01Facts
The Appellants (Promoters) launched a real estate project in Mulund in 2005–2006.
The Respondents (Allottees) booked flats between 2005 and 2007, paying substantial considerations (ranging from 10.6% to 100%)
¶ 10Agreements stipulated possession dates between 2008 and 2010
¶ 10Following significant delays, the Allottees approached the Real Estate Regulatory Authority seeking interest for delayed possession
¶ 3The Competent Authority passed vague directions to "expedite" work without fixing liability
¶ 3On appeal, the Designated Appellate Tribunal (Maharashtra Revenue Tribunal) ordered the Promoter to pay interest @ 10.05% p.a. from 1st February 2014 until actual possession and directed completion within 18 months
¶ 402Issues
i.1. Whether the Maharashtra Revenue Tribunal (MRT) had jurisdiction to adjudicate appeals under RERA after the notification of the permanent Maharashtra Real Estate Appellate Tribunal but before its members took oath
¶ 6, 11ii.2. Whether the composition of a "single-member bench" of the MRT was ultra vires Section 43(3) of RERA
¶ 6, 72iii.3. Whether authorities under RERA can fix a possession date or grant interest if the Agreement for Sale contains force majeure and extension clauses
¶ 6, 100iv.4. Whether the demolition of "Tower C" due to new DCPR 2034 regulations constituted "frustration of contract" under Section 56 of the Contract Act
¶ 13203Law Applied
Section 43 of the RERA, 2016, regarding the "establishment" of the Appellate Tribunal, and Section 43(4) first proviso, which allows "designating" an existing tribunal as a pro-tem arrangement
¶ 14, 20Rule 8 of the Maharashtra Real Estate Appellate Tribunal Rules, 2017, mandating an "Oath of Office" before a member "enters upon office"
¶ 14, 39Section 18 of RERA was applied, establishing an "unqualified right" to interest for delayed possession
¶ 105, 111Newtech Promoters v. State of UP (2021) regarding the retroactive application of RERA
¶ 16Pioneer Urban Land v. Govindan Raghavan (2019) regarding "one-sided" unconscionable contracts
¶ 125Section 56 of the Indian Contract Act and the "multi-factorial approach" from Energy Watchdog v. CERC (2017)
¶ 139, 145Provisions in the judgment · 52 · Linked ones open on LawLens
Real Estate (Regulation and Development) Act, 2016. 39 provisions
Section 1Section 2Section 3Section 4Section 5Section 6Section 7Section 11Section 12Section 13Section 14Section 16Section 17Section 18Section 19Section 20Section 21Section 22Section 31Section 34Section 40Section 43Section 44Section 45Section 46Section 47Section 48Section 53Section 55Section 58Section 59Section 71Section 72Section 79Section 80Section 81Section 84Section 88Section 92Indian Contract Act, 1872 Section 32Section 56
Maharashtra Ownership Flats (Regulation of the promotion of construction, sale, management and transfer) Act, 1963 Section 8
Recovery Of Debts And Bankruptcy Act, 1993 Section 2Section 17Section 18Section 19Section 25Section 30Section 31Section 34
Administrative Tribunals Act, 1985 Section 5
Companies Act, 2013 Section 434
04Reasoning
The Court first resolved the jurisdictional challenge, holding that "establishment" implies a "functional" tribunal; since the permanent members only took oath on 24th December 2018, the MRT (Designated Tribunal) validly held jurisdiction when passing the order on 1st November 2018
¶ 42, 61The court rejected the argument that pro-tem tribunals must match the "two-member bench" composition of a regular RERA tribunal, noting that the first proviso to Section 43(4) allows "any" functioning tribunal to act as the Appellate Tribunal
¶ 88, 93On the merits, the Court held that Section 18 of RERA creates a statutory, unqualified right to interest for delay that cannot be waived by "force majeure" clauses unless the events genuinely beyond control are proved
¶ 111, 116The claim of "frustration" for Tower C was dismissed as "self-induced" and "bad faith," as the Promoter chose to demolish the building to nearly double the number of floors for profit (from 22 to 48) under new regulations, despite retrofitting being a viable, albeit more expensive, option
¶ 148, 15005Holding
The High Court answered all issues in favor of the Respondents and dismissed the 10 Second Appeals
¶ 162It held that the MRT's order was well-reasoned and within jurisdiction
¶ 160The Court affirmed the Allottees' right to interest @ 10.05% from 2014
¶ 121Specifically for Second Appeals 253 and 257 (Tower C), the court found the Promoter had misrepresented facts to the MCGM by promising to safeguard allottee rights merely to obtain higher FSI. Consequently, those two appeals were dismissed with exemplary costs of ₹1,00,000 each, while the other eight appeals were dismissed with costs of ₹10,000 each
¶ 150, 163-164Stay on the judgment was refused
¶ 167Original Court PDF
Runwal Constructions Registered Partnership FirmvsBharat Shah
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
