01Facts
The Appellant, Assam Power Distribution Company Ltd. (APDCL), challenged the Central Electricity Regulatory Commission’s (CERC) orders dated 30.03.2017 and 03.05.2017.
p. 2The Respondent No. 1, ONGC Tripura Power Company Ltd. (OTPC), a joint venture primarily owned by ONGC (50%), operates the "Palatana" generating station.
p. 3OTPC sought a relaxation of the Normative Annual Plant Availability Factor (NAPAF) from 85% to 68% for the 2014–19 period, citing acute fuel gas shortages from its supplier, ONGC.
p. 4The CERC partially granted this, relaxing the NAPAF to 76%, thereby allowing OTPC to recover an additional ₹282.43 Crore from beneficiaries.
pp. 4-5APDCL contended that since ONGC is the majority shareholder of OTPC and the sole fuel supplier, any gas shortage was a commercial risk that OTPC should have addressed via Liquidated Damages (LD) under its Gas Sale & Purchase Agreement (GSPA) rather than passing the cost to consumers.
pp. 5-602Issues
i.1. Whether the CERC was justified in exercising its power to relax operational norms (NAPAF) under Regulation 54 of the 2014 Tariff Regulations due to fuel shortages.
p. 4 · ¶ 8ii.2. Whether the fuel shortage constituted a valid "Force Majeure" event under the GSPA, exempting the generator from its primary obligation to arrange fuel.
p. 6 · ¶ 13 · p. 16 · ¶ 31iii.3. Whether OTPC’s failure to invoke the penalty/Liquidated Damages clauses against its supplier (ONGC) precluded it from seeking tariff relaxation from the Commission.
p. 22 · ¶ 40-4103Law Applied
The responsibility for procurement of primary fuel rests solely with the generating company and cannot be shifted to beneficiaries, as established in NTPC Limited v. CERC & Ors. (Appeal No. 110 of 2012).
p. 7, 18A company and its shareholders are distinct legal entities (doctrine of corporate veil).
p. 12 · ¶ 26Mandatory contractual notice requirements are a condition precedent for relief under Force Majeure clauses, as per Maruti Clean Coal and Power Limited v. PGCIL.
p. 22 · ¶ 40Relaxation under Regulation 54 (Power to Relax) of the CERC 2014 Tariff Regulations cannot be granted to cover a generator’s failure to enforce its own contractual remedies.
pp. 22-23Provisions in the judgment · 2 · Linked ones open on LawLens
Electricity Act, 2003 Section 111
Code of Civil Procedure, 1908 Section 41
04Reasoning
OTPC and ONGC are distinct legal entities, and ONGC’s 50% shareholding does not exempt OTPC from enforcing its rights under the GSPA.
¶ 26-27The GSPA (Clause 15) contained specific provisions for Liquidated Damages in the event of a supply shortfall.
¶ 31OTPC failed to provide the mandatory 48-hour notice required by Clause 17.3 to claim a Force Majeure event under Clause 17.1(c).
¶ 31, 40By seeking NAPAF relaxation instead of claiming LD from ONGC, OTPC effectively passed the financial burden of the fuel supplier’s default onto the consumers.
¶ 41Clause 14.3 (pro-rata supply) did not override the obligation to pay LD under Clause 15.
¶ 42The CERC erred in granting relaxation for a situation that was within the commercial and contractual control of the generator.
¶ 39, 4105Holding
The Tribunal allowed the appeal and set aside the CERC’s Order dated 30.03.2017 and the Corrigendum dated 03.05.2017 regarding the relaxation of NAPAF from 85% to 76%.
¶ 43OTPC failed to exercise its contractual remedies against its fuel supplier and could not shift the resulting financial loss to the beneficiaries.
¶ 41-43All consequential calculations based on the relaxed NAPAF were annulled.
¶ 43Original Court PDF
ASSAM POWER DISTRIBUTION COMPANY LTD.vsONGC TRIPURA POWER COMPANY LIMITED & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
