APTEL

Generators cannot seek normative parameter relaxation without first enforcing contractual remedies against defaulting fuel suppliers.

ASSAM POWER DISTRIBUTION COMPANY LTD. vs ONGC TRIPURA POWER COMPANY LIMITED & Ors

APTELJUDGMENT: April 06, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant, Assam Power Distribution Company Ltd. (APDCL), challenged the Central Electricity Regulatory Commission’s (CERC) orders dated 30.03.2017 and 03.05.2017.

Source reference: p. 2

The Respondent No. 1, ONGC Tripura Power Company Ltd. (OTPC), a joint venture primarily owned by ONGC (50%), operates the "Palatana" generating station.

Source reference: p. 3

OTPC sought a relaxation of the Normative Annual Plant Availability Factor (NAPAF) from 85% to 68% for the 2014–19 period, citing acute fuel gas shortages from its supplier, ONGC.

Source reference: p. 4

The CERC partially granted this, relaxing the NAPAF to 76%, thereby allowing OTPC to recover an additional ₹282.43 Crore from beneficiaries.

Source reference: p. 4-5

APDCL contended that since ONGC is the majority shareholder of OTPC and the sole fuel supplier, any gas shortage was a commercial risk that OTPC should have addressed via Liquidated Damages (LD) under its Gas Sale & Purchase Agreement (GSPA) rather than passing the cost to consumers.

Source reference: p. 5-6
02

Issues

1. Whether the CERC was justified in exercising its power to relax operational norms (NAPAF) under Regulation 54 of the 2014 Tariff Regulations due to fuel shortages.

Source reference: p. 4, para. 8

2. Whether the fuel shortage constituted a valid "Force Majeure" event under the GSPA, exempting the generator from its primary obligation to arrange fuel.

Source reference: p. 6, para. 13; p. 16, para. 31

3. Whether OTPC’s failure to invoke the penalty/Liquidated Damages clauses against its supplier (ONGC) precluded it from seeking tariff relaxation from the Commission.

Source reference: p. 22, para. 40-41
03

Law Applied

The responsibility for procurement of primary fuel rests solely with the generating company and cannot be shifted to beneficiaries, as established in NTPC Limited v. CERC & Ors. (Appeal No. 110 of 2012).

Source reference: p. 7, 18

A company and its shareholders are distinct legal entities (doctrine of corporate veil).

Source reference: p. 12, para. 26

Mandatory contractual notice requirements are a condition precedent for relief under Force Majeure clauses, as per Maruti Clean Coal and Power Limited v. PGCIL.

Source reference: p. 22, para. 40

Relaxation under Regulation 54 (Power to Relax) of the CERC 2014 Tariff Regulations cannot be granted to cover a generator’s failure to enforce its own contractual remedies.

Source reference: p. 22-23
04

Reasoning

OTPC and ONGC are distinct legal entities, and ONGC’s 50% shareholding does not exempt OTPC from enforcing its rights under the GSPA.

Source reference: para. 26-27

The GSPA (Clause 15) contained specific provisions for Liquidated Damages in the event of a supply shortfall.

Source reference: para. 31

OTPC failed to provide the mandatory 48-hour notice required by Clause 17.3 to claim a Force Majeure event under Clause 17.1(c).

Source reference: para. 31, 40

By seeking NAPAF relaxation instead of claiming LD from ONGC, OTPC effectively passed the financial burden of the fuel supplier’s default onto the consumers.

Source reference: para. 41

Clause 14.3 (pro-rata supply) did not override the obligation to pay LD under Clause 15.

Source reference: para. 42

The CERC erred in granting relaxation for a situation that was within the commercial and contractual control of the generator.

Source reference: para. 39, 41
05

Holding

The Tribunal allowed the appeal and set aside the CERC’s Order dated 30.03.2017 and the Corrigendum dated 03.05.2017 regarding the relaxation of NAPAF from 85% to 76%.

OTPC failed to exercise its contractual remedies against its fuel supplier and could not shift the resulting financial loss to the beneficiaries.

Source reference: para. 41-43

All consequential calculations based on the relaxed NAPAF were annulled.

Source reference: para. 43
APTEL

Original Court PDF

ASSAM POWER DISTRIBUTION COMPANY LTD.vsONGC TRIPURA POWER COMPANY LIMITED & Ors

APTEL · April 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment