Facts
The Appellant, Assam Power Distribution Company Ltd. (APDCL), challenged the Central Electricity Regulatory Commission’s (CERC) orders dated 30.03.2017 and 03.05.2017.
Source reference: p. 2The Respondent No. 1, ONGC Tripura Power Company Ltd. (OTPC), a joint venture primarily owned by ONGC (50%), operates the "Palatana" generating station.
Source reference: p. 3OTPC sought a relaxation of the Normative Annual Plant Availability Factor (NAPAF) from 85% to 68% for the 2014–19 period, citing acute fuel gas shortages from its supplier, ONGC.
Source reference: p. 4The CERC partially granted this, relaxing the NAPAF to 76%, thereby allowing OTPC to recover an additional ₹282.43 Crore from beneficiaries.
Source reference: p. 4-5APDCL contended that since ONGC is the majority shareholder of OTPC and the sole fuel supplier, any gas shortage was a commercial risk that OTPC should have addressed via Liquidated Damages (LD) under its Gas Sale & Purchase Agreement (GSPA) rather than passing the cost to consumers.
Source reference: p. 5-6Issues
1. Whether the CERC was justified in exercising its power to relax operational norms (NAPAF) under Regulation 54 of the 2014 Tariff Regulations due to fuel shortages.
Source reference: p. 4, para. 82. Whether the fuel shortage constituted a valid "Force Majeure" event under the GSPA, exempting the generator from its primary obligation to arrange fuel.
Source reference: p. 6, para. 13; p. 16, para. 313. Whether OTPC’s failure to invoke the penalty/Liquidated Damages clauses against its supplier (ONGC) precluded it from seeking tariff relaxation from the Commission.
Source reference: p. 22, para. 40-41Law Applied
The responsibility for procurement of primary fuel rests solely with the generating company and cannot be shifted to beneficiaries, as established in NTPC Limited v. CERC & Ors. (Appeal No. 110 of 2012).
Source reference: p. 7, 18A company and its shareholders are distinct legal entities (doctrine of corporate veil).
Source reference: p. 12, para. 26Mandatory contractual notice requirements are a condition precedent for relief under Force Majeure clauses, as per Maruti Clean Coal and Power Limited v. PGCIL.
Source reference: p. 22, para. 40Relaxation under Regulation 54 (Power to Relax) of the CERC 2014 Tariff Regulations cannot be granted to cover a generator’s failure to enforce its own contractual remedies.
Source reference: p. 22-23Reasoning
OTPC and ONGC are distinct legal entities, and ONGC’s 50% shareholding does not exempt OTPC from enforcing its rights under the GSPA.
Source reference: para. 26-27The GSPA (Clause 15) contained specific provisions for Liquidated Damages in the event of a supply shortfall.
Source reference: para. 31OTPC failed to provide the mandatory 48-hour notice required by Clause 17.3 to claim a Force Majeure event under Clause 17.1(c).
Source reference: para. 31, 40By seeking NAPAF relaxation instead of claiming LD from ONGC, OTPC effectively passed the financial burden of the fuel supplier’s default onto the consumers.
Source reference: para. 41Clause 14.3 (pro-rata supply) did not override the obligation to pay LD under Clause 15.
Source reference: para. 42The CERC erred in granting relaxation for a situation that was within the commercial and contractual control of the generator.
Source reference: para. 39, 41Holding
The Tribunal allowed the appeal and set aside the CERC’s Order dated 30.03.2017 and the Corrigendum dated 03.05.2017 regarding the relaxation of NAPAF from 85% to 76%.
OTPC failed to exercise its contractual remedies against its fuel supplier and could not shift the resulting financial loss to the beneficiaries.
Source reference: para. 41-43All consequential calculations based on the relaxed NAPAF were annulled.
Source reference: para. 43Original Court PDF
ASSAM POWER DISTRIBUTION COMPANY LTD.vsONGC TRIPURA POWER COMPANY LIMITED & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in