valid recourse remaining under these circumstances

¶ 11

The impugned order of the NCLT was upheld, and all pending interlocutory applications were closed

¶ 26
National Company Law Appellate Tribunal

Original Court PDF

G Madhusudhan RaovsBheema Cements Limited & Ors.

National Company Law Appellate Tribunal · March 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment