Facts
The Appellants (Promoters) launched a real estate project in Mulund in 2005–2006.
Source reference: no citationThe Respondents (Allottees) booked flats between 2005 and 2007, paying substantial considerations (ranging from 10.6% to 100%)
Source reference: para. 10Agreements stipulated possession dates between 2008 and 2010
Source reference: para. 10Following significant delays, the Allottees approached the Real Estate Regulatory Authority seeking interest for delayed possession
Source reference: para. 3The Competent Authority passed vague directions to "expedite" work without fixing liability
Source reference: para. 3On appeal, the Designated Appellate Tribunal (Maharashtra Revenue Tribunal) ordered the Promoter to pay interest @ 10.05% p.a. from 1st February 2014 until actual possession and directed completion within 18 months
Source reference: para. 4Issues
1. Whether the Maharashtra Revenue Tribunal (MRT) had jurisdiction to adjudicate appeals under RERA after the notification of the permanent Maharashtra Real Estate Appellate Tribunal but before its members took oath
Source reference: para. 6, 112. Whether the composition of a "single-member bench" of the MRT was ultra vires Section 43(3) of RERA
Source reference: para. 6, 723. Whether authorities under RERA can fix a possession date or grant interest if the Agreement for Sale contains force majeure and extension clauses
Source reference: para. 6, 1004. Whether the demolition of "Tower C" due to new DCPR 2034 regulations constituted "frustration of contract" under Section 56 of the Contract Act
Source reference: para. 132Law Applied
Section 43 of the RERA, 2016, regarding the "establishment" of the Appellate Tribunal, and Section 43(4) first proviso, which allows "designating" an existing tribunal as a pro-tem arrangement
Source reference: para. 14, 20Rule 8 of the Maharashtra Real Estate Appellate Tribunal Rules, 2017, mandating an "Oath of Office" before a member "enters upon office"
Source reference: para. 14, 39Section 18 of RERA was applied, establishing an "unqualified right" to interest for delayed possession
Source reference: para. 105, 111Newtech Promoters v. State of UP (2021) regarding the retroactive application of RERA
Source reference: para. 16Pioneer Urban Land v. Govindan Raghavan (2019) regarding "one-sided" unconscionable contracts
Source reference: para. 125Section 56 of the Indian Contract Act and the "multi-factorial approach" from Energy Watchdog v. CERC (2017)
Source reference: para. 139, 145Reasoning
The Court first resolved the jurisdictional challenge, holding that "establishment" implies a "functional" tribunal; since the permanent members only took oath on 24th December 2018, the MRT (Designated Tribunal) validly held jurisdiction when passing the order on 1st November 2018
Source reference: para. 42, 61The court rejected the argument that pro-tem tribunals must match the "two-member bench" composition of a regular RERA tribunal, noting that the first proviso to Section 43(4) allows "any" functioning tribunal to act as the Appellate Tribunal
Source reference: para. 88, 93On the merits, the Court held that Section 18 of RERA creates a statutory, unqualified right to interest for delay that cannot be waived by "force majeure" clauses unless the events genuinely beyond control are proved
Source reference: para. 111, 116The claim of "frustration" for Tower C was dismissed as "self-induced" and "bad faith," as the Promoter chose to demolish the building to nearly double the number of floors for profit (from 22 to 48) under new regulations, despite retrofitting being a viable, albeit more expensive, option
Source reference: para. 148, 150Holding
The High Court answered all issues in favor of the Respondents and dismissed the 10 Second Appeals
It held that the MRT's order was well-reasoned and within jurisdiction
Source reference: para. 160The Court affirmed the Allottees' right to interest @ 10.05% from 2014
Source reference: para. 121Specifically for Second Appeals 253 and 257 (Tower C), the court found the Promoter had misrepresented facts to the MCGM by promising to safeguard allottee rights merely to obtain higher FSI. Consequently, those two appeals were dismissed with exemplary costs of ₹1,00,000 each, while the other eight appeals were dismissed with costs of ₹10,000 each
Source reference: para. 150, 163-164Stay on the judgment was refused
Source reference: para. 167Original Court PDF
Runwal Constructions Registered Partnership FirmvsBharat Shah
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in