Facts
The applicant, M/s Reinforced Earth Pvt. Ltd. (“REIPL”), was engaged by the respondent, M/s Amar Infrastructure Ltd., under Work Order No. AIL/OD01/2022/01 dated 2 August 2022 for reinforced-earth works on the NH130CD OD1 Dhanara–Hatibena Section, involving design and drawings, supply of materials, and provision of moulds, for a total value of ₹3,67,54,900 and an agreed completion period of eight months.
Source reference: paras. 2, pp. 1–2REIPL alleged delays attributable to the respondent, including delayed approvals, non-availability of work fronts and machinery, and slow progress at the site.
Source reference: para. 2, pp. 2–3It claimed that, against 12 running account bills and tax invoices amounting to ₹2,48,78,784, the respondent paid only ₹2,00,22,422, leaving an outstanding amount of ₹48,56,362.
Source reference: para. 2, pp. 2–3After correspondence and unsuccessful efforts to resolve the payment and project-related disputes, REIPL issued a notice dated 13 November 2024 under Clause “P” of the Work Order invoking arbitration and requested the respondent to appoint its nominee arbitrator within 30 days.
Source reference: para. 2, p. 4The respondent did not appoint an arbitrator within the stipulated period, leading REIPL to file an application under Section 11(6) of the Arbitration and Conciliation Act, 1996.
Source reference: paras. 1, 3, p. 4During the proceedings, the applicant proposed Hon’ble Justice V.P. Vaish (Retd.), while the respondent proposed Hon’ble Justice R.C.S. Samant (Retd.) as its nominee arbitrator.
Source reference: para. 4, p. 5Issues
Whether the respondent’s failure to appoint its nominee arbitrator in accordance with the agreed arbitration procedure justified court intervention under Section 11(6) of the Arbitration and Conciliation Act, 1996?
Source reference: paras. 1, 3, pp. 1, 4Whether Hon’ble Justice V.P. Vaish (Retd.) and Hon’ble Justice R.C.S. Samant (Retd.) should be appointed as nominee arbitrators, with liberty to them to appoint the third arbitrator?
Source reference: paras. 4–5, p. 5Law Applied
The Court applied Section 11(6) of the Arbitration and Conciliation Act, 1996, which permits judicial appointment of an arbitrator where a party fails to act in accordance with the agreed appointment procedure.
Source reference: paras. 1–3, pp. 1, 4It also referred to the 30-day period contemplated under Section 11(4)(a), within which the relevant party is required to appoint its nominee arbitrator after receipt of the request.
Source reference: paras. 1–3, pp. 1, 4The Court gave effect to Clause “P” of the Work Order, which contained the parties’ arbitration and arbitrator-appointment mechanism.
Source reference: paras. 1–3, pp. 1, 4No judicial precedent was cited or relied upon in the order.
Source reference: no citationReasoning
The Court found that the applicant had invoked the arbitration clause by notice dated 13 November 2024 and that the respondent had failed to nominate its arbitrator despite receipt of the notice and expiry of the prescribed period.
Source reference: para. 3, p. 4This failure constituted non-compliance with the agreed appointment procedure and warranted intervention under Section 11(6).
Source reference: para. 3, p. 4Since counsel appearing for the applicant and respondent proposed Justice V.P. Vaish (Retd.) and Justice R.C.S. Samant (Retd.), respectively, the Court accepted those proposals and appointed them as arbitrators representing the parties.
Source reference: paras. 4–5, p. 5The two appointed arbitrators were directed to appoint the third arbitrator and thereafter adjudicate the disputes arising out of or relating to the Work Order.
Source reference: para. 5, p. 5Holding
The application under Section 11(6) was allowed.
Hon’ble Justice V.P. Vaish (Retd.), former Judge of the Delhi High Court, was appointed as the applicant’s nominee arbitrator, and Hon’ble Justice R.C.S. Samant (Retd.), former Judge of the Chhattisgarh High Court, was appointed as the respondent’s nominee arbitrator.
Source reference: para. 5, p. 5They were directed to appoint the third arbitrator and adjudicate the disputes between the parties.
Source reference: para. 5, p. 5The Registry was directed to communicate the order to both arbitrators, and their remuneration was left to be settled by mutual consent of the parties.
Source reference: paras. 6–8, p. 5Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19961
Original Court PDF
M/s Reinforced Earth Pvt Ltd REIPLvsMs Amar Infrastructure Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
