Patna High Court

Government Retains Express Power to Cancel Tender Process Post-Agreement Absent Issuance of Specific Work Orders

M/s Energy United India Private Limited, vs The State of Bihar

Patna High CourtJUDGMENT: June 17, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, an empanelled agency, participated in an Expression of Interest (EOI) issued by the Bihar Renewable Energy Development Agency (BREDA) for the installation of Grid Connected Rooftop Solar Power Plants

Source reference: p. 2-3

Following a Letter of Intent dated 10.02.2025 and an agreement signed on 17.02.2025, the Petitioner was allotted specific districts and directed to conduct site surveys

Source reference: p. 3

However, on 18.09.2025, BREDA issued a cancellation notice for the entire EOI citing "unavoidable circumstances"

Source reference: p. 3-4

The Petitioner challenged this cancellation, alleging it was arbitrary, violated principles of natural justice, and that a concluded contract had already been formed

Source reference: p. 4

The Respondents contended that the cancellation was a policy decision necessitated by the lack of administrative approval for enhanced project capacity and the absence of sanctioned funds

Source reference: p. 5
02

Issues

1. Whether the cancellation of the EOI was legally sustainable under the reserved powers of the tender document after the execution of an agreement

Source reference: para. 16

2. Whether the Petitioner acquired a vested or indefeasible right to execute the work in the absence of a specific work order

Source reference: para. 23
03

Law Applied

The Court primarily applied the principle that a bidder in a tender process has a right to fair treatment but no vested right to the award or completion of a contract

Source reference: para. 24

It relied on the precedent of Maa Binda Express Carrier & Anr. v. North-East Frontier Railway & Ors. (2014) 3 SCC 760, which establishes that a tender is merely an offer and judicial review is limited unless the process is found to be "tailor-made" or arbitrary

Source reference: para. 24

Furthermore, the court applied the principle of contractual autonomy, whereby parties are bound by the specific terms of the EOI, including clauses that allow for cancellation without assigning reasons

Source reference: para. 18-19
04

Reasoning

The Court reasoned that Clauses 3.15 and 3.15.1 of the EOI explicitly empowered BREDA to cancel the process at any stage without liability; since the Petitioner participated with full knowledge of these terms, they were bound by them

Source reference: para. 18-19

The Court found that although an agreement was signed, Article 7.0 stipulated that the work was only triggered by a "particular work order," which was never issued

Source reference: para. 22-23

Regarding the allegation of arbitrariness, the Court observed that the Respondents provided a rational basis for the cancellation—namely, the failure to obtain financial sanction from the Energy Department—and noted that the decision was applied uniformly to all agencies, not just the Petitioner

Source reference: para. 20-21, 26

Consequently, the doctrine of legitimate expectation could not override express contractual stipulations or the State's administrative exigencies

Source reference: para. 25
05

Holding

The Court held that the cancellation was neither arbitrary nor illegal as it was based on bona fide administrative and financial constraints and was consistent with the rights reserved in the EOI

The writ application was dismissed. However, the Court granted the Petitioner liberty to pursue claims for expenditures incurred during site surveys before a competent civil court

Source reference: para. 28, 30
Patna High Court

Original Court PDF

M/s Energy United India Private Limited,vsThe State of Bihar

Patna High Court · June 17, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment