Facts
The Petitioner, an empanelled agency, participated in an Expression of Interest (EOI) issued by the Bihar Renewable Energy Development Agency (BREDA) for the installation of Grid Connected Rooftop Solar Power Plants
Source reference: p. 2-3Following a Letter of Intent dated 10.02.2025 and an agreement signed on 17.02.2025, the Petitioner was allotted specific districts and directed to conduct site surveys
Source reference: p. 3However, on 18.09.2025, BREDA issued a cancellation notice for the entire EOI citing "unavoidable circumstances"
Source reference: p. 3-4The Petitioner challenged this cancellation, alleging it was arbitrary, violated principles of natural justice, and that a concluded contract had already been formed
Source reference: p. 4The Respondents contended that the cancellation was a policy decision necessitated by the lack of administrative approval for enhanced project capacity and the absence of sanctioned funds
Source reference: p. 5Issues
1. Whether the cancellation of the EOI was legally sustainable under the reserved powers of the tender document after the execution of an agreement
Source reference: para. 162. Whether the Petitioner acquired a vested or indefeasible right to execute the work in the absence of a specific work order
Source reference: para. 23Law Applied
The Court primarily applied the principle that a bidder in a tender process has a right to fair treatment but no vested right to the award or completion of a contract
Source reference: para. 24It relied on the precedent of Maa Binda Express Carrier & Anr. v. North-East Frontier Railway & Ors. (2014) 3 SCC 760, which establishes that a tender is merely an offer and judicial review is limited unless the process is found to be "tailor-made" or arbitrary
Source reference: para. 24Furthermore, the court applied the principle of contractual autonomy, whereby parties are bound by the specific terms of the EOI, including clauses that allow for cancellation without assigning reasons
Source reference: para. 18-19Reasoning
The Court reasoned that Clauses 3.15 and 3.15.1 of the EOI explicitly empowered BREDA to cancel the process at any stage without liability; since the Petitioner participated with full knowledge of these terms, they were bound by them
Source reference: para. 18-19The Court found that although an agreement was signed, Article 7.0 stipulated that the work was only triggered by a "particular work order," which was never issued
Source reference: para. 22-23Regarding the allegation of arbitrariness, the Court observed that the Respondents provided a rational basis for the cancellation—namely, the failure to obtain financial sanction from the Energy Department—and noted that the decision was applied uniformly to all agencies, not just the Petitioner
Source reference: para. 20-21, 26Consequently, the doctrine of legitimate expectation could not override express contractual stipulations or the State's administrative exigencies
Source reference: para. 25Holding
The Court held that the cancellation was neither arbitrary nor illegal as it was based on bona fide administrative and financial constraints and was consistent with the rights reserved in the EOI
The writ application was dismissed. However, the Court granted the Petitioner liberty to pursue claims for expenditures incurred during site surveys before a competent civil court
Source reference: para. 28, 30Original Court PDF
M/s Energy United India Private Limited,vsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in