Jharkhand High Court

Financial Incapacity to Pay Pre-deposit Does Not Justify Bypassing Statutory Alternate Remedies in Fiscal Matters.

M/S SUJATA UDIT BUILDERS PRIVATE LIMITED, THROUGH ITS DIRECTOR, MR. SHANKAR KUMAR KUNWAR vs CHIEF COMMISSIONER, CENTRAL GOODS AND SERVICE TAXES AND CENTRAL EXCISE , RANCHI ZONE, PATNA

Jharkhand High CourtJUDGMENT: April 22, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner challenged an Order-In-Original dated 29.09.2025 issued by the CGST authorities.

Source reference: para. 2

The primary ground for challenge was "delayed adjudication," as the show-cause notice was issued on 29.09.2020, but the final order was passed five years later on 29.09.2025.

Source reference: para. 3

The petitioner also argued that the tax liability related to exempt government construction.

Source reference: para. 7

The petitioner approached the High Court under Article 226 instead of the statutory Appellate Authority, claiming a financial inability to meet the mandatory pre-deposit requirement for an appeal, supported by audited accounts.

Source reference: para. 5

The respondents argued that the writ should be dismissed due to the existence of an alternative, efficacious remedy.

Source reference: para. 8
02

Issues

1. Whether an Order-In-Original can be challenged directly under Article 226 solely on the ground of delayed adjudication when a statutory appeal remedy exists.

Source reference: para. 10-15

2. Whether the hardship of paying a mandatory pre-deposit for a statutory appeal renders the alternative remedy "inefficacious," justifies bypassing the statutory regime.

Source reference: para. 18-20
03

Law Applied

The court primarily applied the principle of "exhaustion of alternative remedy" as a self-imposed restriction on High Courts exercising jurisdiction under Article 226 of the Constitution.

Source reference: para. 19

It relied on the Supreme Court's interim directions in Union of India vs. GMR Airport Infrastructure Ltd. (SLP (C) No. 5392 of 2025), which advised deferring hearings on delayed adjudication until the higher court takes a final call.

Source reference: para. 12

The court applied the principle that the right to appeal is a statutory right, not an inherent one, and is subject to conditions like pre-deposit, as upheld in Oberoi Constructions Ltd. vs. Union of India (2025) 137 GSTR 601.

Source reference: para. 18-20

It distinguished J.M. Baxi & Co. v. Commissioner of Customs [(2001) 9 SCC 275] regarding extreme delays.

Source reference: para. 22
04

Reasoning

The court reasoned that since the Order-In-Original is appealable by statute, the petitioner cannot bypass this regime unless an extraordinary case is made out.

Source reference: para. 10

Regarding the issue of "delayed adjudication," the court noted that the Supreme Court is currently seized of the larger legal question in the GMR Airport Infrastructure case; however, this did not mandate the High Court to keep the writ pending indefinitely.

Source reference: para. 11-15

The court observed that an appeal is a "more comprehensive remedy" because it allows for the adjudication of factual disputes and various other grounds beyond just the delay.

Source reference: para. 16

Crucially, the court rejected the petitioner's plea that financial inability to pay the pre-deposit makes the remedy inefficacious, stating that Article 226 cannot be used to frustrate statutory fiscal requirements or the "statutory regime".

Source reference: para. 18-19
05

Holding

The court declined to entertain the writ petition and relegated the petitioner to the alternate remedy of a statutory appeal.

It held that the inability to pay a pre-deposit does not constitute an extraordinary circumstance justifying the bypass of statutory procedures.

Source reference: para. 18

The petition was disposed of with the following directions: (i) the petitioner is granted liberty to file an appeal within four weeks; (ii) if filed within this period and after complying with pre-requisites, the Appellate Authority must decide the case on merits without regard to the limitation period; and (iii) all contentions, including the ground of delayed adjudication, remain open for the petitioner to raise before the Appellate Authority.

Source reference: para. 23-24
Jharkhand High Court

Original Court PDF

M/S SUJATA UDIT BUILDERS PRIVATE LIMITED, THROUGH ITS DIRECTOR, MR. SHANKAR KUMAR KUNWARvsCHIEF COMMISSIONER, CENTRAL GOODS AND SERVICE TAXES AND CENTRAL EXCISE , RANCHI ZONE, PATNA

Jharkhand High Court · April 22, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment