Facts
The Appellant society took possession of an incomplete housing project via DRT orders and contracted the Respondent (M/s Amtech Engineers) on 9 January 2018 to complete the work.
Source reference: para. 12, 14Disputes arose regarding delays and work deficiencies, where the Appellant claimed ₹2.78 Crores for excess payments and penalties, while the Respondent counter-claimed ₹8.52 Crores for escalation, unpaid bills, and idling charges.
Source reference: para. 2, 18-19A Sole Arbitrator awarded ₹2 Crores to the Appellant and ₹1 Crore to the Respondent.
Source reference: para. 3The Respondent challenged this under Section 34 of the Arbitration and Conciliation Act, 1996, and a Single Judge set aside the award entirely, finding it unreasoned and speculative.
Source reference: para. 5, 9The Appellant then filed this appeal under Section 37.
Source reference: para. 6Issues
1. Whether the arbitral award complied with the mandate of providing reasons under Section 31(3) of the Arbitration and Conciliation Act, 1996.
Source reference: para. 10, 342. Whether the Arbitrator’s findings on the nature of the contract (Lump Sum vs. Item Rate) and the ad-hoc quantification of damages were legally sustainable.
Source reference: para. 21, 27Law Applied
Section 31(3) of the Arbitration and Conciliation Act, 1996, which mandates that an arbitral award must state the reasons upon which it is based.
Source reference: para. 34The principle from Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd., establishing that reasons must be proper, intelligible, and adequate.
Source reference: para. 32The doctrines from Associate Builders v. DDA and OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions affirming that awards ignoring vital evidence or lacking a rational nexus between facts and findings suffer from "patent illegality" and "perversity".
Source reference: para. 27, 32The rule from Som Datt Builders Ltd. v. State of Kerala, stating that mere reference to documents is no substitute for reasons.
Source reference: para. 32Reasoning
The Court observed that the Arbitrator failed to discuss specific evidence, such as site reports or depositions, to justify the findings of delay or deficiency.
Source reference: para. 25-26The Arbitrator ignored Clause 16 and witness testimony (CW-2) which explicitly stated the contract was based on "item rates," instead concluding it was a "lump sum" contract without valid basis.
Source reference: para. 27The Court found the quantification of ₹2 Crores as "ad-hoc and fair estimation" to be arbitrary, as the Arbitrator neither held that evidence of loss was impossible to ascertain nor applied the "liquidated damages" clause correctly.
Source reference: para. 29-30The Arbitrator used speculative language (e.g., "perhaps") and dismissed several counter-claims for "want of evidence" without explaining what evidence was missing or how the burden of proof was not met.
Source reference: para. 7, 32-33The inclusion of irrelevant case law further indicated a lack of application of mind.
Source reference: para. 24, 33Holding
An award which is purely "ad-hoc," ignores vital evidence, and lacks intelligible reasons breaches Section 31(3) and is "no award in the eyes of law."
The Court dismissed the appeal and upheld the Single Judge’s judgment setting aside the arbitral award, concluding the award was patently illegal and perverse for failing to provide a "thought process" leading to the conclusions.
Source reference: para. 32, 38, 36Original Court PDF
Flat Owners Association Of Media Magestic TowervsArun Kumar Bhowmik
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in